THE STATE EX REL. AMERICAN SUBCONTRACTORS ASSOCIATION, INC. ET AL. v. OHIO STATE UNIVERSITY
No. 2010-2059
Supreme Court of Ohio
Submitted May 10, 2011-Decided June 21, 2011
129 Ohio St.3d 111, 2011-Ohio-2881
Juvenile Law Center, Marsha L. Levick, Lourdes M. Rosado, Jessica R. Feierman, and Riya S. Shah; National Center for Lesbian Rights, Jody Marksamer, and Ilona Turner; and Nadia Natasha Seeratan, urging reversal for amici curiae Juvenile Law Center; National Juvenile Defender Center; National Center for Lesbian Rights; Barton Child Law and Policy Center, Emory School of Law; Children and Family Justice Center, Bluhm Legal Clinic; Juvenile Justice Initiative of Illinois; Midwest Juvenile Defender Center; Tamar Birkhead; Jeffrey Fagan; Therese Glennon; Martin Guggenheim; Barry Krisberg; Elizabeth Letourneau; and Gail Ryan.
Joseph T. Deters, Hamilton County Prosecuting Attorney, and Phillip R. Cummings, Assistant Prosecuting Attorney, urging affirmance for amicus curiae Ohio Prosecuting Attorneys Association.
Per Curiam.
{¶ 1} This is an original action for a writ of mandamus to compel respondent, Ohio State University, to require that a bond be furnished by Turner Construction Company as construction manager at risk for a construction project. Because relators are not entitled to the requested extraordinary relief, we deny the writ.
Facts
{¶ 2} In 2005, Ohio State began work on a $1 billion expansion of its Medical Center, which has been referred to as “ProjectOne.” In February 2009, Ohio State entered into an agreement for construction-management services with Turner on the project. Construction work on the project began in the fall of 2009 and is scheduled to be completed in 2014.
{¶ 3} Under the usual construction method, public institutions of higher education like Ohio State would be required to employ multiple prime contractors for constructing, renovating, or improving capital facilities. That method would require Ohio State to first engage a company to design the project and then seek bids from contractors to do the construction and would prohibit having one prime contractor holding all trade contracts for a project. It is alleged that the multiple-prime-contractor system has resulted in delays and increased costs.
{¶ 4} In December 2009, the General Assembly enacted Section 8 of Sub.H.B. No. 318 (“H.B. 318“), a temporary uncodified law that directed the chancellor of the Ohio Board of Regents to designate during 2010 one construction project at each of three different state institutions of higher education as a Construction Reform Demonstration Project. The purpose of the law was to test alternative methods of securing public construction projects to determine whether they would afford greater flexibility in increasing efficiency and lowering costs.
{¶ 5} Pursuant to H.B. 318, Ohio State requested that the Ohio Board of Regents designate certain core phases of the overall project as a Construction Reform Demonstration Project. On March 24, 2010, the chancellor designated portions of the project as a Construction Reform Demonstration Project, and on April 5, 2010, the Ohio Controlling Board approved the designation. The core phases of the project encompassed in the designation are (1) constructing a new cancer and critical-care tower, (2) relocating and upgrading infrastructure and roadways, (3) upgrading current space in existing Medical Center facilities, (4) landscaping and urban planning, (5) demolishing Cramblett Hall, and (6) constructing a chiller plant, with the estimated cost of these phases being $658.3 million.
{¶ 6} One of the specified alternative methods of construction delivery authorized by Section 8 of H.B. 318 is designated “construction manager at risk.” On July 8, 2010, Ohio State entered into a construction-manager-at-risk agreement with Turner for the project. Ohio State selected Turner to serve as construction manager at risk through a qualifications-based selection process. This process differed from traditional competitive bidding, which requires selection of a contractor based on the lowest responsive and responsible bidder.
{¶ 7} Ohio State did not require Turner to furnish a surety bond to secure the performance of Turner and its subcontractors. Requiring Turner to provide a
{¶ 8} Relators American Subcontractors Association (“ASA“) and American Subcontractors Association of Ohio, Inc. (“ASA-Ohio“) are trade associations of suppliers who work primarily as subcontractors on construction projects. Their purpose is to protect and advance the interests of subcontractors and suppliers, including those in Ohio. Relator Surety and Fidelity Association of America (“SFAA“) is a national trade association of companies licensed to write fidelity and surety bonds and comprises 451 members, including 33 members with their principal places of business in Ohio. SFAA‘s purpose is to protect and advance the interests of sureties in the nation and in Ohio.
{¶ 9} On November 30, 2010, relators filed this action for a writ of mandamus to compel Ohio State to require that Turner furnish a bond as construction manager at risk. After Ohio State filed an answer, we granted an alternative writ. 127 Ohio St.3d 1530, 2011-Ohio-376, 940 N.E.2d 984. The parties submitted briefs and evidence.
{¶ 10} This cause is now before the court for our consideration of relators’ mandamus claim.
