*1 HEATING, RIDGE AIR CONDITIONING PLUMBING,
AND INC. v. BRENNEN,
Robert et ux. S. Term, 2763, Sept.
No. 1999. Special Appeals Maryland. Court 13, 2000.
Nov. *2 brief), Boozer, P.A., on (Covahey DiPaula & Anthony J. Towson, appellant. for (Brown, LLP, Kearney, Kearney Diffenderffer &
J. Mitchell Baltimore, brief)-, appellees. for on the DAVIS, KENNEY, THIEME and JJ. before Argued DAVIS, Judge. 30,1998, Ridge Heating, Air appellant Condi- September
On Plumbing, Complaint Inc. tioning filed two-count appellees and Enforce a Mechanics’ Lien Establish P. Bremen the Circuit Robert S. Bremen Elizabeth 5, 1998, circuit County. On Court for Baltimore October J.) (Cadigan, court issued an to appel- Order Show Cause inquiring why lees the lien in the should amount claimed attach appellees’ property. Appellees filed a An- Verified 22,1998, swer on denying October liability grounds on the they were not general contractor, indebted to their Timber- (Timberwood). wood Construction
At the show hearing cause on November parties agreed, by Order, Consent that the matter should be course, set trial normal pursuant Maryland Rule 304(e)(2)(E), and that no final lien would be entered at that stage of proceedings. Following discovery, appellees filed Summary Motion for Judgment on May Appellant 1999. filed its Answer and Memorandum in Opposition to Motion for Summary Judgment.
On December the circuit court Opinion issued its granting Order appellees’ motion for summary judgment *3 judgment entered appellees favor of against appel- Appellant lant. timely filed this appeal, presenting ques- one tion, rephrase which we as follows:
Did the trial court err in applying § Real Property 9- 104(f)(3) of Maryland Code, limiting Annotated an own- liability er’s to a subcontractor performs who on work single owner’s family dwelling?
For the reasons forth set below appellant’s we answer question in negative and affirm judgment of the trial court.
FACTUAL BACKGROUND In December appellant contracted with Timberwood to furnish and heating install and air conditioning systems and to furnish and perform requisite work, plumbing part as of the overall construction of an addition to appellees’ residential Mills, home Owings Maryland. The contract between Tim- berwood and appellees provided that Timberwood would com- plete job by April appellees and that pay would progress payments, contract, set forth in totaling $153,085. 3, 1998 project August on be-
Timberwood abandonеd difficulties, with breaching appel- financial its contract cause of $9,000 for a substi- additional costs of Appellees lees. incurred improvements to complete contractor the unfinished tute a lawsuit Although appellant brought home. their invoices, appellant outstanding on its Timberwood collect appellees’ additionally sought impose mechanics’ lien it contract. for the amount owed under the Timberwood home Timberwood, had contracting appellant Prior to with least with and was aware of eight other contracts Timberwood history. Appellant’s records indicate Timberwood’s of payable appellant that Timberwood had accounts over ninety days past due. (1999 Repl.Vol., that
The trial court found Md.Code (R.P.) 9—104(f)(3) case, in this applies Supp.), Prop. Real appellees to subcontractor. Addi- limiting liability dispute trial ho as to tionally, the court found there was appellant prove appellees fact any material failed Therefore, appellees were were indebted Timberwood. enti- grant summary judgment. to a tled
LEGAL ANALYSIS 9—104(f)(3) that R.P. should not Appellant contends only to apply applies in this because the subsection new case family dwellings, improvements, not to construction additions, existing Appellees or renovations homes. contend construction of legislature that the did not intend narrow *4 9—104(f)(3) exception” §R.P. when it enаcted “residential liens; rather, applies to all home to mechanics’ statute solely being newly and not constructed. owners homes 9—104(f)(3) require- Property § Real refers to the notice provide initiating that a must when ments property: mechanics’ lien on an owner’s notice; (f) Payments by limita- owner contractor after dwellings.— against tion on lien certain this (3) section any provision other Notwithstanding single contrary, of the subcontractor the lien for land of the owner on the family dwelling being erected by which the amount shall not exceed his own residence at the time the contract is indebted under the the owner given. notice is 9-102(a) of its con- support § on R.P.
