RIDGE HEATING, AIR CONDITIONING AND PLUMBING, INC., v. Robert S. BRENNEN, et ux.
No. 135, Sept. Term, 2000
Court of Appeals of Maryland
Oct. 19, 2001
783 A.2d 691
336
J. Mitchell Kearney (Brown, Diffenderffer & Kearney, LLP, on brief) of Baltimore, for respondents.
Argued before BELL, C.J., and ELDRIDGE, RAKER, WILNER, CATHELL, HARRELL, and BATTAGLIA, JJ.
RAKER, Judge.
The question in this case is whether a subcontractor who works on an addition to an existing home can impose a mechanic‘s lien on the home when the homeowner has already paid the general contractor for the subcontractor‘s services.
In December 1997, Ridge Heating, Air Conditioning, and Plumbing, Inc. (“Ridge“), a subcontractor, contracted with Timberwood Construction, Inc. (“Timberwood“), a general contractor, to provide and install heating, air conditioning and plumbing for an addition to the home of Mr. and Mrs. Brennen (the “Brennens“). Ridge‘s contract was pursuant to a general contract that required Timberwood to complete construction on the addition to the Brennens’ home by April 25, 1998, and the Brennens to pay progress payments totaling $153,085.
Due to financial difficulties, Timberwood abandoned the project on August 3, 1998, breaching its contracts with the Brennens and Ridge. The Brennens found another contractor to finish the job at an additional cost. After the breach, the Brennens were not indebted to Timberwood for any of the work done prior to the breach, including the labor and materials supplied by Ridge. Ridge, however, had not been paid by Timberwood, and on September 30, 1998, Ridge filed a twocount Complaint to Establish and Enforce a Mechanic‘s Lien against the Brennens in the Circuit Court for Baltimore County. On October 5, 1998, the Circuit Court issued an Order to Show Cause, commanding the Brennens to show cause why the lien should not attach to their property. The Brennens filed a Verified Answer on October 22, 1998, denying
At the show cause hearing on November 12, 1998, the parties agreed, by Consent Order, that the matter should be set for trial in the normal course and that no final lien would be entered at that stage of the proceedings. Following discovery, the Brennens filed a Motion for Summary Judgment on May 9, 1999. On December 29, 1999, Judge Robert E. Cadigan granted summary judgment in favor of the Brennens on the basis that
Ridge noted a timely appeal to the Court of Special Appeals, presenting the following question:
“Did the trial court err in applying
Real Property § 9-104(f)(3) of the Maryland Annotated Code , limiting an owner‘s liability to a subcontractor who performs work on the owner‘s single family dwelling?”
The Court of Special Appeals affirmed the judgment of the Circuit Court on three grounds: (1) that the Court of Special Appeals’ decisions and the decisions of this Court have consistently construed
We granted Ridge‘s petition for writ of certiorari to consider the issue of whether
Before delving into the meaning of the statutory language of
”
Maryland Code, § 9-102 of the Real Property Article provides, in relevant part, that every building that is either newly erected or repaired to the extent of 15% of its value is subject to a lien—a mechanic‘s lien—for the payment of all debts contracted for work done and materials supplied for or about the building. That includes debts owing to subcontractors who have no privity with the owner of the property and whom the owner may not even know worked on or supplied materials for the building.”
Id. at 235, 734 A.2d at 214-15. We also found that the mechanic‘s lien law historically has been construed in the most liberal and comprehensive manner in favor of mechanics and materialmen. Id. at 246, 734 A.2d at 221 (quoting T. Dan Kolker, Inc. v. Shure, 209 Md. 290, 296, 121 A.2d 223, 226 (1956)). This liberal construction is essential to subcontractors, who enhance the value of the homeowner‘s property but have no direct contractual relationship with the owner and therefore cannot otherwise subject the owner‘s property or assets to a mechanic‘s lien. Id.
