In 1980, the plaintiff was the successful bidder on a contract to improve the public address system in 112 New York City subway stations. Pursuant to the contract, which was awarded by the defendant City of New York (hereinafter the City), the plaintiff was to be paid $5,774,000. By January 31, 1986, the work was substantially complete. However, when the parties were unable to resolve various disputes that arose concerning the contract, the plaintiff, by summons and complaint dated October 28, 1987, commenced this action. The plaintiff alleged (1) that it was owed a balance of $41,381.68 on the contract; (2) that it performed "additional work” on the contract in the sum of $1,609,814.70; (3) that it sustained damages in the sum of $5,811,781.92 due to the City’s misrepresentation of material facts and the City’s "wrongful!], deliberate!] and/or negli
As a counterclaim and complete defense to this action, the City alleges that the plaintiff obtained the contract at issue in violation of General Municipal Law § 103. Accordingly, the City argues, the plaintiff should suffer the same harsh penalties imposed upon bidders that obtain public contracts by, inter alia, collusion, fraud, or circumvention of the competitive bidding process (see, D’Angelo v Cole,
Pursuant to General Municipal Law § 103, contracts for public work involving an expenditure of more than $7,000 (currently $20,000), with certain exceptions not here applicable, must be awarded to the "lowest responsible bidder” after public bidding (see, General Municipal Law § 103 [1]). Pursuant to the invitation to bid on the contract at issue, one requirement of a "responsible bidder” was that it possess "free and liquid assets equal to at least thirteen (13) per centum of the total amount of the Total Aggregate Bid”. A corporate bidder was
The City argues that the deposition testimony of Stuart Freeman, who became president of the plaintiff after the bid at issue had already been made, supports a conclusion that the net worth of the plaintiff in 1980 was between $0 and a deficit of $10,321,000. However, we do not find Freeman’s testimony on this issue to be as clear as claimed by the City. Moreover, even if Freeman’s testimony supported such a conclusion, it is hearsay. Freeman admitted that he had no personal knowledge of the facts and that he did not speak to any of the parties allegedly involved in the falsification of the plaintiff’s books. Indeed, the source of Freeman’s knowledge is not clear from the record. Thus, the Supreme Court did not err in denying the City’s motion for summary judgment on the first counterclaim of its amended answer.
The plaintiff argues that the City’s first counterclaim should be dismissed because it is barred by the six-year Statute of Limitations for fraud (see, CPLR 213 [8]). However, even assuming, arguendo, that the counterclaim may be properly characterized as one sounding in fraud, a question of fact exists as to the date that the City did or should have discovered the alleged fraud (see, CPLR 213 [8]). In addition, to the extent that the first counterclaim is interposed to offset any claims by the plaintiff under the contract, the Statute of Limitations is not a bar to recovery (see, CPLR 203 [c]; Matter of Fisher Park Lane Co. [SCM Corp.],
As a complete defense to the second, third, and fourth causes of action in the complaint, the City alleged that the plaintiff failed to comply with the notice provisions of the contract. Pursuant to Chapter III, Article VII, Paragraph (y) of the contract: "If the Contractor shall claim compensation for any damage sustained by reason of any act, neglect, fault or default of the City or the Authority or their agents, he shall within
In response to interrogatories served by the City concerning notice, the plaintiff submitted documentary evidence falling generally into three categories. The first was numerous letters from one of its subcontractors to the City giving notice of various damages sustained during construction. The City has failed to proffer evidence sufficient to support a prima facie showing that such notice was inadequate under the contract. Contrary to the City’s arguments on appeal, we attach no relevant significance to the fact that the alleged notice was supplied by a subcontractor of the plaintiff rather than by the plaintiff directly. The second category of documents submitted by the plaintiff consisted of several internal memoranda of the City recounting discussions and agreements between the parties concerning, inter alia, the performance of additional work and the price to be paid therefor. Whether these memoranda are evidence of either affirmative exercises by the City of its discretion under the contract to excuse the failure to provide written notice of damages or fully negotiated and authorized directives for additional work is a question of fact to be resolved at trial. The final category of documents submitted by the plaintiff consisted of several memoranda from the City to the plaintiff, inter alia, directing it to perform certain additional work and setting forth the price to be paid therefor. We find that these affirmative directives concerning negotiated and agreed to
The City also sought partial summary judgment dismissing all of the plaintiff’s causes of action to recover damages for work performed or damages incurred subsequent to May 1, 1982. This argument is based on the City’s assertion that, as of that date, the plaintiff assigned all of its rights and interest in the contract to a third party, the National Mansfield Corporation (see, McKinney & Son v Lake Placid 1980 Olympic Games,
Finally, the plaintiff argues that the court improvidently exercised its discretion in permitting the City to amend its answer because, inter alia, none of the defenses or counterclaims has merit. However, the arguments proffered by the plaintiff do not support a finding that the additional defenses and counterclaims are "patently insufficient on [their] face”
