SIERRA CLUB, Plaintiff, v. Lisa P. JACKSON, Administrator, U.S. Environmental Protection Agency, Defendant.
Civil Action No. 11–1278 (PLF)
United States District Court, District of Columbia.
Jan. 9, 2012.
tions that are the product of exhaustive study and comprehensive rulemaking, in order to allow a wholesale reevaluation of a major regulatory program, cannot be viewed as a temporary measure for preserving the status quo.“). Consequently, that type of agency action normally requires notice and an opportunity for comment. See, e.g., Environmental Defense Fund v. Gorsuch, 713 F.2d at 818.
In NRDC v. Abraham, 355 F.3d 179 (2d Cir. 2004), a case that neither side cited, the United States Court of Appeals for the Second Circuit provides a possible answer to why a suspension or delayed implementation of a rule normally constitutes a substantive rulemaking requiring notice and an opportunity for comment: because “altering the effective date of a duly promulgated standard could be, in substance, tantamount to an amendment or rescission of the [rule.]” NRDC v. Abraham, 355 F.3d at 194; see also Public Citizen v. Steed, 733 F.2d at 98 (holding that agency‘s suspension of rule was “a paradigm of a revocation,” constituting “a 180 degree reversal of [the agency‘s] former views as to the proper course“) (internal quotations and citation omitted); NRDC v. U.S. EPA, 683 F.2d at 763 n. 23 (“[A]n indefinite postponement which is never terminated is tantamount to a revocation.“). But if a suspension or delayed implementation constitutes a substantive rulemaking for the reason stated by NRDC v. Abraham, then the question arises why, at least under the Clean Air Act, any challenge to such a rule—including a challenge regarding the requirements of notice and comment—should not be raised in the court of appeals rather than in this Court?
Therefore, in view of NRDC v. Abraham, as well as other authority, the Court finds that it would be helpful to have supplemental briefing on the following questions:
(1) Is it Sierra Club‘s position that the Delay Notice is a rule because it operates as an amendment or rescission of the Boiler Rule and the CISWI Rule?
(2) If so, then why does Sierra Club‘s first claim not fall within the court of appeals’ exclusive jurisdiction under
(3) If not, then on what authority does Sierra Club rely for the proposition that EPA was required to provide notice and an opportunity for comment before issuing the Delay Notice?
Accordingly, it is hereby
ORDERED that Sierra Club shall file a supplemental memorandum addressing the questions described above by October 19, 2011; EPA shall file a response by October 24, 2011; and Sierra Club shall file a reply, if any, by October 27, 2011.
SO ORDERED.
Eileen T. McDonough, U.S. DOJ-Environmental Defense Section, Washington, DC, for Defendant.
OPINION
PAUL L. FRIEDMAN, District Judge.
This matter is before the Court on the parties’ cross-motions for summary judgment on plaintiff‘s three claims. Upon consideration of the parties’ papers, the relevant legal authorities, and the entire record in this case, the Court will grant in part and deny in part the parties’ cross-motions for summary judgment, will enter judgment for defendant on Claim 1 and Claim 2, and will enter judgment for plaintiff on Claim 3. As a result, the Court will declare unlawful the defendant‘s “Delay Notice,” 76 FED. REG. 28,662 (May 18, 2011), will vacate the Delay Notice, and will remand the Delay Notice to defendant for further proceedings consistent with this Opinion.1
I. BACKGROUND
The Court previously has described the factual and procedural background of this case, see Sierra Club v. Jackson, 813 F.Supp.2d 149, 152-55 (D.D.C.2011), and therefore will limit its discussion accordingly.
As EPA describes it, by 2014, the Boiler Rule will lead to significant annual health benefits; according to EPA‘s estimates, the rule will help avoid:
- 2,500 to 6,500 premature deaths,
- 1,600 cases of chronic bronchitis,
- 4,000 nonfatal heart attacks,
- 4,300 hospital and emergency room visits,
- 3,700 cases of acute bronchitis,
- 78,000 cases of respiratory symptoms,
- 310,000 days when people miss work or school,
- 41,000 cases of aggravated asthma, and
- 1,900,000 days when people must restrict their activities.
PMSJ, Ex. C, EPA Fact Sheet, Final Air Toxics Standards for Industrial, Commercial, and Institutional Boilers and Process Heaters at Major Source Facilities at 2-3.
Similarly, according to EPA‘s estimates, by 2016, the CISWI Rule will help avoid:
- 40 to 100 premature deaths,
- 27 cases of chronic bronchitis,
- 64 nonfatal heart attacks,
- 68 hospital and emergency room visits,
- 65 cases of acute bronchitis,
- 1,350 cases of respiratory symptoms,
- 5,300 days when people miss work or school,
- 700 cases of aggravated asthma, and
- 31,000 days when people must restrict their activities.
PMSJ, Ex. D, EPA Fact Sheet, Final Amendments to New Source Performance Standards and Emission Guidelines for Commercial and Industrial Solid Waste Incineration Units at 2.