Legal Analysis
Standing
{¶ 11} Ohio State asserts that relators lack standing to institute this mandamus action. “A preliminary inquiry in all legal claims is the issue of standing.” Cuyahoga Cty. Bd. of Commrs. v. State, 112 Ohio St.3d 59, 2006-Ohio-6499, 858 N.E.2d 330, ¶ 22. “Before an Ohio court can consider the merits of a legal claim, the person or entity seeking relief must establish standing to sue.” Ohio Pyro, Inc. v. Ohio Dept. of Commerce, 115 Ohio St.3d 375, 2007-Ohio-5024, 875 N.E.2d 550, ¶ 27. “[T]he question of standing depends upon whether the party has alleged such a ‘personal stake in the outcome of the controversy * * *’ as to ensure that ‘the dispute sought to be adjudicated will be presented in an adversary context and in a form historically viewed as capable of judicial resolution.‘” State ex rel. Dallman v. Franklin Cty. Court of Common Pleas (1973), 35 Ohio St.2d 176, 178-179, 64 O.O.2d 103, 298 N.E.2d 515, quoting Club v. Morton” cite=“405 U.S. 727” pinpoint=“732” court=“U.S.” date=“1972“>Sierra Club v. Morton (1972), 405 U.S. 727, 732, 92 S.Ct. 1361, 31 L.Ed.2d 636, quoting Baker v. Carr (1962), 369 U.S. 186, 204, 82 S.Ct. 691, 7 L.Ed.2d 663, and Flast v. Cohen (1968), 392 U.S. 83, 101, 88 S.Ct. 1942, 20 L.Ed.2d 947.
{¶ 12} “[A]n association has standing on behalf of its members when ‘(a) its members would otherwise have standing to sue in their own right; (b) the interests it seeks to protect are germane to the organization‘s purpose; and (c) neither the claim asserted nor the relief requested requires the participation of individual members in the lawsuit.‘” Ohio Contractors Assn. v. Bicking (1994), 71 Ohio St.3d 318, 320, 643 N.E.2d 1088, quoting Hunt v. Washington State Apple Advertising Comm. (1977), 432 U.S. 333, 343, 97 S.Ct. 2434, 53 L.Ed.2d 383; see also Ohio Hosp. Assn. v. Community Mut. Ins. Co. (1987), 31 Ohio St.3d 215, 218, 31 OBR 411, 509 N.E.2d 1263. We have emphasized that “to have standing, the association must establish that its members have suffered actual injury.” Bicking, 71 Ohio St.3d at 320. At least one of the members of the association must be actually injured. See, e.g., Warth v. Seldin (1975), 422 U.S. 490, 511, 95 S.Ct. 2197, 45 L.Ed.2d 343; Ohio Licensed Beverage Assn. v. Ohio Dept. of Health, Franklin App. No. 07AP-490, 2007-Ohio-7147, 2007 WL 4564391, ¶ 21. “[T]he injury must be concrete and not simply abstract or suspected.” Bicking at 320.
{¶ 13} ASA and ASA-Ohio claim that their members have been injured in two distinct ways caused by the lack of a bond provided by Turner on the project: (1) lost business opportunity for those members who decline to provide labor and material for the project and (2) increased risk of loss and potential default in other areas of business for those members who provide labor and material for the project without the guarantee of payment under a bond.
{¶ 14} They have not supported these claims, however, with any credible evidence. All subcontractors working on the project have been timely paid. No subcontractor working on the project has complained to Ohio State or Turner about the lack of a bond, and the bidding for work on the project by subcontractors has been at the expected level. The evidence shows that Turner has finished many construction projects for Ohio State and has completed many of them without a surety bond, and the construction-manager-at-risk agreement has multiple safeguards to ensure that subcontractors are timely paid for their performance of services and provision of materials.
{¶ 15} In fact, if Ohio State had requested that Turner furnish a bond, Turner would have required bonds from its subcontractors, which might have inhibited EDGE-certified subcontractors from bidding. See
{¶ 17} Conversely, SFAA has established that at least one of its members is actually injured by the lack of a surety bond provided by Turner. Turner has a multisurety agreement with five companies that have agreed to provide performance and payment bonds to Turner when a bond is required for a project. SFAA is a trade association of these bond companies, and relators have established by affidavit that each of these sureties is a member of SFAA. Ohio State concedes that “these companies stand to lose the profit they would have earned-a handsome profit no doubt-on any bond Ohio State required from Turner.”
{¶ 18} Because these SFAA members would otherwise have standing to sue in their own right, because the interests SFAA seeks to protect are germane to its organizational purpose of advancing sureties’ interests, and because the individual sureties’ participation is not required for this mandamus case, SFAA has established that it possesses the requisite standing to raise the mandamus claim. Bicking, 71 Ohio St.3d at 320.
{¶ 19} Therefore, we dismiss ASA‘s and ASA-Ohio‘s claims for lack of standing and proceed to address the merits of SFAA‘s mandamus claim.
Mandamus
{¶ 20} SFAA requests a writ of mandamus to compel Ohio State to require Turner to furnish a surety bond for its position as construction manager at risk. To be entitled to the writ, SFAA must establish a clear legal right to the requested relief, a corresponding clear legal duty on the part of Ohio State to provide it, and the lack of an adequate remedy in the ordinary course of the law. State ex rel. Am. Civ. Liberties Union of Ohio, Inc. v. Cuyahoga Cty. Bd. of Commrs., 128 Ohio St.3d 256, 2011-Ohio-625, 943 N.E.2d 553, ¶ 22.