Appellant relies subject to a mеchan- may all be that not construction tention ics’ lien: rebuilt every building repaired,
Every building erected of its value is percent of 15 improved to the extent with this of a in accordance subject to establishment lien debts, regard to the of all without subtitle for the building amount, work for or about the contracted for done building, includ- for or about the and for materials furnished ing— the distinction legislature specifically
Because the included 9-102(a) “every “every building §R.P. erected” between appellant argues that building repaired, improved,” rebuilt or distinction in would have the same legislature included 9—104(f)(3) improvements R.P. if it had intended excep- in the residential existing homes were to be included 9—104(f)(3)reads, Instead, R.P. “a tion. fаmily dwelling being erected on the land single added.) The (Emphasis for his own residence.” section [or her] existing buildings to be language regarding contain does not “repaired, improved.” rebuilt
Although lien statute was enacted the mechanics’ upon proof of and materialmen 1976 to subcontractors v. Met nonpayment, generally, see Johnson performance (holding that a contractor 209 Md. calfe, performed); Ridge may amounts due based on work recover Morrell, Metal v. Sheet Co. (1986), “protect in 1982 to the law was amended liability. v. family dwelling” from Grubb
owner of a
*5
Abbott,
(1990).
84 Md.App.
Ridge,
1982 Md.
251,
1,1982).
July
Laws
effective
Grubb,
Subsequently,
accept
we declined to
a narrow
Grubb,
“single family
of
dwelling.”
generally
definition
See
393,
Md.App. at
Grubb,
at
Md.App.
(emphasis
Prior to we had that a had held subcontractor who paid by general not been the contractor could not establish mechanics’ lien of a owner payments prime because the owner owed no contractor at time pulled job the contractor out of the for financial Co., Ridge reasons. Sheet Metal 9—104(3)(f)
1133. The
behind R.P.
was to shift
risk
from
loss
the owner of a
dwelling to the
subcontractor. Id. at
Ridge, concerning
(a) At payment the time of settlement or in full between a owner, contractor and an give the contractor shall a signed supplier release of lien frоm each material provided subcontractor who work or materials under the contract.
(b) An subject owner is not to a lien and is not otherwise any liable for work or materials included the release (a) under subsection of this section. that subcon- responsibility insuring provision
This shifts contrac- away prime from the owner to the paid tractors are tor. added). (emphasis
Id. fairness, we argument as to Addressing the subcontractor’s follows: reasoned as appellees that unless we determine
Appellant asserts established, can be the subcontrac- and a lien are “indebted” impecunious prime contractor from the unprotected tor is otherwise uses the rather who and then breaches due over to the subcontractor. Were paying portion than interpretation that an unenforcea- accept appellant’s towe to “indebtedness” under the con- amounted obligation ble despite tract, would be liable to subcontractors owners still they paid over all monies were they fact that have *7 contract, fact despite under the obligated pay against go contractor could not back them prime that the interpretation not limit the retainage. This does for the it. liability but instead extends owner’s Moreover, can risk of loss in subcontractor best bear the clearly who is in the is of situation. One trade type this to know whether the contrac- рosition than owner better financially position. payments in a unstable Late tor is rumors in better materialmen and the trade áre other easily or are discoverable known to the subcontractor more Increasing the than the homeowner. the subcontractor risk double prospective of the house
may dampen well the enthusiasm builder.... 374-75,
Id. at
loss, said: we against
Additionally, subcontractor can itself A.I.A. easily under the contract. The standard very loss judice provided sub in the case contract used joint payee checks to right shall have the issue “[o]wner or materialmen as and such other subcontractors Contractor may necessary Owner deem in Owner’s sole discretion.” if it Appellant, anticipated suspected trouble or the contrac- measure, instability preventive tor of financial or as a could requested payable have the owner to issue progress checks prime to both the contractor and it for the work it did. Single family dwelling owners object have little reason to requests joint when that it be named payee for work request done since such a forestalls the possibility of a mechanic’s against lien levied their [sic] Thus, property. despite it is appellant’s protestations, not necessarily unprotected the impecunious contractor. from Moreover, unpaid subcontractor may always s%dt file against prime contractor to recover mollies due for 9-111, performed. work Section to 1982 and force still in effect, contemplates such a situation by providing
(n)othing this right any person, subtitle affects the any whom debt is due for work done or fur- material nished, to any personal maintain action the owner building any person other liable for the debt. Finally, contrary characterization, to appellant’s appellees unjustly were enriched presented. based the facts It appropriate appellees paid infer that to the contractor last progress payment the amount appel- allocable to lant for the work it performed percent. less 20 Appellees required would bе to pay twice for the work done should they have to pay appellant now or should a lien in full amount be established. *8 conclusion, we hold the owners were indebted under
the contract when the notice of to claim intent a lien was given, Hence, nor they unjustly were enriched. the subcon- tractor’s lien must fail. 375-77, added).