On March 21, 2011, EPA published the Boiler Rule and the CISWI Rule in the Federal Register and established an effective date of May 20, 2011 for each rule. See 76 FED.REG. at 28,663. Also on March 21, 2011, EPA announced that it was initiating an administrative reconsideration process with respect to certain aspects of each rule, see id., a procedure provided for under the Clean Air Act. See
Shortly thereafter, multiple parties, including plaintiff Sierra Club, filed petitions for review of the Boiler Rule and the CISWI Rule in the United States Court of Appeals for the District of Columbia Circuit. The court of appeals consolidated 16 petitions for review of the Boiler Rule into one proceeding, U.S. Sugar Corp. v. EPA, No. 11-1108, and consolidated 17 petitions for review of the CISWI Rule into another proceeding, American Forest & Paper Ass‘n v. EPA, No. 11–1125. Those petitions for review present substantive challenges to the legal sufficiency of the Boiler
While those petitions for review were pending in the court of appeals, on May 18, 2011, two days before the Boiler Rule and the CISWI Rule were to go into effect, EPA issued a notice, referred to by the agency as the “Delay Notice,” staying the effective date of both rules “until the proceedings for judicial review of these rules [in the court of appeals] are completed or the EPA completes its reconsideration of the rules, whichever is earlier[.]” 76 FED. REG. at 28,664. In the Delay Notice, EPA made explicit that it was staying the effective date of these two rules “pursuant to the APA[, that is, the Administrative Procedure Act], rather than ... the Clean Air Act.” Id. at 28,663. Specifically, EPA stated that it was acting pursuant to its authority under
Sierra Club filed this lawsuit on July 14, 2011 to challenge the validity of EPA‘s Delay Notice. See generally Compl. In its complaint, Sierra Club asserts that it has a cause of action against EPA under the APA, and that this Court has jurisdiction to review the Delay Notice under the federal question statute,
The parties simultaneously briefed EPA‘s motion to dismiss for lack of subject matter jurisdiction and cross-motions for summary judgment. On September 27, 2011, the Court denied EPA‘s motion to dismiss, concluding that “[b]ecause EPA‘s Delay Notice was issued under the APA, it is subject to judicial review in this Court under
ties’
In the parties’ supplemental briefing, EPA again argued that this Court lacks subject matter jurisdiction over this case. The Court therefore first will address the issue of subject matter jurisdiction. It concludes that nothing in the parties’ supplemental briefing requires the Court to revisit its determination that it has jurisdiction over Sierra Club‘s complaint. The Court then will address the merits of the parties’ cross-motions for summary judgment.3
II. SUBJECT MATTER JURISDICTION
On September 27, 2011, the Court denied EPA‘s motion to dismiss for lack of subject matter jurisdiction. See Sierra Club v. Jackson, 813 F.Supp.2d at 152-53. As the Court stated, it was unclear from EPA‘s papers whether the agency was asserting “(1) that this Court actually lacks jurisdiction, or (2) that this Court has jurisdiction, but should defer to the ancillary jurisdiction of the court of appeals.” Id. at 155. “When pressed to clarify EPA‘s position during oral argument [on the motion to dismiss], counsel for EPA relied primarily on the agency‘s ancillary jurisdiction argument, but ultimately also asserted that the Clean Air Act divests this Court of jurisdiction over Sierra Club‘s complaint.” Id.
The Court disagreed with EPA, concluding:
EPA acted, by its own admission, under the [APA] in issuing the Delay Notice, rather than under the Clean Air Act. It did so because the APA‘s administrative stay provision gave EPA more flexibility than the Clean Air Act, the latter‘s stay provision being expressly limited to a maximum of three months, a time that has since passed in this case. But in its motion to dismiss, EPA asks this Court to conclude that the agency in fact acted under the Clean Air Act—the very Act that the agency expressly denied invoking in issuing the Delay Notice ... [T]he Court ... holds that the Delay Notice was issued under the APA, not the Clean Air Act. Because EPA‘s Delay Notice was issued under the APA, it is subject to judicial review in this Court under
28 U.S.C. § 1331 .
Sierra Club v. Jackson, 813 F.Supp.2d at 162. Because EPA specifically invoked the APA to avoid the three-month limitation on stays issued under the Clean Air Act, the agency “must suffer the jurisdictional consequences of that decision.” Id. at 158.
In reviewing the parties’ cross-motions for summary judgment, the Court discovered an issue that neither side raised at the motion to dismiss stage that ultimately could relate to the Court‘s subject matter jurisdiction. The Court therefore ordered supplemental briefing in a Memorandum Opinion and Order issued on October 13, 2011. See Sierra Club v. Jackson, 833 F.Supp.2d at 13, 2011 WL 4852208, at *1. As the Court stated in that Memorandum
But the reasoning set forth in Abraham raised a new question in this case:
[I]f a suspension or delayed implementation constitutes a substantive rulemaking for the reason stated by NRDC v. Abraham, then the question arises why, at least under the Clean Air Act, any challenge to such a rule—including a challenge regarding the requirements of notice and comment—should not be raised in the court of appeals rather than in this Court?
Sierra Club v. Jackson, 833 F.Supp.2d at 10, 2011 WL 4852208, at *2. In view of that unaddressed issue, the Court directed the parties to file supplemental memoranda on three questions:
(1) Is it Sierra Club‘s position that the Delay Notice is a rule because it operates as an amendment or rescission of the Boiler Rule and the CISWI Rule?
(2) If so, then why does Sierra Club‘s first claim not fall within the court of appeals’ exclusive jurisdiction under
(3) If not, then on what authority does Sierra Club rely for the proposition that EPA was required to provide notice and an opportunity for comment before issuing the Delay Notice?
Id. at 11, at *3.
