Pit River Tribe v. BlmPit River Tribe v. Blm
OPINION
Appeal from the United States District Court for the Eastern District of California
John A. Mendez, District Judge, Presiding
Argued and Submitted May 14, 2019
Seattle, Washington
Filed September 19, 2019
Before: William A. Fletcher and Morgan Christen, Circuit Judges, and Roslyn O. Silver,* District Judge.
Opinion by Judge Christen
SUMMARY**
Geothermal Steam Act / Federal Leases
The panel affirmed the district court‘s summary judgment in favor of Pit River Tribe and several environmental organizations in their action against federal agencies responsible for administering twenty-six unproven geothermal leases located in California‘s Medicine Lake Highlands.
Pit River alleged
Section 1017 of the GSA authorizes the Secretary of the Interior to approve cooperative or unit plans to manage multiple geothermal leases as a unit, and the Secretary must review such unit plans every five years and eliminate any lease not reasonably necessary for unit operations under the plan. Section 1005(a) of the GSA provides that geothermal leases on federal land have primary lease terms of ten years, and allows the leases to be continued for as long as geothermal steam is produced in commercial quantities. Section 1005(c) states that leases subject to “unit plans” may be extended even if not productive during the initial ten-year term under certain conditions.
The panel held that the statutory meaning of
COUNSEL
Samuel Lazerwitz (argued) and Caleb G. Wright (argued), Certified Law Students; Alicia E. Thesing, Isaac C. Cheng, and Deborah Ann Sivas, Supervising Attorneys; Environmental Law Clinic, Mills Legal Clinic at Stanford Law School, Stanford, California; for Plaintiffs-Appellees.
OPINION
CHRISTEN, Circuit Judge:
The Bureau of Land Management and the Department of the Interior (collectively, BLM) appeal the district court‘s order granting summary judgment in favor of the Pit River Tribe and several local and regional environmental organizations (collectively, Pit River). We have jurisdiction pursuant to
I. Background
Pit River filed this action against the federal agencies responsible for administering twenty-six unproven geothermal leases located in California‘s Medicine Lake Highlands. We refer to these leases as “unproven” because BLM has not determined that they are capable of producing geothermal steam in commercial quantities. See Pit River Tribe v. Bureau of Land Mgmt., 793 F.3d 1147, 1149–50 (9th Cir. 2015) (Pit River III).1 Calpine Corporation, the current leaseholder, was also named as a defendant but it did not appeal the judgment the district court entered on remand from our court. The operative complaint alleges that BLM‘s decision to continue the terms of the unproven leases for up to forty years violated the Geothermal Steam Act (GSA), the National Environmental Policy Act (NEPA), the National Historic Preservation Act (NHPA), and the Indian-fiduciary-trust doctrine.2 Id. at 1148.
The subject leases are located within the Glass Mountain Unit Plan. The parties agree that the GSA requires that any lease be allowed to continue if it is producing geothermal steam in commercial quantities, or is shown to be capable of doing so, within its primary ten-year term. See
II. Procedural History
This is the second time our court has addressed the controversy concerning the duration of the leases in the Glass Mountain Unit. See Pit River III, 793 F.3d at 1148. In July of 2013, the district court granted judgment on the pleadings in favor of BLM on the grounds that Pit River lacked prudential standing to assert its GSA claim. Id. at 1154–55. We reversed the district court‘s judgment, ruling that Pit River‘s claim fell within the GSA‘s “zone of interests,” id. at 1155–58, and we remanded to the district court so it could consider the merits of the claims.
On remand from Pit River III, the district court granted summary judgment in favor of Pit River. The court ruled that, as it was written in 1994, the GSA‘s primary term provision was unambiguous and did not authorize BLM to continue the twenty-six unproven leases for forty years simply because they were part of a unit that contained a single proven lease. The district court reasoned that because Congress referred to “unit plans” in
III. Standard of Review
We review de novo an order granting summary judgment. Cty. of Amador v. U.S. Dep‘t of the Interior, 872 F.3d 1012, 1020 (9th Cir. 2017).