In 1982, Chapter 251 of the
“to ‘limit[] the liability of an owner to a subcontractor for work performed and materials rendered by the subcontractor on a single family dwelling erected on the owner‘s land for his own residence, to the extent that the owner has rendered payment to the contractor.’ The expressed intent of the Legislature was clearly remedial, but remedial, in this instance, in favor of the owner, rather than the claimant. The ability under the existing law of an owner, upon receipt of a subcontractor‘s notice, to withhold the amount of the claim from the prime contractor was obviously not regarded as sufficient protection in the case of a single family residence being built for the owner‘s own residential use. By the time the notice is received, the owner may already have paid the prime contractor or have accumulated set-offs or credits exceeding what is owed on the contract.”
“(f) Payments by owner to contractor after notice, limitation on lien against certain single family dwellings.—
* * *
(3) Notwithstanding any other provision of this section to the contrary, the lien of the subcontractor against a single family dwelling being erected on the land of the owner for his own residence shall not exceed the amount by which the owner is indebted under the contract at the time the notice is given.”
Ridge argues that, although the Brennens have paid for the work done on their home,
In interpreting
“Every building erected and every building repaired, rebuilt or improved to the extent of 15 percent of its value is subject to establishment of a lien in accordance with this subtitle for the payment of all debts, without regard to the amount, contracted for work done for or about the building and for materials furnished for or about the building, including....”
According to Ridge, the opening sentence of
As for case law, Ridge correctly observes that no Maryland court has considered the meaning of the phrase
We do not find Ridge‘s arguments persuasive. The statutory language is anything but clear as to the distinction between new and improved homes. The phrase “being erected” may reasonably be applied to many types of construction, including new homes, an addition to an existing home, or a home erected on an existing foundation after a disaster such as a fire. In Tucker v. Fireman‘s Fund Insurance Co., 308 Md. 69, 517 A.2d 730 (1986), we recognized the rule that:
[W]here a statute is plainly susceptible of more than one meaning and thus contains an ambiguity, courts consider not only the literal or usual meaning of the words, but their meaning and effect in light of the setting, the objectives and purpose of the enactment. In such circumstances, the court, in seeking to ascertain legislative intent, may consider the consequences resulting from one meaning rather than another, and adopt that construction which avoids an illogical or unreasonable result, or one which is inconsistent with common sense.
Id. at 75, 517 A.2d at 732-33 (citations omitted).
The Legislature has not indicated, nor has any court suggested, that other sections of the statute draw the distinction Ridge seeks. We find that, in enacting
The holdings of this Court and the courts below reinforce our reading of the Legislature‘s intent. The language of Ridge Sheet Metal Co., Inc. v. Morrell, 69 Md.App. 364, 517 A.2d 1133, cited by Ridge for the proposition that the Legislature intended to limit
“Turning to the legislative intent, we glean from the preamble to chapter 251 quoted previously that the Legislature intended in limited situations to shift the risk of loss from the owner of a single family dwelling to the subcontractor. The enactment of
§ 9-114 under chapter 251 in 1982 further evidences the Legislature‘s intent to ameliorate owner liability.”
Id. at 374, 517 A.2d at 1138 (emphasis added). At no point does the Court of Special Appeals state or imply that “limited situations” means only those situations where a homeowner builds a new home. Moreover, the relevant case law has evolved since Ridge Sheet Metal. See Winkler Const. Co., v. Jerome, 355 Md. 231, 734 A.2d 212 (1999); Reisterstown Lumber Co. v. Tsao, 319 Md. 623, 574 A.2d 307 (1990); Best Drywall, Inc. v. Berry, 108 Md.App. 381, 672 A.2d 116 (1996); F. Scott Jay & Co., Inc. v. Vargo, 112 Md.App. 354, 685 A.2d 799 (1996); Grubb Contractors v. Abbott, 84 Md.App. 384, 579 A.2d 1185 (1990).
Generally, courts have hesitated to construe the statute against homeowners. For example, in Best Drywall, Inc. v. Berry, the court decided whether a vacation home is a single family dwelling being erected on the land of the owner for his own residence within the meaning of
“contrary to the general purpose of the overall mechanic‘s lien statute to protect subcontractors and materialmen,
§ 9-104(f)(3) clearly has as its purpose an intent to shift respon-
sibility for insuring payment of a subcontractor from the owner of the dwelling to the prime contractor, i.e., to limit the subcontractor‘s ability to lien the single family residence. Consistent with the reasoning in Ridge Sheet Metal that the subcontractor‘s broad reading of “indebted” in
§ 9-104(f)(3) was inimicable [sic] to the intended limiting effect of that particular section of the statute, we conclude here that Best Drywall is better able than appellees to bear the risk of loss in this type of situation also.”