The parties made clear in their supplemental briefing that neither side contends that the Delay Notice operates as an amendment or rescission of the Boiler Rule or the CISWI Rule. See Pl. Supp. at 1 (“EPA‘s Delay Notice is neither an amendment nor a rescission of the delayed rules.“); Def. Supp. Response at 2 (The Delay Notice “is only a temporary procedural device ... that maintains the status quo[.]“); see also Intervenor Supp. Response at 1 n. 1 (The Delay Notice “preserv[es] the status quo until administrative reconsideration or judicial review is complete.“). According to the parties, the Delay Notice is a temporary stay that makes no change to the substantive requirements of either the Boiler Rule or the CISWI Rule. See Pl. Supp. at 4, 6; Def. Supp. Response at 2.
The Court finds no reason to disagree with the parties’ characterization. Consequently, the Court need not revisit its prior decision denying EPA‘s motion to dismiss for lack of subject matter jurisdiction. The issue raised by the Second Circuit in NRDC v. Abraham is not implicated here. Instead, because EPA‘s Delay Notice was issued under the APA and because all agree that the Delay Notice does not operate as an amendment or rescission of a Clean Air Act rule, it is subject to judicial review in this Court under
III. THE MERITS
EPA‘s Delay Notice is subject to review by this Court under the standard set forth
As the Supreme Court has stated, an agency action is arbitrary and capricious if the agency
relied on factors which Congress has not intended it to consider, entirely failed to consider an important aspect of the problem, offered an explanation for its decision that runs counter to the evidence before the agency, or is so implausible that it could not be ascribed to a difference in view or the product of agency expertise.
Air Transport Ass‘n of Am., Inc. v. National Mediation Bd., 719 F.Supp.2d at 30 (quoting Motor Vehicle Mfrs. Ass‘n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983)). Although review under Section 706 is “narrow,” the agency “must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made.’ ” Motor Vehicle Mfrs. Ass‘n v. State Farm Mut. Auto. Ins. Co., 463 U.S. at 43 (quoting Burlington Truck Lines v. United States, 371 U.S. 156, 168 (1962)).
The parties have filed cross-motions for summary judgment. Under
Under the APA, it is the role of the agency to resolve factual issues to arrive at a decision that is supported by the administrative record, whereas the function of the district court is to determine whether or not as a matter of law the evidence in the administrative record permitted the agency to make the decision it did.... Summary judgment serves as the mechanism for deciding, as a matter of law, whether the agency action is supported by the administrative record and otherwise consistent with the APA standard of review, but the normal summary judgment standard does not apply. Id. (quotations and citations omitted).
Sierra Club argues that it is entitled to summary judgment on all three of its claims and requests that the Court declare the Delay Notice unlawful and vacate it. First, Sierra Club contends that the Delay Notice is unlawful because EPA promulgated it without providing the public with notice and an opportunity for comment. See PMSJ at 14-15. Second, Sierra Club contends that EPA lacked the authority to
EPA opposes Sierra Club‘s motion for summary judgment and has filed its own cross-motion for summary judgment. See generally DMSJ. As EPA describes it, the agency had the authority to promulgate the Delay Notice; the agency provided adequate justification for the Delay Notice; and the Delay Notice is not a rule and therefore is not subject to notice and comment requirements.
In the discussion that follows, the Court first will address the question whether EPA had the authority to issue the Delay Notice under
A. Authority to Issue the Delay Notice Under Section 705 of the APA (Claim 2)
1. Relevant Statutes and Procedural Background in Civil Action No. 01-1537
The question whether EPA had the authority to issue the Delay Notice under
a. Statutory and Court-Ordered Deadlines. In 1990, Congress enacted sweeping revisions to the Clean Air Act and “imposed a technology-based, emission-control scheme that limited EPA‘s discretion and that set strict requirements and deadlines for the promulgation of emission standards.” Sierra Club v. Jackson, 2011 WL 181097, at *2. The Clean Air Act established a statutory deadline of November 15, 2000 by which EPA was to have promulgated emission standards like the Boiler Rule and the CISWI Rule—that is, emission standards for sources accounting for ninety percent of the aggregate emissions of especially dangerous hazardous air pollutants. See Sierra Club v. Johnson, 444 F.Supp.2d at 49-50. EPA, however, failed to meet this statutory deadline. See id.; see also Sierra Club v. Jackson, 2011 WL 181097, at *3. So in 2001 Sierra Club filed seven different complaints against EPA, each seeking relief for EPA‘s failure to discharge its regulatory duties under the Clean Air Act; these seven cases were consolidated before this Court under Civil Action No. 01-1537. See Sierra Club v. Jackson, 2011 WL 181097, at *3.
In 2005 the parties filed cross-motions for summary judgment in Civil Action No. 01-1537. EPA did not contest the issue of liability: it admitted that it had failed to promulgate regulations by the statutory deadline of November 15, 2000. Sierra Club v. Jackson, 2011 WL 181097, at *3. Accordingly, the only matter before the Court at that time was to fashion an appropriate equitable remedy. Id. On March
After the Court issued its March 31, 2006 Order, however, the Court granted a number of EPA‘s motions to extend its court-ordered deadlines, all without opposition from Sierra Club. Sierra Club v. Jackson, 2011 WL 181097, at *1. Thus, after these amendments, the Court‘s March 31, 2006 Order required, in relevant part, that EPA fully discharge its statutory duties by issuing its overdue Clean Air Act rules by January 21, 2011. See id. As EPA described it, in order to discharge its statutory duties the agency needed to complete additional emission standards for “(1) certain area source boilers, (2) major source boilers, and (3) CISWI units (collectively, ‘the Three Air Rules‘).” Id. at *4.