Id. at 517 (emphasis A.2d 1133 Similarly, held, Appeals the Court of in Reisterstown Lum- Tsao, (1990), ber Co. v. that, 319 Md. 574 A.2d 307 con- liberally be statute “should mechanics’ lien although the 9—104(f)(3) claimants,” § was R.P. in favor of lien strued Reisterstown Court statute. The created as 9—104(f)(3) § was to purpose of R.P. that the clear held payment to family dwelling from double single of a the owner A.2d 307. Id. at and subcontractor. the contractor R.P. exception in directly purpose of the Speaking Reisterstown, explained: 9-104, Appeals, § the Court with the residential particularly concerned But we are here current statute Ch. was added to the exception which is to purpose That clear exception’s Acts of 1982. of the family “single of a the owner payment double protect from land for his own on the owner’s dwelling being erected ... residence.” (f)(3), balance, potential the limit of the establishes per
That property of the owner imposed upon can lien which be lien cannot exceed The subcontractor’s a “residence.” In that way owner to the contractor. due amount receipt of payment. double On protected can be from owner is entitled intent to claim lien the the notice of to the. contractor “the payments from future draw withhold ascertains to be due the amount the owner 9-104(f)(l). If subcontractor estab- giving the notice.” lien, for the hen may take credit the owner lishes 9-104(f)(2). account with contractor. resolving the how much lien on the residence issue here is not The §in Thus, specified 9- time of the notice may be. 104(f) controlling.... is not is “a applies only where the construction special rule on the owner’s land family dwelling being erected on the could double produce own residence”
his the Tsaos. part of added). 628-31, (emphasis
Id. that, has “at no time asserts its brief Although appellant whether court been asked determine Maryland appellate 9-104(f)(3) hold- applies improvements,” home § R.P. consistently Appeals have of this and the Court ings Court
257
9—104(f)(8)
exception
construed the residential
of R.P.
in the
Reisterstown,
homeowner’s favor.
generally
See
Contrary
argument,
to appellant’s
of any
the absence
lan-
guage
regarding repairs
statute
or improvements does
countermand the
in protecting
concerns
the home-
owner. Our
decisions have
reiterated
the distinction
legislature
made in enacting the
exception
residential
was
a distinction
buildings
between commercial
dwellings, rather than
newly
between
built
existing
homes and
Grubb,
(“...
homes.
See
[legislature sought
...
family
opposed
as
protecting the commercial enterprise multiple family
dwell-
ings.”).
decision,
Grubb is instructive in our
because there the
building
owner was
improvement
likewise
or addition to his
existing family
Grubb,
holding
however,
home. Our
ad-
dressed
“single
whether
the term
family dwelling” would
include
apartment
so,
the addition of an in-law
and if whether
separate
construction of a
dwelling on
property
was
9-104(0(3).
covered
the residential
of R.P.
See
id. at
its the is protect to and matеrialmen overrid- law was subcontractors 9—104(f)(3) §R.P. by underlying the considerations den Grubb, with the status of specifically which dealt embraced an exception as to the mechanics’ lien statute. See the statute Gntbb, Lumber, In Md. at A.2d 307. Reisterstown by affixing apart- an in-law expanding that a house we held exception to lien to it would fall under the the mechanics’ ment law; distinguish is no construction of an there reason to something apart- than an in-law that results in other addition evolved, on issue have appellate As decisions this ment. emerged have more defini- policies behind the statute likewise (1) single family an a tively: protection of owner of dwelling from to the and subcontrac- payment primary double (2) Grubb, tor; limiting аs stated in and this Court to potential liability of an residence of exposure owner’s as to commercial enter- opposed protecting lien mechanics’ dwellings. argument advanced multiple family The prise of minority interprets “single family narrowly phrase being dwelling erected.” family interpreted “single dwelling” recently
Since we have apartment to of in-law include construction Grubb Reisterstown, that Appeals, has determined the Court not to move erected on his one who later decides into home covered, pellucidly, is these property or her nevertheless intent that interpretation legislative evince an decisions 9-104ffl(3) as distinguishing §R.P. is to be read between the owner, opposed drawing homeowner the commercial is a distinction between whether exception mechan- being “erected” “remodeled.” statute, view, protect was the owner ics’ lien in our enacted home, kind of regardless of the construction conducted his or her residence. position judice, appellant
In
case
in a better
sub
was
a financially
was in
appellees
than
know
Timberwood
fact,
knew,
position.
