NAR Businees Park, LLC v. Ozark Automotive Distributors, LLCNAR Businees Park, LLC v. Ozark Automotive Distributors, LLC
MEMORANDUM OPINION AND ORDER
Before the Court are Defendant’s motion for summary judgment [95] and Plaintiff’s cross-motion for partial summary judgment [105] on Plaintiff’s Counts I and II; Plaintiff’s [113] and Defendant’s [115] cross motions for summary judgment on Defendant’s two counterclaims; and Plaintiff’s motion for leave to file a sur-reply [111]. For the reasons set forth below, the Court grants Defendant’s motion for summary judgment [95] on Plaintiff’s Counts I and II, and judgment is accordingly entered in Defendant’s favor on those counts. The Court also grants Plaintiff’s motion for leave to file a sur-reply [111]. Plaintiff’s partial cross motion for summary judgment [105] on Count I is denied. Plaintiff’s and Defendant’s respective cross-motions for summary judgment [113, 115] on Defendant’s Counterclaims I and II are each granted in part and denied in part. Judgment is entered in Plaintiff’s favor and against Defendant on Defendant’s Counterclaim II. The case is set for further status on January 15, 2020 at 9:00 a.m.
I. Background
The Court takes the relevant facts from the parties’ Local Rule 56.1 statements of undisputed material facts and supporting exhibits: [57], [72–73], [77], [79-1–7], [80], [85], [97], [103], [106], and [108–10]. The Court construes the facts in the light most favorable to the nonmoving party on any given issue. The following facts are undisputed unless otherwise noted. “When we cite as undisputed a statement of fact that a party has attempted to dispute, it reflects our determination that the evidence
Plaintiff NAR purchased a large parcel (“Parcel“) in Naperville, IL in 2006 or 2007. [103 at 3, ¶ 12.] The topographically low-lying land was, at the time, used for farming. [Id.] Roughly contemporaneously, Plaintiff contracted with Naperville to excavate another (unrelated) site. [Id., ¶ 13.] Killing two birds with one stone, Plaintiff transported the excavated land to the Parcel, filling it in. [Id.] The extent to which Plaintiff measured the soil density in the Parcel is disputed, as are the measures taken to ensure that the land was properly filled. [Id., ¶¶ 14–15.] The quality of excavated soil taken from the other parcel is also in dispute. [108 at 3, ¶ 5.]
Plaintiff contracted with Ozark Automotive Distributors1 on September 17, 2012; it agreed to sell the Parcel for $5,171,400. [103 at 2, ¶ 10.] The parties also agreed, however, that a condition precedent to the land sale was a construction contract. [Id.] The construction contract contemplated a 400,000 square foot automotive distribution center upon the empty Parcel. [Id.]; [Id., ¶ 8.] Defendant’s distribution centers receive and ship inventory to Defendant’s retail stores; these centers generally service dozens of stores. [80 at 8, ¶ 13.]
Before the construction contract was executed, Defendant hired a geotechnical engineering consultant, Terracon Consultants, Inc. (“Terracon“), to test the soil and determine the feasibility of completing a construction project on the Parcel. [103 at 4, ¶ 16.] Terracon tested 24 soil-depths at various locations on the Parcel and submitted a report on March 15, 2013 that summarized its findings. [Id. at 5, ¶ 17]; see also generally [97-6]. Terracon was concerned about the existing fill, finding that the “composition, moisture content and standard penetration test blow counts * * * were variable” and therefore unsuitable for laying foundations for the construction project. See [97-6 at 10]; see also [103 at 5, ¶¶ 18–19]. Terracon recommended that the foundation not be built on the existing fill, and instead opined that “excavations for the building foundations should extend through the fill to the underlying native soils.” [103 at 5, ¶ 18]. Terracon also recommended that if these excavations uncovered soft or low-density native soils, then the native soils should be excavated until “suitable bearing soils” were uncovered. [103 at 5, ¶ 19]. The Terracon Report was included in the bidding documents, and Plaintiff admits that it received the report and never objected or requested clarification. [103 at 5–6, ¶¶ 20–21.]