In December 2010, EPA requested that the Court extend the January 21, 2011 deadline for the promulgation of the Three Air Rules to April 13, 2012 so that EPA could re-propose those rules. See Sierra Club v. Jackson, 2011 WL 181097, at *1, *4-5. That request was opposed by Sierra Club. Id. Because EPA did not meet its heavy burden of demonstrating that it would be impossible to promulgate substantively adequate rules by January 21, 2011, the Court denied EPA‘s request for an extension of time until April 13, 2012 so that EPA could re-propose the Three Air Rules. Id. at *11. But the Court extended the January 21, 2011 deadline one month, to February 21, 2011, so that EPA would be able to respond to significant comments regarding the Three Air Rules. See id. at *14.
In accordance with the Court‘s January 20, 2011 Order, EPA signed the Boiler Rule and the CISWI Rule on February 21, 2011. See Sierra Club v. Jackson, 813 F.Supp.2d at 153-54. But as discussed, on May 18, 2011, two days before the Boiler Rule and the CISWI Rule were to go into effect, EPA issued its Delay Notice, staying the effective date of both rules “until the proceedings for judicial review of these rules [in the court of appeals] are completed or the EPA completes its reconsideration of the rules, whichever is earlier[.]” 76 FED.REG. at 28,664.
b. Effective Dates—Section 112(d)(10) and Section 129(f) of the Clean Air Act.
The provisions of section 553 through 557 and section 706 of Title 5 [of the APA] shall not, except as expressly provided in this subsection, apply to actions to which this subsection applies. This subsection shall not apply in the case of any rule or circumstance referred to in subparagraphs (A) or (B) of subsection 553(b) of Title 5.
A later provision within the rulemaking subsection of the Clean Air Act,
d. Relief Pending Review—Section 705 of the APA.
When an agency finds that justice so requires, it may postpone the effective date of action taken by it, pending judicial review. On such conditions as may be required and to the extent necessary to prevent irreparable injury, the reviewing court, including the court to which a case may be taken on appeal from or on application for certiorari or other writ to a reviewing court, may issue all necessary and appropriate process to postpone the effective date of an agency action or to preserve the status or rights pending conclusion of the review proceedings.
2. The Parties’ Arguments
Under the Clean Air Act, the Boiler Rule and the CISWI Rule each have specified effective dates. See
EPA disagrees. It contends that the Clean Air Act does not limit the agency‘s authority to stay the Boiler Rule and the CISWI Rule under
In support of its argument, EPA relies on
The provisions of section 553 through 557 and section 706 of Title 5 [of the APA] shall not, except as expressly provided in this subsection, apply to actions to which this subsection applies. This subsection shall not apply in the case of any rule or circumstance referred to in subparagraphs (A) or (B) of subsection 553(b) of Title 5.
3. NRDC v. Reilly
EPA argued in NRDC v. Reilly that it had the authority to suspend its standards under
Although the court of appeals in NRDC v. Reilly used broad language in its opinion—stating that EPA “had no authority to stay the effectiveness of a promulgated standard except for the single, three-month period authorized by section 307(d)(7)(B) of the Clean Air Act,” NRDC v. Reilly, 976 F.2d at 41—the court specifically did not address whether EPA would have had the authority to stay its radionuclides standards under
4. Statutory Interpretation
Since NRDC v. Reilly does not control, the Court must look at the language of the relevant statutes to resolve the question presented by Sierra Club‘s second claim: whether EPA lacked the authority to issue the Delay Notice under
The Court concludes that the language of the Clean Air Act does not on its face provide a clear answer. Rather, the Act is ambiguous on the issue because (1) it does not directly address whether its three-month limitation on stays during reconsideration proceedings under
As noted,
If
The Court concludes that this is not what Congress intended. Sierra Club‘s unpersuasive reasoning aside, see PMSJ Reply at 12-14, one cannot find a principled analysis by which to preserve the courts’ authority to grant stays pending judicial review under Section 705 while simultaneously concluding that the agency has been deprived of such authority. While the Clean Air Act establishes the process by which either EPA or a court may stay the effectiveness of a rule pending reconsideration, it does not by its terms or by logical implication limit the authority of either an agency or a court to exercise its traditional statutory authority under
tion
As the Supreme Court recently has reaffirmed, the power of federal courts to grant stays pending judicial review is ” ‘firmly embedded in our judicial system,’ ‘consonant with the historic procedures of federal ... courts,’ and ‘a power as old as the judicial system of the nation.’ ” Nken v. Holder, 556 U.S. 418, 129 S.Ct. 1749, 1757 (2009) (quoting Scripps-Howard Radio, Inc. v. FCC, 316 U.S. at 13). Although Congress can restrict the courts’ authority to stay rules pending judicial review under
Without clearer evidence of congressional intent than that suggested by Sierra Club, the Court is unwilling to infer a congressional policy that would deprive both an agency and the federal courts of their traditional authority to stay rules pending judicial review as codified in
Finally, in resolving this question, the Court considers useful the canon of statutory construction expressio unius est exclusio alterius, that is, “when Congress enacts specific limitations in a general statute it is presumed to allow other circumstances not included in those limitations[.]” Alegria v. District of Columbia, 391 F.3d 262, 266 (D.C.Cir.2004); see Michigan Citizens for an Independent Press v. Thornburgh, 868 F.2d 1285, 1293 (D.C.Cir.1989) (“[I]f Congress banned the importation of apples, oranges, and bananas from a particular country, the canon of expresio unius est exclusio alterius might well indicate that Congress did not intend to ban the importation of grapefruits.“) (emphasis in original); see also Leatherman v. Tarrant County Narcotics Intelligence & Coordination Unit, 507 U.S. 163, 168 (1993) (applying canon of expressio unius est exclusio alterius to interpretation of
The Court therefore concludes that EPA had the authority to issue the Delay Notice under
B. Notice and an Opportunity for Comment (Claim 1)
The APA defines a “rule” as “the whole or a part of an agency statement of general or particular applicability and future effect designed to implement, interpret, or prescribe law or policy or describing the organization, procedure, or practice requirements of an agency[.]”