IV. Jurisdiction
We must first assure ourselves of our jurisdiction to hear this appeal because the district court‘s order granting summary judgment vacated BLM‘s 1998 decision letters and remanded to the agency. See Pit River Tribe v. U.S. Forest Serv., 615 F.3d 1069, 1075 (9th Cir. 2010). “[R]emand orders are generally not ‘final’ decisions for purposes of
V. Discussion
A. The Geothermal Steam Act
This appeal requires us to interpret the GSA,
When Congress enacted the MLA, oil and gas were extracted under the common-law “rule of capture,” which encouraged landowners to drill wells on individual leases to capture as much oil or gas as possible. See Frank Sylvester & Robert W. Malmsheimer, Oil and Gas Spacing and Forced Pooling Requirements: How States Balance Energy Development and Landowner Rights, 40 U. Dayton L. Rev. 47, 49 (2015). The rule of capture encouraged overdrilling that dissipated reservoir pressure and ultimately led to inefficient oil and gas recovery. See Northcutt Ely, The Conservation of Oil, 51 Harv. L. Rev. 1209, 1219–22 (1938). The practice of unitization emerged in response to these inefficiencies. See Sylvester, et al., supra at 49–50. Unitization allows an entire oil or gas field “to be operated as a single entity, without regard to surface boundary issues,” see Norfolk Energy, Inc. v. Hodel, 898 F.2d 1435, 1438 (9th Cir. 1990) (internal quotation marks omitted), i.e., it allows drilling and production operations occurring on a single lease within a unit to be deemed performed on all other leases within the unit for purposes of showing that bona fide development efforts have been made, or for sharing royalties. See, e.g.,
The GSA refers to production-based “continuations” and drilling-based “extensions“—concepts articulated in the MLA—but neither the MLA nor the GSA explicitly define these terms. See
1. 30 U.S.C. § 1017 : The Unitization Provision
Section 1017 of the GSA authorizes the Secretary of the Interior to approve cooperative or unit plans to manage multiple leases as a unit “[f]or the purpose of properly conserving the natural resources of any geothermal pool, field, or like area.”
2. 30 U.S.C. § 1005 : The Lease Duration Provisions
Section 1005(a) of the GSA provides that geothermal leases on federal land have primary lease terms of ten years.
Neither
authorize one or two additional five-year extensions if the lessee has made certain bona fide efforts.8
if it was only previously extended pursuant to
B. The Glass Mountain Leases
Three years after Congress enacted the GSA, BLM promulgated regulations authorizing holders of geothermal leases to enter into unit agreements for the development of geothermal resources. See 38 Fed. Reg. 35,068, 35,073–75 (Dec. 21, 1973); see also
The twenty-six unproven leases at issue in this appeal—plus a twenty-seventh “proven lease” that BLM determined was capable of producing geothermal steam in commercial quantities—were eventually committed to the Glass Mountain Unit Agreement. Pit River III, 793 F.3d at 1149–51. The Agreement established a “Unit Area” and “Participating Area.” The Unit Area is the area comprised of all leases subject to the Agreement, and the Participating Area is the “part of the Unit Area which is deemed to be productive,” i.e., it is “all land then regarded as reasonably proved to be productive from a pool or deposit discovered or developed[.]” By the fifth anniversary of the Participating Area‘s effective date, the Agreement requires that all portions of unitized lands not entitled to be included in the Participating Area must be automatically eliminated from the Agreement and from the Unit Area, unless drilling operations are in progress on an exploratory well and these operations continue diligently.
