16 Wend. 632 | N.Y. Sup. Ct. | 1837
Lead Opinion
The offer made by the defendant below for the purpose of effecting a settlement, was rejected by the plaintiff, and must therefore be laid out of the case.
The change which the defendant consented to make in the price to be paid for the timber, only modified the written contract in that particular. .In all other respects the agreement, and the rights of the parties under it, remained unaltered. The delivery of the whole quantity of timber, and by the specified time, continued, as they were before, to be conditions precedent to the plaintiff’s right to the price; except as to that portion which was payable on the delivery of each load, and that has been paid.
The contract afterwards underwent a further modification, by enlarging the time for the delivery of the timber. Although there was no express stipulation to that effect,
What then is this case ? The plaintiff agreed to deliver a large quantity of timber ; for which he was to be paid— ■except the part which he has already received—when the whole quantity should be delivered. He furnished a part of the timber, and then, without any excuse or apology whatever, stopped short; and now claims to recover for the timber actually delivered. The mere statement of the
The cases cited by the plaintiff’s counsel will not aid him. In Linningdale v. Livingston, 10 Johns. R. 36, the contract had been partially performed by the plaintiff in proper time, and after the day he offered to complete the work, but was prevented by the defendant. The court said that this put an end to the special contract, and the plaintiff might recover for the logs which had been delivered, under the general counts. In the case under consideration, the plaintiff has never offered to complete the performance of his contract, nor has he been prevented from doing so by any act of the defendant. Raymond v. Bearnard, 12 Johns. Rep. 274, turned on the same distinction. The plaintiff offered to. go on with the contract, but the defendant refused, on the ground that the plaintiff was in default. The court held that there was no longer any subsisting special agreement between the parties, and the plaintiff might recover back the money paid, under the common counts. In Dubois v. The D. & H. Canal Co., 4 Wendell, 285, the plaintiff had been prevented from performing the work in time by the act of the defendants, and it had, in fact, been performed, though after the day. It was also said that the special contract had been rescinded by the acts of the de-, fendants. But in this case, the plaintiff has neither performed on his part, nor is there any pretence that the defendant has done any act to put an end to the special agreement. The remarks of Sir James Mansfield, C. J., in
Some confusion has crept into the cases for the want of proper care in distinguishing between the right and the remedy—or in other words, between the cause of action and the mode of enforcing it. These are distinct considerations, and yet the language of judges, in relation to one branch of the subject, has frequently been quoted as an authority concerning the other. Where there is no dispute about the right of action, there may still be a question about the form of the remedy. One general rule in relation to special agreements for the performance of labor, delivery of materials, or the like, is, that so long as the contract continues executory, the plaintiff must declare specially ; but when it has been executed, he may declare generally—using only the appropriate common counts. This he may do although the
Whether we regard this as a question of pleading or one of principle, there is - no foundation for the present action. In all the cases where the plaintiff has been allowed to recover on the general counts for labor performed or materials furnished under a special contract, the work had either been actually executed, though with variation as to time or manner, or the special agreement had been rescinded—it was no longer in force. As a question of principle, it is impossible to uphold the action. The defendant has not only fully performed the agreement on his part, but he has done much more than could have been required of him. He has consented to an advance in price, and enlarged the time for the delivery of the timber. Neither before nor since the plaintiff’s default has he either done or said any thing to prevent the plaintiff from completing the execution of the contract. We have then the naked case of a man violating his own contract without cause, and then attempting to maintain an action against the injured party. To allow the experiment to succeed, would be both contrary to law and against good morals.
The following dissenting opinion was delivered :
Dissenting Opinion
It is clear the plaintiff below would have had no right to recover without strict performance, unless there had been a departure from the contract by mutual consent, express or implied. 13 Wendell, 258. The fact is clear, however, that the contract was departed from by mutual agreement; and yet the defendant below contends that he is entirely absolved from payment. He waived the time, he waived the price, he paid the money after the time, and finally sent in his account with the balance, after charging
The late case of Champlin v. Rowley, 13 Wendell, 258, certainly goes far enough for all necessary purposes of protection to vendees. That allows a man, where only part of the goods are delivered pursuant to the contract, that being entire, to- retain whatever shall have come to his hands without paying any thing. Former cases had repeatedly gone as far in respect to labor, and several English cases, even where materials had been found and applied to improvements on real estate. In the two latter cases, all return in kind would be impracticable. But wherever it was otherwise, as in the case of a vendee of portable articles, he was bound to return them, or else pay on a quantum valebant, though the vendor failed to perform. Oxendale v. Wetherell, 9 Barn. & Cress. 386. This case, however, stands expressly overruled in Champlin v. Rowley, and it strikes me very properly. The case at bar might have afforded, in its original shape, an illustration of its soundness. The vendee is in the course of receiving vendible articles in the line of his trade. He is certainly not bound to keep them on hand, to ascertain whether the vendor will deal honestly or falsely with him. He might have said to the plaintiff, “ Fulfil your contract as it stood, or I will pay you nothing.” That, we have seen, he did not do; and no case, in this or any other court, has gone1 so far, as to require the plaintiff to do what the defendant has himself waived. On the contrary, there are a multi
In the case at bar, we not only have an abundance in the acts of the parties pending the contract, from which to imply that they had changed it; but, as I said before, the defendant himself finally made out an account current, presenting those very principles of equitable adjustment on which the court below proceeded. It does not detract materially from the force of this evidence that the defendant intended it as a measure of com
In the case before us, the account was drawn out, as we .'have seen, crediting all the timber delivered and received, ■not at priees under the first contract, but the new one. In truth, the account is a solemn and deliberate admission of ■ every thing on the credit side. The only qualification is a debit for damages which were unliquidated, and therefore -open to negotiation. The paper was in other respects equivalent to a balance struck on the part of the defendant. It was saying, “ I owe the plaintiff for so much lumber at such a .¡price,” and the admission stood fortified by the whole course .of the transaction.
My opinion is, that the judgment below should be affirmed
The Chief Justice, however, concurring in the opinion delivered by Mr. Justice Bronson, that the judgment of the .mayor’s court ought to be reversed, it was accordingly r-s~ ¡parsed and a venire de novo awarded.