Sierra Club contends that the Delay Notice is unlawful because it is a substantive rule that EPA promulgated without providing the public with notice and an opportunity for comment. See PMSJ at 14-15. As discussed, however, Sierra Club expressly acknowledges that the Delay Notice does not operate as an amendment or rescission of the Boiler Rule or CISWI Rule. Pl. Supp. at 1. Sierra Club states that “[the Delay Notice‘s function and purpose are well-defined, and not consistent with either an amendment or a rescission: the Delay Notice temporarily relieves industry from the burdens (and deprives the public of the benefits) associated with” the Boiler Rule and CISWI Rule. Id. at 3. Nevertheless, Sierra Club contends that the Delay Notice—a temporary stay that “makes no change to the
EPA counters that the Delay Notice is not a rule.5 As EPA describes it, the Delay Notice is a temporary device that “serves only to maintain the status quo until the earlier of resolution of the litigation or completion of the ongoing reconsideration proceedings.” DMSJ at 12. As such, the Delay Notice does not “implement, interpret, or prescribe law or policy,”
Sierra Club‘s first claim presents the initial question “whether a suspension of delayed implementation of a final regulation constitutes substantive rulemaking.” Sierra Club v. Jackson, 833 F.Supp.2d at 10, 2011 WL 4852208, at *2. As the Court previously stated,
[t]he case law suggests that normally it does. See Environmental Defense Fund v. EPA, 716 F.2d 915, 920 (D.C.Cir.1983) (citing Environmental Defense Fund v. Gorsuch, 713 F.2d 802, 816 (D.C.Cir.1983)); NRDC v. U.S. EPA, 683 F.2d 752, 761 (3d Cir.1982); and Council of S. Mountains, Inc. v. Donovan, 653 F.2d 573, 580 n. 28 (D.C.Cir.1981); Ranchers Cattlemen Action Legal Fund v. U.S. Department of Agric., 566 F.Supp.2d 995, 1004 (D.S.D.2008); see also Public Citizen v. Department of Health & Human Servs., 671 F.2d 518, 520 (D.C.Cir.1981) (Edwards, J., dissenting) (“Certainly a decision to suspend indefinitely regulations that are the product of exhaustive study and
comprehensive rulemaking, in order to allow a wholesale reevaluation of a major regulatory program, cannot be viewed as a temporary measure for preserving the status quo.“). Consequently, that type of agency action normally requires notice and an opportunity for comment. See, e.g., Environmental Defense Fund v. Gorsuch, 713 F.2d at 818.
Sierra Club v. Jackson, 833 F.Supp.2d at 10, 2011 WL 4852208, at *2.
As the Second Circuit stated in NRDC v. Abraham, however, the reason that the suspension or delayed implementation of a rule normally constitutes substantive rulemaking is because “altering the effective date of a duly promulgated standard could be, in substance, tantamount to an amendment or rescission of the [rule.]” NRDC v. Abraham, 355 F.3d at 194; see also Public Citizen v. Steed, 733 F.2d 93, 98 (D.C.Cir.1984) (holding that agency‘s suspension of rule was “a paradigm of a revocation,” constituting “a 180 degree reversal of [the agency‘s] former views as to the proper course“) (quotations and citation omitted); NRDC v. U.S. EPA, 683 F.2d at 763 n. 23 (“[A]n indefinite postponement which is never terminated is tantamount to a revocation.“).
Sierra Club expressly has disclaimed any argument that the Delay Notice operates as an amendment or rescission of the Boiler Rule or CISWI Rule; the Delay Notice “makes no change to the substantive requirements of either rule.” Pl. Supp. at 4. Thus, Sierra Club does not disagree with EPA‘s characterization of the Delay Notice as a “temporary procedural device ... that maintains the status quo with respect to boilers and CISWI units[.]” Def. Supp. Response at 2; see Pl.
