Rochon Corporation of Iowa, Inc. n/k/a Graphite Construction Group, Inc., Appellant, vs. Des Moines Area Community College, Appellee.
No. 22-2098
In the Iowa Supreme Court
Submitted October 10, 2024—Filed November 22, 2024
May, J.
A public entity seeks further review of the court of appeals’ reversal of the district court‘s ruling that the entity was not obligated to pay certain funds to a contractor. Decision of Court of Appeals Vacated; District Court Judgment Affirmed.
May, J., delivered the opinion of the court, in which all justices joined.
Stephen D. Marso (argued) and Bryn E. Hazelwonder of Whitfield & Eddy, P.L.C., Des Moines, for appellant.
Jodie McDougal (argued), Philip S. Bubb, and Michael D. Currie of Fredrikson & Byron, P.A., Des Moines, for appellee.
Jason Craig and Kristine Stone of Ahlers & Cooney, P.C., Des Moines, for amici curiae Community Colleges of Iowa, Iowa Association of School Boards, Iowa State Association of Counties, and Iowa League of Cities.
May, Justice.
One of those requirements is called “retainage.” Retainage is money that the public entity collects by withholding a small portion (no more than 5%) of its monthly progress payments to the contractor. The point of retainage is to assure “payment of claims for materials furnished and labor performed on” the project.
Here there is a dispute as to when—exactly—the contractor can receive that retainage. The contractor here claims that it is entitled to the retainage now even though the construction project is not yet completed. This is true, the contractor claims, because it has taken сertain procedural steps, including the filing of a bond.
We disagree. Except in limited circumstances that are specified in the statutory text, chapter 573 does not allow the contractor to obtain the retainage before the “completion and final acceptance” of the project.
I. Factual and Procedural Background.
Des Moines Area Community College (DMACC) is a public entity. In 2019,
Work on the project proсeeded. Graphite made monthly requests for progress payments. DMACC‘s project architect reviewed the requests. Subject to the architect‘s approval, DMACC generally made payments consistent with Graphite‘s requests. But DMACC withheld 5% of each payment as retainage.
By January 2022, the project was approaching completion. On January 4, Graphite made its twenty-ninth application for payment. This amounted to Graphite‘s final invoice, through which it requеsted final payment under the contract. By that time, all that was left under the contract was the retainage, which amounted to about $510,000.
But at the time of Graphite‘s payment application, the project was not yet completed. A punch list of the incomplete work hadn‘t even been created yet. So DMACC‘s architect declined to approve Graphite‘s request for payment.
Meanwhile, a dispute arose between Graphite and Metro Concrete, Inc. (Metro), a subcontractor that had provided concrete services for the project. Metro believed that Graphite owed over $212,000 for unpaid services. In late January, Metro served a claim “Under Provisions of Chapter 573 Iowa Code” against Graphite and DMACC. Then, in March, Graphite served a demand on Metro to file suit on its claim.1 Metro obliged by filing the current suit, in which Metro seeks payment for its unpaid services. Metro named DMACC and Graрhite as defendants. Both DMACC and Graphite answered.
In July, Graphite filed a “Motion to Compel Defendant DMACC to Release Retainage.”2 In its motion, Graphite claimed that after Metro filed its suit, Graphite had filed a bond for twice the amount of Metro‘s claim. Therefore, Graphite contended,
DMACC resisted the motion. DMACC maintained that because the project was not yet completed, Graphite was not yet entitled to the requested retainage. DMACC also resisted Graphite‘s request for attorney fees.
The district court denied Graphite‘s requests. Relying on the plain language of
Then Graphite filed this appeal. In its appellate brief, Graphite argues that the district court wаs wrong to deny its claims to retainage and attorney fees. Graphite also requests appellate attorney fees.
We transferred Graphite‘s appeal to the court of appeals. The court of appeals reversed and remanded for payment to Graphite from the retainage fund. But the court of appeals denied Graphite‘s requests for attorney fees. The court reasoned that
Then DMACC applied to this court for further review. We granted DMACC‘s application. We also accepted an amicus brief from organizations that represent public entities, namely, the Community Colleges of Iowa (not including DMACC), Iowa Association of School Boards, Iowa State Association of Counties, and Iowa League of Cities. These amici argue that the district court was correct in concluding that Graрhite was not entitled to retainage because the project was not completed.
II. Merits.
We begin our analysis with an overview of chapter 573 and particularly its retainage features. We then explain why, in our view, the district court was right to deny Graphite‘s motion to compel payment of the retainage. After that we address Graphite‘s counterarguments. And then we briefly discuss the issue of attorney fees.
A. Overview. Chapter 573 helps ensure that public construction projects get completed and that contractors and subcontractors get paid. The statute works through two main mechanisms. First, chapter 573 requires general contractors to provide a performance bond to ensure “faithful performance of the contract” and “fulfillment of other requirements as provided by law.”