appellant
In
of Timberwood’s
unstable
history,
as it had several
con-
payment
particular,
previously,
noted
“the
As we have
Timberwood.
tracts with
easily under
very
loss
itself
can
1133. Armed
Ridge,
the contract.”
history,
financial
knowledge of Timberwood’s
appеllant’s
with
requesting ap-
its interest
protected
could have
appellant
both to Timberwood
payable
progress checks
pellees to issue
and this
Moreover,
Appeals
the Court
appellant.
purpose”
that “the clear
consistently underscored
Court have
homeowner
by the
is to avoid double
of the
owner of a
of loss from the
and to shift the risk
374-75,
The stated
behind the
exposure
personal
limit
residences
protect
family
subjecting
to avoid
enterprises,
as
opposed
commercial
liability
payment,
homeowners to
for double
and to shift the
subcontractor,
risk of loss from
the homeowner
who is
position
protect
by requiring
in a better
that
itself
agree
progress
to authorize the
draw payable to both
prime
Additionally,
Ridge
subcontractor.
Metal
Sheet
out,
points
generаl
is more familiar with the
contractor’s financial circumstances and better able to ascer-
collapse
tain when financial
quote
imminent. To
a maxim in
jurisprudence,
equitable
per-
“Whenever one of two innocent
third,
sons must suffer
the acts of a
he who has enabled
person
such third
to occasion the loss must sustain it.” Busey
Reese,
(1873).
v.
The 1982 amendment case law continue to pronounce the stated that subcontractors and material- however, protected; men be that rationale the homeowner general must bear the loss contractor when becomes insol- paying without vent his her subcontractors because the supplanted by homeowner received thе benefits has been subcontractors, requirement providing when labor or construction, materials residential simple precautions take interest, their being general the net result contractors would not projects be able “kite” their periods extended and fewer subcontractors and owners would “holding bag,” general be left because contractors who are Metal, impecunious simply Finally, would fold. in Ridge Sheet pointed we out that R.P. 9-104 did right not affect the personal maintain a against anyone, action including the owner *12 contractor, case, prime or the in which put the claimant is its of proving liability burden the for debt. The merely prohibits of encumbrance the residence with a mеchan- ics’ lien. reasons, foregoing
For the § in R.P. 9- 104(f)(3) narrowly should not be so as to construed be incon with sistent considerations behind the homeowner’s We, therefore, exception. appellant hold that cannot establish against a appellees’ single family lien for home the materials and performed furnished work and that trial court did not
261 liability 9—104(f)(3),limiting appellees’ §R.P. applying err lien. petition for mechanics’ appellant’s denying BALTI- FOR THE CIRCUIT COURT OF JUDGMENT AFFIRMED. MORE COUNTY BY APPELLANT. BE PAID TO
COSTS KENNEY, by J. Dissenting Opinion KENNEY, Judge, dissenting. policies within competing involves the collision
This case
those who
adopted
protect
law that
was
the mechanics’ lien
Abrams,
v.
Riley
in construction.
labor and materials
furnish
(1980).
legislature
348, 357,
Notwithstanding any provision other contrary, the lien of the subcontractor the oumer being erected on the land family dwelling amount which the residence shall not exceed the his own time the notice under the contract at the owner is indebted [Emphasis given. added.] Tsao, Md. In Lumber v. Reisterstown Co. (1990), recognized that the clear Appeals
A.2d 307
the Court of
9-104(f)(3)
purpose
is “to
from double
being erected on the
owner of ‘a
”
Property
9-
owner’s land for his own residence.’ Real
mind,
104(f)(3)
and, my
appropriately
liberally
has been
carry
perceived legislative
out
construed
our courts
however, in
acknowledged,
Ridge
This
Sheet
intent.