{¶ 21} SFAA bases its entitlement to the writ on Section 8 of H.B. 318 and
{¶ 22} “For purposes of this section, ‘construction manager at risk’ means a person with substantial discretion and authority to plan, coordinate, manage, direct, and construct all phases of a project for the construction, demolition, alteration, repair, or reconstruction of any public building, structure, or other improvement and who provides the state institution of higher education a guaranteed maximum price utilizing an open book pricing method, wherein the construction manager at risk provides the state institution of higher education all books, records, documents, and other data in its possession related to itself, its subcontractors, and material suppliers pertaining to the bidding, pricing, or performance of a construction management contract. The construction manager at risk shall be selected using a qualifications based selection process, including best value criteria. ‘Best value criteria’ includes technical design, technical approach, quality of proposed personnel, management plan, or other factors that are determined to derive or offer the greatest value to the state institution of higher education.”
{¶ 23} Pursuant to Section 8 of H.B. 318, certain core phases of ProjectOne were designated as a Construction Reform Demonstration Project, and Ohio State used the required qualifications-based selections process to choose Turner as the construction manager at risk on the project. Section 8(C)(2) states:
{¶ 24} “In developing their Construction Demonstration Reform Projects, the state institutions of higher education are not exempt from the applicable provisions of law concerning any of the following:
{¶ 25} “* * *
{¶ 26} “(b) Bonding.”
{¶ 27} SFAA claims that
{¶ 28} “(A) Each person bidding for a contract with the state or any political subdivision, district, institution, or other agency thereof, excluding therefrom the department of transportation, for any public improvement shall file with the bid, a bid guaranty in the form of either:
{¶ 29} “(1) A bond in accordance with division (B) of this section for the full amount of the bid;
{¶ 30} “(2) A certified check, cashier‘s check, or letter of credit pursuant to
* * *
{¶ 32} “(1) Provide that, if the bid is accepted, the bidder, after the awarding or the recommendation for the award of the contract, whichever the contracting authority designates, will enter into a proper contract in accordance with the bid, plans, details, specifications, and bills of material. * * *
{¶ 33} “* * *”
{¶ 34} “(C)(1) A bid guaranty filed pursuant to division (A)(2) of this section shall be conditioned to provide that if the bid is accepted, the bidder, after the awarding or the recommendation for the award of the contract, whichever the contracting authority designates, will enter into a proper contract in accordance with the bid, plans, details, specifications, and bills of material. * * *
{¶ 35} “If the bidder enters into the contract, the bidder, at the time the contract is entered to [sic], shall file a bond for the amount of the contract to indemnify the state, political subdivision, district, institution, or agency against all damage suffered by failure to perform the contract according to its provisions and in accordance with the plans, details, specifications, and bills of material therefor and to pay all lawful claims of subcontractors, material suppliers, and laborers for labor performed or material furnished in carrying forward, performing, or completing the contract * * *.
{¶ 36} “(2) A construction manager who enters into a contract pursuant to
{¶ 37} In determining whether
{¶ 38} The plain language of
{¶ 39} But “[u]nder the standard for construing statutes in pari materia, statutes relating to the same subject matter must be construed together to give full effect to the provisions.” State ex rel. Lucas Cty. Republican Party Executive Commt. v. Brunner, 125 Ohio St.3d 427, 2010-Ohio-1873, 928 N.E.2d 1072, ¶ 14. As used in
{¶ 40} In fact, although SFAA attempts to argue otherwise in its reply brief, in its initial merit brief, SFAA conceded that H.B. 318 mandated a “non-bid method of selecting entities principally responsible for alternative methods of construction delivery.” (Emphasis added.) That is, in essence, SFAA admitted that the qualifications-based selection process set forth in H.B. 318 is inapplicable to the bidding requirements of the low-cost selection process of
{¶ 41} Conversely, because there is no bidding as that term is used in
{¶ 42} In effect, SFAA‘s arguments contravene the plain text of the H.B. 318 and
{¶ 43} Therefore, SFAA is not entitled to the requested extraordinary relief in mandamus.
Conclusion
{¶ 44} Based on the foregoing, we dismiss the claims of ASA and ASA-Ohio because they lack standing, and we deny SFAA‘s mandamus claim.
Judgment accordingly.
O‘CONNOR, C.J., and PFEIFER, LUNDBERG STRATTON, O‘DONNELL, LANZINGER, and CUPP, JJ., concur.
MCGEE BROWN, J., not participating.
Williams & Petro Co., L.L.C., John J. Petro, Richard A. Williams, and Susan S.R. Petro, for relators.
Michael DeWine, Attorney General, Alexandra T. Schimmer, Solicitor General, and Jon C. Walden and Jerry K. Kasai, Assistant Attorneys General; and Porter, Wright, Morris & Arthur, L.L.P., Kathleen M. Trafford, and Ryan P. Sherman, for respondent.