Second, chapter 573 requires retainage procedures. These procedures start with monthly progress payments that public еntities make to the general contractor. These payments are based on “estimates of labor performed and material delivered, as determined by the project architect.”
Disposition of the fund is the central topic of this suit. Chapter 573 is clear that, as a general matter, the fund must be “retained by” the public entity for no less than “thirty days after the completion and final acceptance of the improvement.”
(allowing later claims in specified circumstances),
But suppose that, at the end of this thirty-day period, there are no claims on file with the public entity. In that case, the entire retainage fund must be paid to the contractor.
Chapter 573 also contemplates a second thirty-day period. This is the period in which suits must be filed to obtain the remaining retainage. The period begins with “the expiration of thirty days . . . following the completion and final acceptance” of the project.
Regardless of how litigation begins, all outstanding claims should be resolved in a single action. This single-action requirement is reflected in the text of
B. Application. With this overviеw in mind, we now turn to the dispute before us. Graphite contends that even though the project is not completed, much less finally accepted, DMACC is obligated to release the retainage to Graphite because three things have occurred: Graphite served a demand for suit upon subcontractor Metro, then Metro responded by commencing an action, and then Graphite filed a surety bond in twice the amount of Metro‘s claim. Graphite bases this argument on certain language in the second paragraph of
1. The public corporation, the principal contractor, any claimant for labor or material who has filed a claim, or the surety on any bond given for the performance of the contract, may, at any time after the expiration of thirty days, and not later than sixty days, following the completion and final acceptance of said improvement, bring action in equity in the county where the improvement is located to adjudicate all rights to said [retainage] fund, or to enforce liability on said bond.
2. Upon written demand of the contractor served, in the manner prescribed for original notices, on the person filing a claim, requiring the claimant to commence action in court to enforce the claim, an action shall be commenced within thirty days, otherwise the retained and unpaid funds due the contractor shall be releasеd. . . . After an action is commenced, upon the general contractor filing with the public corporation or person withholding the funds, a surety bond in double the amount of the claim in controversy, conditioned to pay any final judgment rendered for the claims so filed, the public corporation or person shall pay to the contractor the amount of funds withheld.
We disagree with Graphite‘s argument. Like the district court, we think Graphite takes the italicized language out of context. As explained, other provisions of chapter 573 make it clear that the retainage cannot be released before thirty days after the completion and final acceptance of the project. See, e.g.,
C. Counterarguments. We have considered all of Graphite‘s counterarguments. We believe three of them should be discussed here: (1) Grаphite‘s theory that
1. Unity of section 573.16. We start with Graphite‘s theory about the text of
We disagree. When reading statutes, “we seek to determine the ordinary and fair meaning” of the legislature‘s chosen language. Doe v. State, 943 N.W.2d 608, 610 (Iowa 2020). We think the most fair and natural reading of
This view is consistent with the legislature‘s own approach to
We also bear in mind that when the legislature wants subsections to operate independently, the legislature knows how to say so. Indeed, in other parts of chapter 573, the legislature makes it clear that some subsections can act independently. For instance,
This leads to a larger point about
We note also that if, as Graphite suggests, a contractor could demand a lawsuit and then bond off every time a subcontractor brings a claim, then there could be a
2. Chapter 573 versus chapter 572. Next we address Graphite‘s analogy between
We disagree. To be sure, we have noted similarities between chapters 572 and 573. See Farmers Coop. Co. v. DeCoster, 528 N.W.2d 536, 537-38 (Iowa 1995) (per curium). But we have not said—and we could not say—that courts may ignore textual differences between the two chapters. Rather, courts must give effect to those differences. And those differences are dispositive here. On one hand, it appears that nothing in the text of chapter 572 requires property owners to wait until completion of the project before bonding off liens. Indeed,
3. Surplusage? Finally, we address Graphite‘s concern that our interpretation would leave
We disagree. Suppоse that after the completion and acceptance of a project, there is litigation over the retainage. That litigation will take time. And during that time, the contractor will not have access to the retainage funds unless the contractor files the bond permitted by
So
D. Attorney Fees. For the reasons explained above, we conclude that Graphite should not prevail on its claim to recover the retainage. Because Graphite is not a prevailing party, Graphite is not entitled to attorney fees under
We conclude, therefore, that the district court was right to deny Graphite‘s claim
III. Disposition.
The district court was correct to deny Graphite‘s motion to compel payment of the retainage. As to this issue, the court of appeals erred in reversing the district court.
As to attorney fees, the district court and the court of appeals were both correct to reject Graphite‘s claims.
Decision of Court of Appeals Vacated; District Court Judgment Affirmed.