In 1989, BLM determined that a single lease in the Glass Mountain Unit was capable of producing geothermal steam in commercial quantities. Pit River III, 793 F.3d at 1151. In 1991 and 1992, at the request of Calpine‘s predecessors, BLM‘s California State Office extended the terms of twenty-four
In 1995, BLM sent Calpine‘s predecessor a letter stating that the predecessor was “in default of meeting reasonable diligence in the unit,” and that the Glass Mountain Unit was “no longer of any significant benefit to the BLM or Forest Service” because “[t]he unit has become an impediment to development by causing operators to select drilling targets on the basis of whether a lease is or is not committed to the unit instead of the area with the greatest potential to support a development project.” On June 3, 1996, BLM notified Calpine‘s predecessor via an additional letter that a proposed Participating Area should have been submitted in 1989, but that due to agency delay and other circumstances, BLM would allow submission of a proposed Participating Area within sixty days of receipt of the letter. Calpine‘s predecessor submitted a proposed Participating Area on August 15, 1996.11
BLM‘s California State Office changed its interpretation of
On May 18, 1998—five days after Hagerty circulated his memo—BLM‘s California Office issued decision letters vacating the 1991 and 1992 lease extensions for the unproven leases and continuing them for
C. Statutory Analysis
It is clear that the GSA authorizes “continuations” based on production, see
“We interpret a federal statute by ascertaining the intent of Congress and by giving effect to its legislative will[,]” beginning with the statute‘s language. Artichoke Joe‘s Cal. Grand Casino v. Norton, 353 F.3d 712, 720 (9th Cir. 2003) (internal quotation marks omitted). We “presume that [the] legislature says in a statute what it means and means in a statute what it says.” BedRoc Ltd., LLC v. United States, 541 U.S. 176, 183 (2004) (internal quotation marks omitted). “The plainness or ambiguity of statutory language is determined by reference to the language itself, the specific context in which the language is used, and the broader context of the statute as a whole.” Geo-Energy Partners-1983 Ltd. v. Salazar, 613 F.3d at 956 (internal quotation marks omitted). If “the language is not dispositive, we look to the congressional intent revealed in the history and purposes of the statutory scheme.” Artichoke Joe‘s, 353 F.3d at 720 (internal quotation marks omitted). “[I]f we find that the statutory meaning is plain and unambiguous, then our ‘sole function . . . is to enforce it according to its terms.‘” Hernandez v. Williams, Zinman & Parham PC, 829 F.3d 1068, 1072 (9th Cir. 2016) (alteration in original) (quoting United States v. Ron Pair Enters., 489 U.S. 235, 241 (1989)); see Chevron, U.S.A., Inc. v. Nat. Res. Def. Council, Inc., 467 U.S. 837, 842–43 (1984) (“If the intent of Congress is clear, that is the end of the matter; for the court, as well as the agency, must give effect to the unambiguously expressed intent of Congress.“).
We begin with the GSA‘s text, and observe that
It is a well-established canon of statutory interpretation that the use of different
words or terms within a statute demonstrates that Congress intended to convey a different meaning for those words. Congress‘s explicit decision to use one word over another in drafting a statute is material. It is a decision that is imbued with legal significance and should not be presumed to be random or devoid of meaning.
SEC v. McCarthy, 322 F.3d 650, 656 (9th Cir. 2003) (internal citations omitted). “[W]hen Congress includes particular language in one section of a statute but omits it in another section of the same Act, it is generally presumed that Congress acts intentionally and purposely in the disparate inclusion or exclusion.” Barnhart v. Sigmon Coal Co., 534 U.S. 438, 452 (2002) (internal quotation marks omitted). We conclude that the use of “unit plan” in
BLM argues that Congress‘s omission of the term “unit plan” from
BLM argues that the MLA provides important context and that the incorporation of the unitization principle into the MLA suggests Congress intended to adopt the same statutory scheme for the GSA. We disagree. Congress enacted the MLA decades before it enacted the GSA, and we assume Congress is knowledgeable about existing law when it enacts new legislation. See Miles v. Apex Marine Corp., 498 U.S. 19, 32 (1990); see also Cty. of Amador, 872 F.3d at 1022 (“[U]nderstanding the historical context in which a statute was passed can help to elucidate the statute‘s purpose and the meaning of statutory terms and phrases.“). The GSA‘s sponsor understood the 1970 bill to generally permit the Secretary of Interior to lease public lands in “much the same manner” as the Secretary was authorized to do by the MLA. S. Rep. No. 91-1160, at 4 (1970). But Congress recognized that efforts to harness geothermal steam in an emerging market posed unique challenges. See H.R. Rep. No. 91-1544, at 3–4 (1970). By 1970, the MLA was in its fiftieth year of regulating oil and gas leasing but the geothermal steam industry was still in its infancy. Congress acknowledged that the mining and mineral leasing statutes “lack many of the requirements necessary to encourage [geothermal steam‘s] orderly development.”
