PULLMAN against W. AND T. CORNING
Court of Appeals of the State of New York
October, 1853
9 N.Y. 93
The judgment of the court below should should be reversed and a new trial granted.
DENIO, J., did not hear the argument.
All the other judges concurring,
Judgment reversed and new trial ordered.
PULLMAN against W. AND T. CORNING.
A person who has engaged to build a house for another in a good, skilful and workmanlike manner, at a price to be paid when the work should be completed, but who has done it in a negligent, unskilful and unworkmanlike manner, cannot recover the price agreed to be paid, nor anything for the work done, when the person for whom it was done has neither accepted the work, nor waived a faithful performance of the contract.
APPEAL from a judgment of the supreme court in the sevеnth district, in favor of the defendant. (14 Barb., 174.) The material facts in the case will be found in the opinion of JOHNSON, J.
The case was submitted on printed points by
T. Hastings for the appellant.
M. S. Newton for the respondents.
The other exception is taken to the statement of the witness Town, who said that he should not think the wall worth covering; and that the materials were worth more than the wall. This expression of opinion was objected to only upon the ground that witness was not a mason. It appeared that he had been a carpenter and house joiner by trade for twenty-two years, аnd had worked some on stone buildings, some on brick and some on cobble-stone, but mostly on wooden buildings. Under these circumstances I do not think he was less competent to express an opinion whether the wall was worth covering, or of less value thаn the materials employed in building it, than a mason would have been. Upon neither of these exceptions ought the report to be disturbed.
The report of the referee finds certain facts specially; upon which, as matter of law, judgment has been given for the defendant. To these determinations of law no exceptions appear, by the record, to have been taken as required by the Code of 1848, under which the case was tried, (
They also found the value of the good wall, exclusive of materials, to be.......................$161 60
The expense of taking down the bad wall,.... 57 00
__________
$104 60
That plaintiff did extra work on the building for defendants to ....................... 4 40
__________
Making the whole value of the plaintiff‘s work to the defendants,......................$109 00
subject to a deduction of such damages as defendants may have sustained by loss of the use of the building. If under these circumstances the plaintiff, who has substantially failed to perform his contract, and who does not even manifest a willingness to complete his undertaking by replacing his bad work with good, can compel the defendants to accept his work and pay for it what a jury shall say it is worth, it is not a little extraordinary.
In Champlin v. Rowley (18 Wend., 187), it was held that where personal property was delivered under a contract for the purchase of a larger amount than that delivered, at a price to be paid on the complete delivery, and there was no fault, acquiescence or waiver оf strict performance on the
The other cases in this state to which we were referred as sustaining the plaintiff‘s claim do not conflict with Champlin v. Rowley. Linningdale v. Livingston (10 John., 57) wеnt upon the ground that performance had become impossible by the act of the defendant. Jennings v. Camp (13 John., 94) decidedly favors the defendants’ position, and is not reconcilable with the plaintiff‘s recovery.
Jewell v. Schroeppel (4 Cow., 564) was put upon the ground that the defendant had by his сonduct waived all right to object to the plaintiff‘s performance on the ground that the work was not done in time. In the case at bar it is on the contrary found that no waiver existed.
The foreign cases cited are no more available. Oxendale v. Wetherell (9 B. & Cr., 386) was overruled expressly in Champlin v. Rowley; and Hayward v. Leonard (7 Pick., 181) and Smith v. Lowell (8 Pick., 178) stand upon the same ground with Britton v. Turner.
In Mead v. Degolyer (16 Wend., 632), all the cases up to that time are carefully considered; аnd although COWEN, J., dissented from the opinion of the court by BRONSON, J., yet both the judges agreed in their views of the law upon the point we are considering. This case occurred intermediate to the decisions of the supreme court and the court of errors in Champlin v. Rowley, and is valuable as showing that all the cases had been there considered.
Without spending more time upon the point, which we consider clear upon authority, we are of opinion that no recovery can be had for work done under a sрecial contract, where the work has neither been accepted, nor a faithful,
The judgment ought to be affirmed.