Court
Morrell,
364, 369,
decided, construction, dwelling occupy not to because after They ulti- cemetery. of a decided proximity of its view the Court occupy dwelling. question before mately *13 262 dwelling being being
was whether the
erected was still
erected
they
their residence after
decided not to live
the house.
problem
Acknowledging
presented
was of limited
scope,
in Reisterstown
language
the Court
focused on the
“for
§in
his own residence” found
9-104 and held that whether the
building is intended to be the owner’s residence is determined
as of thе time when the subcontractor commences an other-
substantially
for,
uninterrupted performance
wise
of work
or
to,
Reisterstown,
sells
contractor.
materials
The
finds
Md.App.
Grubb Contractors v.
84
384,
(1990),
“instructive,”
majority opinion
Grubb looked to Sheet involving case indebtedness, guidance issue of as to legislative intent. recently, Drywall More in Best v. Berry, (1996), we construed the term “residence” also to include vacation home. Both Ridge Sheet Metal and Best involved Drywall new construction.
It appears directly no case has decided the issue now before us: Is there a distinction to be made between new remodeling improving construction and an existing dwelling 9-104(f)(3)? application in the always, goal As our is to aim, general statute, purpose, determine the of and, although not to plain we are be enslaved meaning rule, starting point always our is of the statute. (1992). Tracey v. 328 Md. Tracey, A.2d 590 In our it analysis, important to examine the statute as а whole to *14 legislative Admin., divine the v. Hyle intent. Motor Vehicle (1997) (“In Md. 702 interpreting A.2d statute, whole, Appeals Court of construes statute as inter- preting provision in each of statute context of entire the scheme.”) statutory statute,
In reviewing the I following provisions, find the emphasized, instructive: (1974,
[Maryland Ann. Repl.Vol.)] Prop- Code 9-102 erty subject to lien.
(a) Buildings.—Every building erected and build- every rebuilt, ing repaired, or improved to the of 25 extent percent of subject its value is to establishment of a lien in debts, accordance with this subtitle for the of all amount, regard without to the for work contracted done for building or about the and for materials for furnished or about building, including drilling and installation of water, to supply wells the construction or installation any of swimming pool or fencing, sodding, seeding planting or shrubs, trees, or about premises any plants, or nursery products, flowers grading, filling, landscap- ing, and paving premises, of the leasing equip- ment, with or operator, without an for use for or about the building premises. or
(c) Machines, wharves, machine, bridges.—Any wharf, erected, constructed, bridge or repaired within the may subjected State be to a lien the same manner as a building subjected to a lien in accordance with this subtitle.
(d) Exemptions.—However, a building or the land on which the building may is erected subjected be to a lien if, under this subtitle establishment a lien subtitle, accordance with this legal title has granted been purchaser a bona fide for value. lien;
§ 9-104. requirement Notice for form (a) lien.—(1) Notice entitle required subcontractor A subcontractor doing work or furnishing or both materials family dwelling than a building
for or about other residence is owner’s land his own erected on the being for unless, within 120 to a lien under this subtitle not entitled materials, furnishing days doing the work or after an intention to claim a gives written notice of subcontractor (b) specified form in subsection substantially lien this section.