The central question, however, “is not the length of the stay or its temporary nature,” but rather whether the stay of the Boiler Rule and the CISWI Rule constitutes substantive rulemaking. Sierra Club v. Jackson, 833 F.Supp.2d at 10, 2011 WL 4852208, at *2; see Council of S. Mountains v. Donovan, 653 F.2d at 582; Environmental Defense Fund, Inc. v. Gorsuch, 713 F.2d at 818. And on that question, the court of appeals’ opinion in Council of S. Mountains v. Donovan is unhelpful to Sierra Club. In that case, the court of appeals concluded that an agency order altering implementation of certain mine safety regulations by deferring a compliance deadline for six months “was in effect an amendment to a mandatory safety standard.” Council of S. Mountains v. Donovan, 653 F.2d at 579 n. 26 (emphasis added); see id. at 582 n. 40 (same). The court of appeals agreed with the proposition, undisputed by the government agency, that the agency order—which moved a compliance deadline from December 21, 1980 to June 21, 1981 so that coal mine operators would have more time to make available to miners life-saving equipment for use during emergencies, see 45 FED. REG. 80,501, at 80,501-02 (Dec. 5, 1980)—was a substantive rule subject to notice and comment requirements. See id. at 580 & n. 28.6
In contrast, Sierra Club argues that the Delay Notice does not operate as an amendment to the Boiler Rule or the CISWI Rule. See Pl. Supp. at 4. Instead, the Delay Notice simply preserves the status quo. A temporary stay to preserve the status quo does not constitute a substantive rulemaking because, by definition, it is not “designed to implement, interpret, or prescribe law or policy[.]”
Consequently, the Court concludes that the Delay Notice does not constitute substantive rulemaking, see
C. Justification for the Delay Notice (Claim 3)
Sierra Club argues that the Delay Notice is arbitrary and capricious for “at least four reasons, each of which independently requires vacatur.” PMSJ at 21. Sierra Club contends that (1) EPA failed “to consider or even acknowledge the impact of [the Delay Notice] on people who are exposed to emissions from Industrial Boilers and CISWI,” id. at 21; (2) EPA failed “to articulate any rational connection [between] its alleged concern for public comment opportunity and its decision not just to reconsider the Industrial Boilers and CISWI Rules but to stay them as well,” id. at 22; (3) EPA failed “to link its rationale [for the Delay Notice]—EPA‘s voluntary reconsideration“—to the pending litigation in the court of appeals, id. at 23; and (4) EPA failed to apply or even mention the four-part test—likelihood of success on the merits; irreparable harm; balance of equities; public interest—applicable to agency stays under
EPA argues that the rationale for the Delay Notice is reasonable and should be upheld. See DMSJ at 13. EPA disagrees with Sierra Club that it must apply the four-part test in determining whether to stay a rule under the APA. Instead, according to EPA, all that is required under
EPA explained its reasons for issuing the Delay Notice as follows:
We find that justice requires postponing the effectiveness of these rules. As explained in the March 21, 2011 notice of
reconsideration, see 76 FED.REG. 15,266; AR at 186,] EPA has identified several issues in the final rules which it intends to reconsider because we believe the public did not have a sufficient opportunity to comment on certain revisions EPA made to the proposed rules. These issues include revisions to the proposed subcategories and revisions to some of the proposed emissions limits. In addition, EPA received data before finalizing both rules but was unable to incorporate that data into the final rules given the court deadline for issuing the rules, which the Agency was unable to extend. EPA also notes thousands of facilities across multiple, diverse industries will need to begin to make major compliance investments soon, in light of the pressing compliance deadlines. These investments may not be reversible if the standards are in fact revised following reconsideration and full evaluation of all relevant data.... Since petitions for judicial review of both the Major Source Boiler MACT and the CISWI Rule have been filed, and, as explained above, justice requires a delay of the effective dates, it is reasonable for the EPA to exercise its authority to delay the effective dates of the Major Source Boiler MACT and the CISWI Rule under the APA for a period that exceeds three months.
76 FED.REG. at 28,663-64. EPA contends that the reasons listed above provide a rational basis for its finding that justice requires staying the Boiler Rule and CISWI Rule pending the completion of the litigation in the court of appeals, or until EPA completes its reconsideration of the rules, whichever is earlier. See id. at 28,664; see also DMSJ at 14-16.
The Court concludes that the Delay Notice is arbitrary and capricious for three separate reasons: (1) the standard for a
1. Four-Part Preliminary Injunction Test—The Standard for Stays Under Section 705
The Court concludes that the standard for a stay at the agency level is the same as the standard for a stay at the judicial level: each is governed by the four-part preliminary injunction test applied in this Circuit. See Cuomo v. U.S. Nuclear Regulatory Comm‘n, 772 F.2d 972, 974 (D.C.Cir.1985); Virginia Petroleum Jobbers Ass‘n v. Federal Power Comm‘n, 259 F.2d 921, 925 (D.C.Cir.1958). EPA, however, failed to employ or even mention this four-part test in issuing the Delay Notice.
Under
when an agency finds that justice so requires, it may postpone the effective date of action taken by it, pending judicial review. On such conditions as may be required and to the extent necessary to prevent irreparable injury, the reviewing court, including the court to which a case may be taken on appeal from or on application for certiorari or other writ to a reviewing court, may issue all necessary and appropriate process to postpone the effective date of an agency action or to preserve status or rights pending conclusion of the review proceedings.
According to EPA, however, “[t]hat Congress chose, in the second sentence of section 705, to make irreparable injury a predicate for a court‘s grant—presumably over an agency‘s objection—of a judicial stay in fact indicates that neither irreparable injury nor any other portion of the traditional judicial standard for granting preliminary relief is a predicate to an agency‘s own exercise of discretion under section 705[.]” DMSJ at 13. Thus, EPA argues, it need only find that justice requires a stay, according to its broad, discretionary determination of what constitutes justice; a court, in contrast, may only grant a stay upon consideration of the four-part preliminary injunction test. See id.
