CHAD WENZLICK PRIDGEN, Plaintiff v. APPEN BUTLER HILL, INC., Defendant.
CIVIL NO. JKB-18-61
IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND
April 23, 2018
James K. Bredar, Chief Judge
MEMORANDUM
Plaintiff Chad Wenzlick Pridgen brought this action against Defendant Appen Butler Hill, Inc., in Maryland state court on October 20, 2017, and Defendant removed the case to this Court on January 8, 2018. (See Notice of Removal, ECF No. 1.) Before the Court is Defendant’s motion to dismiss Count IV of Plaintiff’s complaint. (Mot. Dismiss, ECF No. 10.) Plaintiff has responded in opposition (ECF No. 11) and Defendant has replied (ECF No. 13). The motion is therefore ripe for review. No hearing is necessary to resolve the matter. See Local Rule 105.6 (D. Md. 2016). Plaintiff may plead alternative and even conflicting claims for relief, and therefore Defendant’s motion to dismiss Count IV of Plaintiff’s complaint will be denied by accompanying order.
I. Background1
Plaintiff began working for Defendant as a Senior Auditor on August 8, 2010. (Compl. ¶ 10, ECF No. 2.) Plaintiff is homosexual, and “shortly after learning” this fact, Defendant began
Plaintiff brought this lawsuit against Defendant in the Circuit Court for Baltimore County on October 20, 2017. (See Notice of Removal ¶ 1.) Defendant removed the case to this Court on January 8, 2018, asserting federal question jurisdiction under
II. Standard
A complaint must contain “sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007)). The issues presented by the Defendant’s motion are almost entirely legal in nature, and, although the Court will accept all of Plaintiff’s factual allegations as true, this principle does not apply to legal conclusions. Twombly, 550 U.S. at 555.
III. Analysis
The Court will deny Defendant’s motion for a simple reason: even subcontractors deserve to be paid for their work. To explain why that principle settles this matter will take slightly more time, but not much.
Defendant contends that Plaintiff cannot bring both a quantum meruit claim under Maryland common law and a wage and hour claim under the FLSA, because the FLSA preempts Maryland law. Defendant is half right. The FLSA does, to an extent, preempt state law. See Anderson v. Sara Lee Corp., 508 F.3d 181, 194 (4th Cir. 2007). Generally speaking, “there is a strong presumption that Congress, in enacting the FLSA for the benefit of workers, did not intend to override the States’ traditional role in protecting the health and safety of their citizens,” and the FLSA “contains a ‘savings clause’ that expressly allows states to provide workers with more beneficial minimum wages and maximum workweeks than those mandated by the FLSA itself.” Id. at 193 (emphasis added) (quoting S. Blasting Servs., Inc. v. Wilkes Cty., NC, 288 F.3d 584, 590 (4th Cir. 2002)); see
Plaintiff has alleged that he is owed money under the FLSA, because he was an “employee” of the Defendant, but was improperly classified as a “sub-contractor,” who was not entitled to overtime. This claim—that Plaintiff is owed overtime under the FLSA because he was improperly classified—is an FLSA claim, regardless of what label one attaches to it. Such a claim must be brought under the FLSA’s enforcement scheme, and would preempt any state common law claim based on the same FLSA violation.
But Plaintiff may plead alternative, and even inconsistent, claims for relief. See
Defendant further argues that Count IV must be dismissed because of a purported contract between the parties. Defendant’s argument here fails for the same reason that Count IV will not be dismissed despite the alternative possibility of relief under the FLSA. Plaintiff cannot recover under the FLSA, as well as a common law claim of quantum meruit. And he cannot recover under a common law claim of quantum meruit if “the subject matter of the claim is covered by an express contract between the parties.” FLF, Inc. v. World Publ’ns, 999 F. Supp. 640, 642 (D. Md. 1998). But, Plaintiff can plead alternative theories of recovery, and they will not be dismissed at this early stage. See Roble v. Celestica Corp., Civ. No. 06-2934 (JRT/FLN), 2006 WL 3858396, at *3 (D. Minn. Dec. 29, 2006) (“While additional discovery may reveal that
IV. Conclusion
Plaintiff may plead alternative theories of relief in his complaint, and therefore the Court will not dismiss Count IV, and will deny Defendant’s motion to dismiss by accompanying order.
DATED this 23rd day of April, 2018.
BY THE COURT:
____________/s/________________
James K. Bredar
Chief Judge