This Court has dealt with
Reisterstown and Winkler are not controlling in that they concern the burdens borne by a lien claimant, whereas here we are concerned with a phrase that governs the applicability of the statute. Nevertheless, we may still draw two lessons from Reisterstown and Winkler: in interpreting
There is no support for the claim that the Legislature, in attempting to encourage construction, favored construction of new homes over improvements. In Ridge Sheet Metal, the Court of Special Appeals reasoned that “[i]ncreasing the risk of double payment for the single family dwelling owner may well dampen the enthusiasm of the prospective house builder.” 69 Md.App. at 375, 517 A.2d at 1138. This analysis, however, was part of the court‘s discussion of “manifest fairness,” not legislative intent. Moreover, if Ridge‘s view were adopted, a family that has paid for building a new home on a vacant lot would not be subject to a subcontractor‘s lien, while a family such as the Brennens, having spent the same amount of money, will be in danger of losing their home through foreclosure on a mechanic‘s lien. Creating a risk of double payment for homeowners considering expensive improvements surely will not benefit the construction industry, which profits from improving homes. Because the Legislature has given us no indication that it wanted to encourage only one type of construction, we cannot ascribe to it an intent that would impede rather than encourage construction.
In light of the foregoing, we hold that
Dissenting Opinion by BELL, C.J., in which WILNER, J. joins.
We granted certiorari, Ridge Heating v. Brennen, 362 Md. 624, 766 A.2d 147 (2001), to consider whether
Historically, the mechanic‘s lien law, remedial legislation, see
Section
(f) Payments by owner to contractor after notice; limitation on lien against certain single family dwellings.—
* * *
erected on the owner‘s land for his own residence, to the extent that the owner has rendered payment to the contractor.” As reported in Winkler, supra, 355 Md. 231, 249, 734 A.2d 212, 222 (1999),
The Legislature chose to achieve its intended result in three ways, all of which fit together: (1) by amending
§ 9-104(a) to add as a condition to a subcontractor‘s entitlement to a lien for work or materials supplied in such a circumstance that the owner not have made full payment to the contractor prior to receiving the notice; (2) by adding§ 9–104(f)(3) , to provide that a lien may not exceed the amount of the owner‘s indebtedness to the prime contractor at the time the subcontractor‘s notice is given; and (3) by adding a new§ 9-114 , requiring that the prime contractor, at the time of settlement with or payment in full by the owner, give the owner a signed release from each material supplier and subcontractor who provided materials under the contract.
(3) Notwithstanding any other provision of this section to the contrary, the lien of the subcontractor against a single family dwelling being erected on the land of the owner for his own residence shall not exceed the amount by which the owner is indebted under the contract at the time notice is given. (emphasis supplied)
Thus,
The majority in the Court of Special Appeals broadly construed
[D]ivining an intent to distinguish between new construction and ‘erection’ of an addition to an existing structure is less plausible than the difference between home improvements, remodeling, and repairs as contradistinguished from new construction and building on an addition. Significantly, the legislature could have expressly excluded additions ‘erected’
or self-contained units added to existing improvements ‘erected on the land of the owner for his [or her] own residence’ had that been the intent underlying the enactment of the legislation.
The majority in this Court agrees with that result. Characterizing the phrase, “being erected,” as “anything but clear,” it being reasonable, they assert, to apply it “to many types of construction, including new homes, an addition to an existing home, or a home erected on an existing foundation after a disaster such as a fire,” 366 Md. at 342, 783 A.2d at 694, and noting its belief that, “in enacting
The position of the intermediate appellate court and of the majority of this Court is inconsistent with the plain meaning of the statutory language as well as other applicable canons of statutory construction.