The Court disagrees with EPA. The agency has failed to advance any persuasive reason why it should be treated differently from a court when staying agency
This section permits either agencies or courts, if the proper showing be made, to maintain the status quo.... The authority granted is equitable and should be used by both agencies and courts to prevent irreparable injury or afford parties an adequate judicial remedy.
ADMINISTRATIVE PROCEDURE ACT, PUB.L. 1944-46, S. Doc. 248 at 277 (1946) (describing the intent of 5 U.S.C. § 1009(d), the prior version of Section 705) (emphasis added).
EPA neither employed nor mentioned the four-part test in its Delay Notice. And as the court of appeals recently held, in considering whether a preliminary injunction is warranted “a district court must set forth its consideration of the [four] factors and its attendant conclusions of law[.]” Gordon v. Holder, 632 F.3d 722, 724 (D.C.Cir.2011) (emphasis added). So must EPA, and the failure to do so in this case is arbitrary and capricious.
2. Departure from Prior Precedents
Even if EPA were not required as a matter of law to employ the four-part preliminary injunction test in granting a stay under Section 705 of the APA, EPA previously has done so in its review of requests to stay its rules. See In re Public Serv. Co. of N.H., 1 E.A.D. 389, 1977 WL 45581 (1977) (formal adjudication by Environmental Appeals Board applying the four-part test to a request for a stay under
It is established that an agency, like a court, “[n]ormally ... must adhere to its
[If an agency] announces and follows—by rule or by settled course of adjudication—a general policy by which its exercise of discretion will be governed, an irrational departure from that policy (as opposed to an avowed alteration of it) could constitute action that must be overturned as “arbitrary, capricious [or] an abuse of discretion” within the meaning of the [APA].
INS v. Yang, 519 U.S. 26, 32, 117 S.Ct. 350, 136 L.Ed.2d 288 (1996) (quoting
As discussed, EPA previously has employed the four-part preliminary injunction test in its review of requests to stay prior agency actions, see, e.g., In re Public Serv. Co. of New Hampshire, 1 E.A.D. 389, 1977 WL 45581 (1977), and the agency expressly has stated that this test sets forth the “merits criteria” for evaluating a request for a stay under
EPA now contends in a footnote in its motion papers that on prior occasions it “was simply responding to statements in the stay requests that claimed [that the four-part test was met],” but “did not refer to those factors as its reasons for denying the stay requests.” DMSJ at 13 n. 9. That claim, however, is refuted by the prior statements of the agency itself. See, e.g., 76 FED.REG. at 4,800 (concluding that a stay under
3. “Pending Judicial Review”
Finally, even if EPA were correct that a lower standard applied to stays at the agency level, such stays plainly must be tied to the underlying pending litigation when the APA rather than the Clean Air Act is the authority under which the stay is granted. Under
The reasons for the Delay Notice articulated by EPA in the Notice relate entirely to the pending reconsideration proceedings: (1) “EPA has identified several issues in the final rules which it intends to reconsider because we believe the public did not have a sufficient opportunity for comment“; (2) “EPA received data before finalizing both rules but was unable to incorporate that data into the final rules,” so that the “standards [may be] revised following reconsideration and full evaluation of the data“; and (3) “thousands of facilities ... will need to begin to make major compliance investments soon” that “may not be reversible if the standards are in fact revised following reconsideration and full evaluation of all relevant data.” 76 FED. REG. at 28,663 (emphasis added). But EPA did not issue the Delay Notice under the reconsideration provision of the Clean Air Act,
EPA stated in the Delay Notice that “[s]ince petitions for judicial review of both the Major Source Boiler MACT and the CISWI Rule [were] filed, and ... justice require[d] a delay of the effective dates,” it was “reasonable for the [agency] to exercise its authority to delay the effective dates of the Major Source Boiler MACT and the CISWI Rule under the APA for a period that exceeds three months.” 76 FED.REG. at 28,663-64. EPA therefore stayed the rules “until the proceedings for judicial review are completed or the EPA completes its reconsideration of the rules, whichever is earlier[.]” 76 FED.REG. at 28,664. In fact, EPA states in its papers, “[g]iven that the [a]gency was confronted with petitions for administrative reconsideration and stay of the [r]ules, as well as petitions for judicial review, after the [r]ules were promulgated,” the distinction between pending litigation and agency reconsideration proceedings is one “without a difference.” DMSJ at 15.
EPA is wrong. The agency cannot use
EPA now argues in the papers it filed in this Court that the reasons set forth in the Delay Notice “establish litigation risk,” justifying the stay. DMSJ Reply at 9. EPA further contends that it issued the Delay Notice because of the “risk that the [r]ules could be vacated by the D.C. Circuit.” Id. But the Delay Notice itself makes no mention of any concern about the substantive merit of its rules, and the Court will not uphold an agency decision “where the agency has offered a justification in court different from what it provided in its opinion.” Morgan Stanley Capital Group, Inc. v. Public Util. Dist. No. 1 of Snohomish Cnty., 554 U.S. 527, 544, 128 S.Ct. 2733, 171 L.Ed.2d 607 (2008); see Manin v. NTSB, 627 F.3d at 1245 (courts “generally may not uphold agency action on a basis other than that relied upon by the agency“). Moreover, the administrative record belies EPA‘s purported concern about “litigation risk“: as EPA itself stated in its May 21, 2011 notice of reconsideration—explicitly referenced by the agency in finding that justice required the issuance of the Delay Notice, 76 FED. REG. at 28,663—although some issues relating to the Boiler Rule and CISWI Rule could “benefit from additional public involvement,” the agency “believe[s] that the final [Boiler and CISWI] rules reflect reasonable approaches consistent with the requirements of the Clean Air Act.” AR at 187 (emphasis added). The Court therefore concludes that EPA‘s Delay Notice has no rational connection to the underlying litigation in the court of appeals. Consequently, the Delay Notice is arbitrary and capricious.