Plaintiff and Defendant executed a construction contract on July 2, 2013. [103 at 3, ¶ 8.] The contract consisted of the “Lump Sum Contract,” an addendum, General Conditions, and various architectural Specifications. [72 at 3, ¶¶ 8–9]; [103 at 5, ¶ 21.] The default provisions of the contract placed the risk of loss on Plaintiff: “Contractor at its sole cost, risk, and expense shall construct, supply equipment, provide, purchase, pay for, and furnish all of the Work in accordance with the Contract Documents.” [57-1 at 22, Art. 2.] In exchange for providing construction services, Plaintiff was to receive $21,309,412.21. [97-1 at 4, Art. 4.] The parties do not dispute that the contract incorporated structural engineering and architectural “Specifications.” [103 at 5, ¶ 21.] Those Specifications, in turn, incorporated the Terracon Report by reference, requiring that the Terracon Report “be included
Plaintiff began work on the project on August 20, 2013. [72 at 3, ¶ 11.] Almost immediately, Plaintiff ran into trouble with the fill. [103 at 9, ¶ 32.] On August 28, 2013, Plaintiff formally requested that Defendant increase the contract sum in light of the extensive excavations (also called “undercuts“) required to conform to the Terracon Report. [Id. at 8–9, ¶¶ 30-31]. Two days later, Defendant responded that it would not modify the contract sum because the recommendations of the Terracon Report were well-known when the contract was signed and incorporated by reference as part of the contract itself. [Id., ¶¶ 32–33.] Plaintiff again sought to increase the contract sum in light of the undercutting in September 2013 and was again rebuffed. [Id., ¶ 34]. Plaintiff completed the excavations and continued with its construction. See [108 at 10–12, ¶¶ 19–20, 22, 24.] It is undisputed that in other instances, the contract sum was increased by over $1,000,000 for various changes and modifications. See, e.g., [110 at 2].
Plaintiff had 365 days to complete the work—that is, until August 20, 2014. See [97-1 at 3, Art. 3.1]. Unfortunately, not all of the project components were completed on time. The parties do not dispute that as of August 20, 2014 Plaintiff had not done the following: (1) completed a sidewalk (or issued a bond to the city of Naperville in lieu of completing the sidewalk); (2) completed some landscaping work; (3) repaired an adjacent road; (4) completed an entrance for a neighboring facility; (5) paved a cul-de-sac; and (6) repaved part of a parking lot. [80 at 4, ¶ 10.] The parties dispute whether Plaintiff should be held liable for these delays. [Id., ¶ 9]. The parties also agree that two other tasks—fixing a problem with the “hazardous room” and finalizing the “record drawings“—were outstanding and delayed certification but disagree whether they were within Plaintiff’s or Defendant’s responsibilities.2 Regardless, a permanent Certificate of Occupancy (CO) was not issued until December 15, 2015. [80 at 7, ¶ 11.] During this lag-time, Defendant sent three letters to Plaintiff complaining that the work had not been substantially completed, and (in some letters) outlining the outstanding work. [73 at 85–91.] Notwithstanding Plaintiff’s delays in getting the permanent CO, Plaintiff was able to obtain a temporary CO on August 26, 2014 (that is, less than a week after the Contract
In July 2017, Plaintiffs sued Defendant in state court for breach of contract,3 arguing that the extensive undercutting was not within the scope of work. Plaintiffs now seek $334,486.07 for its undercutting work.4 [104 at 14.] Plaintiff also seeks $103,487.36 that Defendants have withheld in partial satisfaction of its liquidated damages counterclaim (discussed below). Defendant removed to federal court [1] and counterclaimed to enforce the liquidated damages provision in the contract: Defendants seek $2,000 for each day that the permanent CO was delayed after August 20, 2014—483 days (and $966,000) in all. [41 at 16, ¶¶ 13–14.] Defendant also wants Plaintiff to indemnify it for any losses it may accrue in Plaintiff’s original breach of contract claim and attorneys’ fees. [Id. at 17, ¶¶ 19–20.]
