ADRIAN NILES vs. HUNTINGTON CONTROLS, INC., & another.1
No. 16-P-229
Appeals Court of Massachusetts
January 12, 2017. - July 31, 2017.
Kafker, C.J., Hanlon, & Agnes, JJ.
Norfolk. Practice, Civil, Summary judgment. Labor, Public works, Wages. Public Works, Wage determination. Administrative Law, Wage administration.
NOTICE: All slip opinions and orders are subject to formal revision and are superseded by the advance sheets and bound volumes of the Official Reports. If you find a typographical error or other formal error, please notify the Reporter of Decisions, Supreme Judicial Court, John Adams Courthouse, 1 Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-1030; SJCReporter@sjc.state.ma.us
Practice, Civil, Summary judgment. Labor, Public works, Wages. Public Works, Wage determination. Administrative Law, Wage administration.
Civil action commenced in the Superior Court Department on November 22, 2013.
Motions for summary judgment were heard by Thomas A. Connors, J.
Joseph L. Sulman for the plaintiff.
Stephen P. Kolberg for the defendants.
AGNES, J. The Massachusetts prevailing wage law,
In the present case, Adrian Niles filed a four-count complaint in the Superior Court alleging a violation of the prevailing wage law (count one), breach of contract (count two), breach of the covenant of good faith and fair dealing (count three), and unjust enrichment (count four). The judge allowed a motion for summary judgment filed by the defendants, Huntington Controls, Inc., and its president, Paul Milano (collectively, Huntington), on all four counts and denied Niles‘s cross motion for partial summary judgment on liability under count one. Niles appealed. The sole question presented is whether the judge was correct in ruling that Huntington did not violate the prevailing wage law because none of the work performed by Niles for Huntington was subject to the prevailing wage law. We conclude that the judge erred in failing to give appropriate deference to opinion letters issued by the department that stated that the work performed by a heating, ventilation, and airconditioning (HVAC) technician such as Niles, who, while onsite, installs software in HVAC components and then tests those components to ensure that they operate properly, is employment “in the construction of public works” and thus is subject to the prevailing wage law. Because it is undisputed on the record before us that at least some of the hours worked by Niles for Huntington involved such activity, it was error to deny his motion for partial summary judgment and to grant summary judgment to Huntington on count one.3
Background. The essential facts are not in dispute. In September, 2009, Niles began working for Huntington as a non- union,
Although the parties do not agree as to all the work activities that were performed by Niles as an HVAC technician, it suffices to say, as the judge below recognized, that at least some of the duties he performed were onsite and included downloading programs to the HVAC system controllers and performing certain tests required to ensure the controllers worked properly. For example, Niles would use a program to turn exhaust fans on and off, in order to ensure that they operated as intended when they received the proper signals. There is evidence that occasionally he would “switch out” a malfunctioning component with one that worked.5 It is undisputed that the majority of the hours Niles worked on the two school projects were identified by Huntington as work performed under the service code “1-003, Tech/Commissioning.”6 It is also undisputed that he performed this work on those systems after the components were installed and wired by the electricians, but before they were turned over to the customer for operation. There was evidence that another subcontractor also performed testing services after Huntington completed its work.
At least once, prior to turning over the systems to the customer, Huntington required Niles to be onsite to “go over our punch list
Discussion. 1. Standard of review. We review a grant of summary judgment de novo, Federal Natl. Mort. Assn. v. Hendricks, 463 Mass. 635, 637 (2012), to determine “whether, viewing the evidence in the light most favorable to the nonmoving party, all material facts have been established and the moving party is entitled to a judgment as a matter of law.” Augat, Inc. v. Liberty Mut. Ins. Co., 410 Mass. 117, 120 (1991). “The entry of summary judgment will be upheld when there are no genuine issues of material fact and the nonmoving party ‘has no reasonable expectation of proving an essential element of its case.‘” Okerman v. VA Software Corp., 69 Mass. App. Ct. 771, 780-781 (2007), quoting from Miller v. Mooney, 431 Mass. 57, 60 (2000). In deciding a motion for summary judgment the court may consider the pleadings, depositions, answers to interrogatories, admissions on file, and affidavits. Community Natl. Bank v. Dawes, 369 Mass. 550, 553 (1976).
2. The department‘s opinion letters. The commissioner sets the prevailing wages based on “collective agreements or understandings in the private construction industry between organized labor and employers.”