The cardinal rule of statutory interpretation is to ascertain and to give effect to the intent of the Legislature. See Mayor and City Council of Baltimore v. Chase, 360 Md. 121, 128, 756 A.2d 987, 991 (2000); see also Oaks v. Connors, 339 Md. 24, 35, 660 A.2d 423, 429 (1995); Montgomery County v. Buckman, 333 Md. 516, 523, 636 A.2d 448, 451, (1994); Condon v. State, 332 Md. 481, 491, 632 A.2d 753, 755 (1993). The primary
The words of a statute are to be given their ordinary meaning. See Chase, supra, 360 Md. at 126, 756 A.2d at 990; see also Chesapeake and Potomac Telephone Co. of Maryland v. Director of Finance for Mayor and City Council of Baltimore, 343 Md. 567, 578, 683 A.2d 512, 517 (1996). In that regard, we have explained:
Where the statutory language is plain and unambiguous, a court may neither add nor delete language so as to ‘reflect an intent not evidenced in that language,’ Condon, supra, 332 Md. at 491, 632 A.2d at 755, nor may it construe the statute with “forced or subtle interpretations that limit or extend its application.” Id. (quoting Tucker v. Fireman‘s Fund Insurance Co., 308 Md. 69, 73, 517 A.2d 730, 732 (1986)). Moreover, whenever possible, a statute should be read so that no word, clause, sentence or phrase is rendered superfluous or nugatory. Buckman, supra, 333 Md. at 524, 636 A.2d at 452; Condon, supra, 332 Md. at 491, 632 A.2d at 755.
Chesapeake, supra, 343 Md. at 578, 683 A.2d at 517.
We have acknowledged that, in determining a statute‘s meaning, courts may consider the context in which a statute
We have further instructed:
Where the statute to be construed is a part of a statutory scheme, the legislative intention is not determined from that statute alone, rather it is to be discerned by considering it in light of the statutory scheme. State v. Crescent Cities Jaycees Foundation, 330 Md. 460, 468, 624 A.2d 955, 959. When, in that scheme, two statutes, enacted at different times and not referring to each other, Farmers & Merchants Bank v. Schlossberg, 306 Md. 48, 56, 507 A.2d 172,
176 (1986); Management Personnel Serv. v. Sandefur, 300 Md. 332, 341, 478 A.2d 310, 314 (1984), address the same subject, they must be read together, State v. Bricker, 321 Md. 86, 93, 581 A.2d 9, 12 (1990), i.e., interpreted with reference to one another, Schlossberg, 306 Md. at 61, 507 A.2d at 178; Bridges v. Nicely, 304 Md. 1, 10, 497 A.2d 142, 146 (1985), and harmonized, to the extent possible, both with each other and with other provisions of the statutory scheme. Balto. Gas & Elec. v. Public Serv. Commission, 305 Md. at 157, 501 A.2d at 1313. Neither statute should be read, however, so as to render the other, or any portion of it, meaningless, surplusage, superfluous or nugatory. Tracey v. Tracey, 328 Md. 380, 387, 614 A.2d 590, 594 (1992); D & Y, Inc. v. Winston, 320 Md. 534, 538, 578 A.2d 1177, 1179 (1990); Kindley v. Governor of Maryland, 289 Md. 620, 625, 426 A.2d 908, 912 (1981); Moberly v. Herboldsheimer, 276 Md. 211, 217, 345 A.2d 855, 858 (1975). In attempting to harmonize them, we presume that, when the Legislature enacted the later of the two statutes, it was aware of the one earlier enacted. Cicoria v. State, 332 Md. 21, 43, 629 A.2d 742, 752 (1993); Bricker, 321 Md. at 93, 581 A.2d at 12.
GEICO v. Insurance Com‘r, 332 Md. 124, 132-33, 630 A.2d 713, 717-18 (1993).
The critical question to be resolved in this case is whether
Every building erected and every building repaired, rebuilt or improved to the extent of 15 percent of its value is subject to establishment of a lien in accordance with this subtitle for the payment of all debts, without regard to the amount, contracted for work done for or about the building and for materials furnished for or about the building....