Before the Court are four cross motions for summary judgment. Defendant seeks full summary judgment [95] on Plaintiff’s Claim I; Plaintiff cross moved for partial summary judgment [105] on that claim, arguing that it is at the very least entitled to the withheld funds. Plaintiff has abandoned its Claim II. See [104 at 20]. Plaintiff has also filed a sur-reply on Defendant’s motion for summary judgment over Claim I [111]. Plaintiff moved for summary judgment [113] on Defendant’s two counterclaims, and Defendant cross moved for summary judgment [115] on those claims as well.
II. Legal Standard
Summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
“Once a party has made a properly-supported motion for summary judgment, the opposing party may not simply rest upon the pleadings but must instead submit evidentiary materials that ‘set forth specific facts showing that there is a genuine issue for trial.‘” Harney v. Speedway SuperAmerica, LLC, 526 F.3d 1099, 1104 (7th Cir. 2008) (quoting
III. Analysis
A. Plaintiff’s Breach of Contract Claim (Claim I)6
Plaintiff’s Claim I is for breach of contract: Plaintiff alleges that it performed “extra work” by undercutting the soil, and was therefore entitled to payment for those services. Defendant has moved for summary judgment, arguing that the express language of the contract (and documents incorporated by reference) required undercutting the soil, and therefore this work was not “extra.” Plaintiff counters that the contract is ambiguous as to the status of the undercuts, and therefore summary judgment is inappropriate. Plaintiff has also moved for partial summary judgment on this count, arguing that irrespective of any ambiguity in the contract, it is entitled to funds withheld by Defendant in partial satisfaction of liquidated damages (discussed below).
The Court turns to Illinois8 contract law to determine whether the disputed undercutting was within the scope of the contract. “The primary objective in construing a contract is to give effect to the intent of the parties.” Gallagher v. Lenart, 226 Ill.2d 208, 232 (2007). The language of a contract provides the best indication of that intent. Id. (citation omitted); see also Right Field Rooftops, LLC v. Chi. Cubs Baseball Club, LLC, 870 F.3d 682, 690 (7th Cir. 2017) (applying Illinois contract law) (“A court must initially look to the language of a contract alone, as the language, given its plain and ordinary meaning, is the best indication of the parties’ intent.“). If the contract’s language is facially unambiguous, its words “must be given their plain, ordinary, and popular meaning.” Central Illinois Light Co. v. Home Ins. Co., 213 Ill.2d 141, 154 (2004). If the contract’s language is susceptible of more than one meaning, it is ambiguous and the court can consider extrinsic evidence to determine the parties’ intent. Right Field Rooftops, 870 F.3d at 690. All portions of a contract should be “construed as a whole, viewing each part in light of the others.” Gallagher 226 Ill.2d at 233 (citation omitted). In so construing a contract, a court should “attempt to give meaning to every provision of the contract and avoid a construction that would render a provision superfluous.” Land of Lincoln Goodwill Indus., Inc. v. PNC Fin. Servs. Grp., Inc., 762 F.3d 673, 679 (7th Cir. 2014).
Here, the contract unambiguously required Plaintiff to undercut the existing fill. As explained above, the contract documents included architectural Specifications, which required Plaintiff to hew to the Terracon Report’s recommendations when laying the foundation. [103 at 5–6, ¶¶ 21–22]. The Terracon Report, in turn, described the existing fill as “variable” and recommended excavating and replacing all
This case is almost identical to a Seventh Circuit case in which the court determined that under-compensated “overexcavation” was not “extra work” when the contract specifications contemplated excavations. See generally Brant Const, 967 F.2d at 246. There, the buyer supplied specifications and a geoengineering report containing the “soil borings and soil analyses on which those plans were based. It also provided bidders with the opportunity to conduct further tests of their own.” Id. at 245–46. The contract in that case provided a per-cubic-yard rate of reimbursement for excavation. Id. at 246. Although it later turned out that the “overexcavation” was of a different, costlier nature the contractor anticipated, the Seventh Circuit concluded that the contract settled this issue, and that the contractor could only be reimbursed for the lower, contract price. Id. at 247. So too here—the contract expressly required Plaintiff to excavate the Parcel in accordance with the Terracon Report; even if these were costlier or more extensive than Plaintiff anticipated, the Court cannot ignore the parties’ intent as reflected in the contract language.