The department, in response to inquiries, issues opinion letters stating whether certain jobs are subject to the prevailing wage law.9 The department issued one such opinion letter on June 11, 2008, in response to an inquiry whether the prevailing wage law applied to a company‘s HVAC control technicians. The job description at issue stated that a controls technician was responsible for “repair and modification of environmental-control systems, utilizing knowledge of electronics, direct digital control, HVAC theory, and control applications.” In relevant part, the letter stated:
“As we understand it, after a new system has been installed, or an existing system is replaced in whole or in part, the system must undergo testing, adjusting and balancing (TAB), and commissioning (in the case of a new system) or re-commissioning (in the case of a replacement project). . . . The important point seems to be that installation or replacement of a system involves much more than simply installing a ‘system’ and cleaning up. Such construction work is incomplete unless the owner has the assurance that the system purchased actually works as designed, and this assurance is provided by both the TAB and commissioning processes. Therefore, this agency will consider installation/replacement, TAB, and recommissioning and commissioning of an HVAC system to be all part of the same ‘construction’ work
within the meaning of the statute.”
That letter also discussed aspects of the job to which the prevailing wage law did not apply, such as contacting customers, attending training, and offsite work.
Subsequently, in an August 18, 2009, opinion letter, the department further stated that job descriptions involving “the programming and downloading of software and installation and commissioning of electronic direct digital controls (DDC) for HVAC systems in buildings” fell under the prevailing wage law. Specifically referencing the June 11, 2008, opinion letter, the 2009 letter stated that “[t]here is no question that the installation of HVAC systems, including commissioning and re-commissioning and testing and balancing of the HVAC system[,] is ‘construction’ within the meaning of the statute and covered by the provisions of
The judge below noted that Niles “failed to support his contentions that his work constitutes prevailing wage work by pointing to facts in the record.” Specifically, the judge noted that “[t]he work that [Niles] performs does not fit under ‘construction’ as defined by the prevailing wage law,” because “[his] work as a controls technician does not fall under any of the relevant CBAs [collective bargaining agreements], and therefore cannot be prevailing wage work.”10
Courts customarily defer to an administrative agency‘s interpretation of its governing statute unless that interpretation is inconsistent with the statute or it purpose. See Mullally, 452 Mass. at 533 (Department of Labor‘s opinion letter that defendant violated prevailing wage law entitled to deference because it was not contrary to “plain language of the statutes or their underlying purposes“). See also Swift v. AutoZone, Inc., 441 Mass. 443, 450 (2004), quoting from Massachusetts Hosp. Assn. v. Department of Med. Sec., 412 Mass. 340, 345-346 (1992) (“In general, we
3. Scope of “construction” work under G. L. c. 149, § 27. For purposes of the prevailing wage law, the term “construction” includes “additions to or alterations of public works.”
In reviewing the record, the judge correctly noted that there was no dispute that some of the work performed by Niles “involved downloading a program into every HVAC controller and verifying that those programs are working properly.” However, because the work performed by Niles took place after a licensed electrician had installed the wiring, the judge erroneously concluded that it was “postinstallation” work and for that reason was not work that qualified as “construction” work within the
4. Establishing a job classification and pay rate for an HVAC technician. It is undisputed that the work performed by Niles did not all come within the job classifications for licensed electricians or pipefitters that appear in the relevant collective bargaining agreements. Niles is not a licensed electrician. Furthermore, as the judge noted, there is no dispute that the work performed by Niles did not involve the installation of the physical components of the HVAC system, which was handled by licensed electricians, or the handling and installation of tubing and sheet metal as performed by pipefitters. However, the department‘s two opinion letters that are before us address this question as well. The department states, in its August 18, 2009, letter, that “the relevant question is whether the work performed on the job site falls within the scope of work that is covered by a collective bargaining agreement.” In its June 11, 2008, letter the department states that “the collective bargaining agreements with the pipefitters union cover the commissioning of HVAC systems as described. Union pipefitters perform HVAC commissioning on job sites in Massachusetts, and are trained in commissioning processes through their apprentice training program. Therefore, the proper
Conclusion.
For the reasons stated above, the judge erred in allowing Huntington‘s motion for summary judgment on count one and in denying Niles‘s motion for partial summary judgment as to liability on count one. We hold that the work performed by an HVAC technician such as Niles who, while onsite, downloads and installs software into HVAC components and then tests those components to ensure that they operate properly is employment “in the construction of public works” and thus is subject to the prevailing wage law. Consequently, the judge should have allowed Niles‘s motion for partial summary judgment as to count one. Because there are material facts in dispute as to the number of hours Niles performed “construction” work, as opposed to other kinds of work for Huntington, the case must be remanded to the Superior Court.
Insofar as the judgment dismisses count one, it is vacated, and the case is remanded for entry of an order allowing the plaintiff‘s motion for partial summary judgment as to liability on count one and for further proceedings on count one consistent with this opinion. In all remaining respects the judgment is affirmed.
So ordered.