I agree with the petitioner,
Notes
(c)Machines, wharves, and bridges.—Any machine, wharf, or bridge erected, constructed, or repaired within the State may be subjected to a lien in the same manner as a building is subjected to a lien in accordance with this subtitle.
(d) Exemptions.—However, a building or the land on which the building is erected may not be subjected to a lien under this subtitle if, prior to the establishment of a lien in accordance with this subtitle, legal title has been granted to a bona fide purchaser for value.
Sections
(a) Notice required to entitle subcontractor to lien.—(1) A subcontractor doing work or furnishing materials or both for or about a building other than a single family dwelling being erected on the owner‘s land for his own residence is not entitled to a lien under this subtitle unless, within 120 days after doing the work or furnishing the materials, the subcontractor gives written notice of an intention to claim a lien substantially in the form specified in
subsection (b) of this section .(2) A subcontractor doing work or furnishing materials or both for or about a single family dwelling being erected on the owner‘s land for his own residence is not entitled to a lien under this subtitle unless, within 120 days after doing work or furnishing materials for or about that single family dwelling, the subcontractor gives written notice of an intention to claim a lien in accordance with
subsection (a)(1) of this section and the owner has not made full payment to the contractor prior to receiving the notice.
In
As we have seen, the majority concludes that
The majority‘s reliance on Tucker v. Fireman‘s Fund Insurance Co., supra, 308 Md. at 69, 517 A.2d at 730, is misplaced. There, the Court was required to construe “pedestrian” as used in
The majority‘s reading of
In fact, if the Legislature‘s intent was to have
Section
As noted,
As it does in connection with its interpretation of
Furthermore, although the majority holds that “the crucial distinction is between homes improved to the extent of 15% of
The majority‘s holding that the distinction is between residences improved by more than 15 percent of their value and those that are not, while I believe it not to be a proper interpretation of the statute, is fraught with significant difficulties in its application, not the least of which is the specter of a trial within a trial as to the value of the homeowner‘s residence as well as the relative value of the improvements. This is not productive of a simple and efficient application of
Finally, the cases on which the majority relies, Winkler, supra; Reisterstown Lumber, supra; Best Drywall, supra; F. Scott Jay & Co., supra; Grubb, supra, do not support its conclusion. Those cases have discussed
In none of those cases was the meaning of the phrase “being erected” presented to the court for resolution. And, rather than being in conflict with the construction urged by the petitioner and the dissenting judge in the intermediate appellate court, the cases are consistent. In Winkler, the Court ruled in favor of the subcontractor, holding that
Reisterstown Lumber, although characterized by the majority as one of two cases in which this Court recently “dealt” with
In selecting the standard, ‘for [the owner‘s] own residence,’ the General Assembly surely did not intend to put on the lien claimant the burden of demonstrating a predominant intent over the entire course of construction in order to avoid the residential exception. Indeed, it is difficult enough to establish intent at the moment of the res gestae in the prosecution of some crimes. A construction of
§ 9–104(a)(2) which is heavily dependent on subjective intent or on tracing, over a long period of time, the conduct of persons with whom the claimant has no privity would not allow liens to be established, or the residential exception to be applied, with relative simplicity.” reasoning “the General Assembly surely did not intend to put on the lien claimant the burden of demonstrating a predominant intent over the entire course of construction in order to avoid the residential exception.
Id. New construction was involved in this case, as to which Judge Rodowsky commented: “The problem presented by this case is of limited scope. It arises only when an owner is having a home built on the owner‘s land, and there is a change of plan.” Id. at 630, 574 A.2d at 311.
Contrary to the majority‘s view, these cases do not evidence a trend favoring homeowners although they do, as they must, acknowledge the purpose of the residential exception. In addition, to the extent the cases instruct courts to strike a fair and reasonable balance between the competing interests of homeowners and subcontractors, they also underscore that this balance may, on occasion, require that even the “residential exception” should be construed in favor of subcontractors.
The remaining cases on which the majority relies are simply unpersuasive. Two of them, see Best Drywall, supra; F. Scott Jay & Co., supra,5 are factually distinguishable from the case
In summary,
Judge WILNER joins in the views herein expressed.