TAGGART, J. In this cаse substantial justice has been done to the parties, and it devolves upon the court to determine whether such justice has been meted out in accordance with the rules of law. The plaintiff contracted to put up the walls of a cobble stone house which the defendants designed constructing, and to put them up in a workmanlike manner and within a specified time. He did put up the walls within the time specified, but failed to do so in a workmanlike manner; but on the contrary, he constructed the sаme in so unskilful, negligent and unworkmanlike a manner, that by reason thereof the walls are cracked, warped and unsafe, and cannot be made good and safe walls without taking down and rebuilding two-fifths of the same.
The rule which requires a party for whom a рiece of work is to be done to accept the work in a state unfit for use, and to be at the trouble and expense of remodeling the work, and paying for what has been done (deducting the damages), is in many cases unjust and oppressive to the employer. Yet the opposite rule, viz., to reject the claim of the contractor entirely, might in many cases work great injustice. It is therefore difficult to draw the dividing line so as to establish any rule which shall be free from objection. Where the contract has not been substantially performed, the contractor cannot recover. Where it has been performed, but not in the time or manner specified, he can recover what the services are worth to the other pаrty, according to the price fixed by the contract; and the employer is compellable to pay for work which he is reluctant to use and ought not to be compelled to use. In a case such as this appears to be from the finding of the referee and the evidence, many men would greatly prefer the materials
The case of Jewell v. Schroeppel (4 Cow., 564) is the leading case in this state as to the right of the plaintiff to recover, where the work has been performed, but not in pursuance of the agreement. In that case, however, the agent of the defendant had accepted the work as completed, and did not object that any part of it was defective. In reference to the evidence on that point, Mr. Justice SUTHERLAND, who delivered the opinion of the court, says: “I аm inclined to think that this testimony, connected with other circumstances in the case, would authorize a jury to believe that a special agreement, of the nature stated in the declaration, was in fact made, but at all events it strengthens and cоnfirms the plaintiff‘s right to recover under the common counts. If the defendant intended to rescind the contract it was his duty then to have spoken.” In the case at bar it is expressly found by the report of the referee, that the work was not acceрted.
The case of Pike v. Butler (4 Comst., 360) is more like this case than any other we have found. A lease executed by Thomas C. Butler as lessor, and Elizabeth Parcels as lessee, contained a covenant on the part of the lessor, that if the lessee should erect upon the lot a brick dwelling-house corresponding in elevation with the house then on the premises, the lessor at the termination of the lease, or at the end of the second term if renewed, would pay to the lessee the value of the building, to be ascertained by three appraisers, not to exceed $2500. A brick building was erected on the premises, designed to be used and occupied as a cabinet-maker‘s shop, and not corresponding in height with the dwelling already on the premises, but the building sо erected was capable of
If, therefore, a building capable of being converted into a dwelling-house, according to the requirements of the lease, without any considerable delay or expense, as in the case of Pike v. Butler, does not authorize the court to grant relief, it is clear that the plaintiff in this case, who has constructed the walls in so unskilful, negligent and unworkmanlike a manner, that by reason thereof they are cracked, warped and unsafe, and cannot be made good and safe walls without taking down and rebuilding two-fifths of the same, is not entitled to recover, but, on the contrary, he should be dealt with precisely as though he had built but three-fifths of the walls in question. The contract was only three-fifths performed, and the plaintiff is not entitled to recover for what he has done. But it is said that the referee finds that the plaintiff performed extra work for the defendants to the value of $4.40, and the plaintiff was at least entitled to judgment for that sum. It does not appear whether the extra work was рerformed on that part of the work which it was necessary to have taken down, or on the other part. If on the former, the extra-work was of no value, and we will intend, in support of the judgment, that it was upon that part.
The objection to the testimony is not well taken. The witness Rich did not testify to any opinion on the subject,
The judgment should be affirmed, with costs.
DENIO, J., did not hear the argument.
All the other judges concurring in the above conclusions,
Judgment affirmed.