D. Remedy
For the reasons set forth above, the Court concludes that EPA‘s Delay Notice is arbitrary and capricious. Sierra Club contends that such a conclusion necessarily requires that the Court vacate the Delay Notice, see Pl. Supp. Reply at 10 (“If EPA acted ... arbitrarily, the Delay Notice must be vacated.“), whereas EPA requests that the Court remand the Delay Notice to the agency for further consideration without vacating it. See Def. Supp. Response at 8.
While an agency‘s failure to set forth a reasoned explanation requires a reviewing court to remand to the agency for further consideration, see Motor Vehicle Mfrs. Ass‘n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 57 (1983), such a defect does not necessarily require vacatur. See, e.g., Advocates for Highway & Auto Safety v. Federal Motor Carrier Safety Admin., 429 F.3d 1136, 1151 (D.C.Cir.2005) (“While unsupported agency action normally warrants vacatur, ... this court is not without discretion [to remand without vacating].“); Allied-Signal, Inc. v. Nuclear Regulatory Comm‘n, 988 F.2d 146, 150 (D.C.Cir. 1993) (“An inadequately supported rule ... need not necessarily be vacated.“). The decision whether to vacate hinges on [1] “the seriousness of the [regulation‘s] deficiencies (and thus the extent
“[I]n deciding whether to vacate a flawed agency action, the district court should be guided by two principal factors: (1) the seriousness of the ... deficiencies of the action, that is, how likely it is the [agency] will be able to justify its decision on remand; and (2) the disruptive consequences of vacatur.”
Heartland Reg‘l Med. Ctr. v. Sebelius, 566 F.3d at 197 (quotations omitted) (alterations in original). Having considered the two principal factors in deciding whether to vacate EPA‘s flawed action, the Court concludes that vacating the Delay Notice is the appropriate remedy in this case.
First, the Court doubts that EPA will be able to justify a decision to stay the Boiler Rule and the CISWI Rule pending judicial review in the court of appeals. EPA has not persuaded the Court that there is ” ‘a serious possibility’ ” that it would be able to offer an adequate explanation for its decision on remand. American Petroleum Inst. v. Johnson, 541 F.Supp.2d at 185 (quoting Milk Train, Inc. v. Veneman, 310 F.3d 747, 756 (D.C.Cir.2002)). As discussed, although EPA has attempted to characterize the Delay Notice as a stay pending judicial review, the rationale offered for the Delay Notice relates exclusively to the pending reconsideration proceedings. Furthermore, after EPA promulgated the Delay Notice, the agency then moved the court of appeals to hold its review in abeyance until the agency finished its reconsideration proceedings, likely ensuring that the Delay Notice will end only when EPA completes the reconsideration process. EPA since has informed the Court that it anticipates it will complete reconsideration proceedings and will sign final Boiler and CISWI Rules by April 30, 2012, DMSJ at 5—thereby effectively granting itself the extension that this Court expressly rejected. See Sierra Club v. Jackson, 2011 WL 181097, at *11 (“Because EPA has not met its heavy burden of demonstrating that it would be impossible to promulgate substantively adequate regulations ..., the Court denies EPA‘s request for an extension of time until April 13, 2012 so that EPA can re-propose the Three Air Rules.“). It is clear to the Court that EPA‘s Delay Notice, in form and effect, operates as a stay pending reconsideration, not litigation. The first factor therefore weighs in favor of vacating the Delay Notice.
The second factor also weighs in favor of vacatur. EPA, in issuing the Delay Notice, noted that “thousands of facilities across multiple, diverse industries will need to begin to make major compliance investments soon, in light of the pressing compliance deadlines.” 76 FED.REG. at 28,663. EPA further noted that “[t]hese investments may not be reversible if the standards are in fact revised following reconsideration and full evaluation of all relevant data.” Id. (emphasis added). The Court acknowledges that vacating the Delay Notice likely will have an effect on industry facilities throughout the country: they will finally, more than 12 years after a clear congressional mandate, have to comply with overdue Clean Air Act emission standards. But although the Boiler Rule and the CISWI Rule may be changed after the reconsideration proceedings,
IV. CONCLUSION
For the foregoing reasons, the Court will grant in part and deny in part the parties’ cross-motions for summary judgment. It will enter judgment for EPA on Claim 1 and Claim 2 and for Sierra Club on Claim 3. As a result, the Court will declare unlawful EPA‘s Delay Notice, will vacate the Delay Notice, and will remand the Delay Notice to EPA for further proceedings consistent with this Opinion.
An Order consistent with this Opinion shall issue this same day.
SO ORDERED.
PAUL L. FRIEDMAN
UNITED STATES DISTRICT JUDGE