production.”13 S. Rep. No. 91-1160, at 8. Contrary to BLM‘s argument, the text of the GSA, read as a whole, demonstrates that Congress deviated from the MLA when it adopted the GSA, perhaps because it was aware of the need to accommodate the uniquely-situated geothermal steam technology and developing market.
A comparison of the GSA‘s primary term provision,
BLM goes on to argue that the GSA provision authorizing unit plans,
basis because
BLM next argues that the following language in
Any geothermal lease issued pursuant to this chapter for land on which, or for which under an approved cooperative or unit plan of development or operation, geothermal steam has not been produced or utilized in commercial quantities by the end of its primary term, or by the end of any extension provided by subsection (c) . . . may be extended for successive 5-year periods[.]
we are not persuaded. BLM‘s reasoning overlooks the most straightforward reading of the statute: Regardless of the combination of primary term, continuations or extensions, Congress capped the terms of geothermal leases at fifty years. Consistent with this scheme, leases that receive forty-year continuations under
BLM also argues that because GSA
exploration on all leases to define the contours of the productive area during the primary term. The decision not to incorporate unit-wide continuations during the primary term still allows leaseholders to benefit from unitization through cost and royalty sharing. It is also consistent with
BLM‘s final argument is that
Section 6 of the bill provides that each geothermal lease shall be for a primary term of 10 years. If steam is produced or utilized in commercial quantities within this term the lease will continue for so long thereafter as such production or utilization continues, but not to exceed an additional 40 years. If at the end of such 40 years steam continues to be produced in commercial quantities, and the
land is not needed for other purposes, the lessee is given a preferential right to a renewal of the lease for a second 40-year period in accordance with such terms and conditions as the Secretary deems appropriate. Comparable provision is also made respecting lands leased for development under approved cooperative and unit plans.
H.R. Rep. No. 91-1544, at 7 (1970) (emphasis added). BLM argues that the “comparable provision” for leases committed to unit plans must be
VI. Conclusion
The statutory meaning of
AFFIRMED.
Notes
actual drilling operations were commenced prior to the end of its primary term and are being diligently prosecuted at that time shall be extended for five years and so long thereafter, but not more than thirty-five years, as geothermal steam is produced or utilized in commercial quantities.
(1) Any geothermal lease issued pursuant to this chapter for land on which, or for which under an approved cooperative or unit plan of development or operation, geothermal steam has not been produced or utilized in commercial quantities by the end of its primary term, or by the end of any extension provided by subsection (c) of this section, may be extended for successive 5-year periods, but totaling not more than 10 years, if the Secretary determines that the lessee has met the bona fide effort requirement of subsection (h) of this section, and either of the following:
(A) [T]he payment in lieu of commercial quantities production requirement of subsection (i) of this section.
(B) The significant expenditure requirement of subsection (j) of this section.
(2) A lease extended pursuant to paragraph (1) shall continue so long thereafter as geothermal steam is produced or utilized in commercial quantities, but such continuation shall not exceed an additional 25 years, for a total of 50 years, if such lease was also the subject of an extension under subsection (c) of this section or an additional 30 years, for a total of 50 years, if such lease is only extended pursuant to paragraph (1).