UNITED STATES FIDELITY AND GUARANTY COMPANY, Respondent-Appellant, v DELMAR DEVELOPMENT PARTNERS, LLC, Appellant-Respondent.
Supreme Court, Appellate Division, Third Department, New York
803 N.Y.S.2d 254
By a standardized American Institute of Architects agreement—with insertions and modifications—executed in August 1999, defendant hired Matzen Construction, Inc. to construct a luxury apartment complex in the Town of Bethlehem, Albany County. The initial agreement was amended by a letter agreement executed by the parties in July 2001. Plaintiff, as surety for Matzen, commenced this action in October 2002 to recover payment in accordance with the terms of the amended agreement. Pursuant to a stipulation by the parties, defendant moved for partial summary judgment on the sole issue of whether the amendment to the agreement was enforceable. As a result, Supreme Court rendered a decision, affirmed by this Court, that the July 2001 letter agreement is enforceable (United States Fid. & Guar. Co. v Delmar Dev. Partners, LLC, 14 AD3d 836 [2005]).
We turn first to Supreme Court‘s partial denial of defendant‘s motion to amend its answer, a decision “committed to the court‘s discretion” (Edenwald Contr. Co. v City of New York, 60 NY2d 957, 959 [1983]). “Provided that there is no prejudice to the nonmoving party and the amendment is not plainly lacking in merit, leave to amend pleadings under
We also reject plaintiff‘s alternative arguments to preclude defendant from asserting that the amended agreement was induced by fraud. Although the issue of the enforceability of the amendment to the agreement has already been litigated—a fact which, under other circumstances, would preclude revisiting the issue—here defendant specifically reserved its right to assert the defense of fraud in the inducement in its motion papers seeking partial summary judgment. Also, contrary to plaintiff‘s assertion, we find that the proposed amendment is pleaded with sufficient particularity to satisfy
Next, we conclude that Supreme Court appropriately granted defendant‘s request to add a counterclaim for breach of contract and liquidated damages, while limiting any remedy thereunder to the amount demanded by plaintiff in the complaint. “It is axiomatic that claims and defenses that arise out of the same transaction as a claim asserted in the complaint are not barred by the statute of limitations, even though an independent action by defendant might have been time-barred at the time the action was commenced” (Bloomfield v Bloomfield, 97 NY2d 188, 193 [2001], citing
Finally, we find that Supreme Court properly denied plaintiff‘s motion for summary judgment. Notwithstanding plaintiff‘s assertions that the work was substantially complete—as that term is defined in the contract—prior to the September 30, 2001 completion date designated in the amended contract and that defendant‘s complaints regarding the pool, roof and punch list items are either outside the scope of the contract or de minimis, our review of this record reveals that these issues cannot be resolved at this juncture as a matter of law (see Trustees of Columbia Univ. in City of N.Y. v Gwathmey Siegel & Assoc. Architects, 167 AD2d 6, 12 [1991]; cf. State of New York v Lundin, 91 AD2d 343, 346-347 [1983], affd 60 NY2d 987 [1983]). Likewise, we reject plaintiff‘s argument that defendant waived
We also reject plaintiff‘s contention that defendant‘s pleadings fell short of the particularity required by
Mercure, J.P., Peters, Mugglin and Rose, JJ., concur. Ordered that the order is modified, on the law, without costs, by reversing so much thereof as partially denied defendant‘s motion for leave to serve an amended answer; motion granted to that extent; and, as so modified, affirmed.