(2) furnishing materials or doing A work being erected on both or about a for own residence is not entitled to land his owner’s unless, days doing within 120 after lien under this subtitle furnishing materials for or about work or of an gives written notice inten- dwelling, the subcontractor *15 (a)(1) of in accordance with subsection tion to claim lien payment has not made full this section the owner receiving the notice. contractor
v [*] [*] (f)(3) Notwithstanding any of this section provision other against a contrary, the lien of the subcontractor on the land dwelling being erected amount his own residence shall not exceed the owner for is indebted under the contract the time which the owner given. the notice is executory in contracts. provisions
§ Prohibited 9-113. ' (a) executory a contrac- In contract between general.—An construction, that is related to any tor and alteration, structure, or repair building, improve- or aof not subcontractor to waive may require ment waive or to: right (1) lien; or Claim a mechаnics’ (2) on a contractor’s bond. Sue (b) to subcontractor on conditioning payment Provisions provision executory in an con- contractor.—A payment of a contractor and a subcontractor is tract between alteration, construction, or repair building, related to structure, payment and that conditions improvement or receipt by the contractor of the subcontractor any party may abrogate from or third the owner other or to: right waive the of the subcontractor
(1) lien; Claim mechanics’
(2) on a contractor’s bond. Sue
(c) provision of a contract made provisions.—Any Void public violation of this section is void as this State. lien, § to a 9- describing property subjected that can be 102(a) “every building “every refers to and to build- erected” ”
ing repaired, improved.... rebuilt or The value of the labor “building materials is not an issue the case of a erected.” It is material to a lien attach in the case of a whether will 9-102(c), repair, rebuilding improvement. or an on the Section hand, machines, other makes no distinction the case of Moreover, bridges. exemption wharves and created 9-102(d) bona purchasers fide value also makes no distinction existing between new construction and buildings long building subject pursuant so to a lien 9-102(a). §to 9-104, language the section which the limitation found, repeatedly
under review is out an carves buildings generally between and “a
being erected on the owner’s land for his
residence.”
own
added.)
(Emphasis
language closely
This
tracks the
*16
9-102(a)
me,
§of
implies,
applies
and
to
it
to new
9-104(f)(3)
If
§
construction.
intent was not to limit
to
new
construction,
purpose
“being
there was no
to the words
erect-
ed.” Those words could
from
provision
be excised
protect generally
the owners of
residences simi-
larly to
broad protection given
purchasers
to bona fide
9-102(d).
exemption
§
value
in
not to interpret
We are
clause, sentence,
in a
statute
manner that would render a
or
phrase “surplusage, superfluous, meaningless,
nugatory.”
or
(1996)
State v. Pagano, 341 Md.
Since the materialmen, that it Appeals repeatedly the Court of ruled interpreted comprehensive was to be the most liberal and Courts, however, had “no manner favor mechanics. cases, power beyond to extend the law to the obvious Although a designs plain requirements and of the statute.” significant change law in as Chief occurred recently repeated, interpreted it is still to Judge Gilbert be suppliers. in favor of mechanics and 369-370, (internal cita- Ridge, omitted). tions cases, could without preceding the statute be construed buildings language distinguishes
reference to between “being existing building being erected or and an erected” rebuilt, 9-104, repaired, improved. language § or both (a)(1) (2) provisions, in the notice and and in limitation (f)(3), consistently family to “a language refers dwelling being land for his own resi- erected the owner’s dence.”
Obviously, legislature any how to understands eliminate construсtion, linguistic existing distinctions between new 9-102(c) marine, wharf, (“any bridge § as demonstrated in or erected, 9-113 repaired”) constructed 9-113. Section contracts contractors and concerns between subcontractors construction, executory contracts “related to refers alteration, structure, repair building, of a or improvement.” 9-113(a) (b). clearly encompasses R.P. & That *17 noted, It is improvements. construction and home both new also, contracts created 9-113 prohibition that the to a right their requiring or subcontractors waive waiving of the contrac- obligation or to make the mechanics’ lien even upon payment by the tor to subcontractor conditioned the contractor, subcon- reinforces a owner the in this appellant tractors such as case. a distinction? One possible for such
Are there reasons In actually Ridge. Court explanation suggested may be a explaining why person the trades better contrac- general position than owner know whether the Court reflected financially position, tor is in a unstable [increasing risk of double dampen the enthusiasm of the
dwelling may well This in turn would further de- prospective house builder. starts, in a slow housing particularly crease market. (emphasis supplied).
Ridge, Md.App. at ‘Tfjor those unfamiliar with The Court went on to note that housing industry, housing number of starts is used as year.” predictor coming Ridge, for market conditions for the added). (emphasis fn. creating existing than for owners of protection Rather homes, designed jump start legislation may have been encourage support housing new home construction matter, legislature industry. Perhaps, practical as a be- homes, existing likely lieved that owners of who are more may during greater be on site construction and who have utilized, personal knowledge being of the contractor do not require protection buyer. the same as the new home end, course, may simply legislative it be a matter of oversight imprecise drafting. Obviously, we cannot know for sure, necessary I but do not believe it to be we do. and, narrowly
I interpret would the limitation based on the statute, Therefore, I appellant. of the find for the respectfully dissent.