Plaintiff’s arguments to the contrary are unconvincing. Plaintiff first argues that there is a conflict between the contract of land sale and the construction contract. [104 at 4–5.] As noted above, the litigants entered into two separate contracts. The land-sale contract provided that the land would be sold “AS-IS.” [108, ¶ 1.] Plaintiff argues that this provision saddles Defendant with the risk that contingencies may arise in the construction of the distribution center. [104 at 5.] But the land sale contract required that Plaintiff further contract with Defendant to build a distribution center; that construction contract, in turn, required that construction follow certain protocols, including excavating the extant fill and possibly even excavating weak native soils. [103-3, ¶ 10]; see also [97-7 at 2 (incorporating the Terracon Report)]. If Plaintiff’s reading of the words “AS-IS” is correct, then the entire construction contract (not to mention the condition precedent within the land sale agreement) is superfluous—Defendant bought an empty lot “as is,” so it is entitled to nothing more than an empty lot. The Court cannot accept this interpretation. See Land of Lincoln Goodwill, 762 F.3d at 679.
Plaintiff also argues that the requirement that “foundation construction shall be in accordance with the recommendations of [the Terracon Report]” conflicts with other contractual documents, revealing an ambiguity that cannot be resolved on the face of the contract. [104 at 5–7.] Plaintiff points to “Document 003132—Geotechnical Data.” See [103-5 at 10]. D003132 is part of the bidding documents and explains that the Terracon Report was provided “for contractor’s convenience and [is] intended to supplement rather than serve in lieu of contractor’s own investigations.” [Id.] D003132 states that it (i.e., D003132) is not part of the Contract Documents. [Id.] Plaintiff argues that D003132 is a Contract Document and its guidance that contractors conduct their own observations conflicts with the Specifications. Plaintiff is not correct, and there is no ambiguity in the integrated contract. As explained above, Article 1 of the Lump Sum Contract defines the Contract Documents; it unambiguously includes the Specifications (which in turn require that the Terracon Report guide laying the foundation).
Next, Plaintiffs argue that the contract requires compensating work remediating “concealed or unknown conditions.”10 [104 at 7–8.] But the contract only requires additional compensation when “concealed physical conditions [] differ materially from those indicated in the Contract Documents.”11 [97-2 at 6, Art. 8.4.] The Contract Documents require that the Terracon Report “be included as an integral part of the project specifications” and that “foundation construction shall be in accordance with the recommendations of said report.” [97-7 at 2]; see also [103, ¶ 21–22]. The Terracon Report, in turn, noted that the soil strengths were “variable,” and could lead to “unpredictable foundation performance” if not excavated and replaced with engineering fill. [97-6 at 11–12]. Thus, at the very least, the existing fill was not a “concealed physical condition which differ[s] materially from those indicated in the Contract Documents“—to the contrary, the Contract Documents acknowledged the substandard quality of the existing fill. Whether the substandard quality of the native soil is a “concealed or unknown condition” is a slightly closer question. But even there, the Terracon Report discusses the possibility that “lower strength soils, if encountered, will be undercut and replaced.” [97-6 at 15.]. The Report concludes that “[n]ew foundations should bear on tested and approved native soils or on newly placed engineered fill.” [97-6 at 11.] Plaintiff concedes that the undercuts of native soil were “into lesser bearing capacity native soils.” [104 at 10 (emphasis added).] Thus, though the native soil quality was concealed at the time of contracting, the soil quality and undercutting did not “differ materially” from anything described in the Contract Documents.12
Finally, Plaintiff argues that Defendant should be estopped from denying that the “extra work” is compensable, because Defendant later encouraged Plaintiff to complete work it formally adjusted the contract sum via “Change Order.” [104 at 16.] Plaintiff’s argument is not easy to follow, but as far as the Court can tell, even if Defendant’s subsequent course of conduct was to approve Change Orders late, every Change Order Plaintiff cites was approved after the Change Order at issue here was denied. Compare [104 at 16 (listing subsequent orders)], with [103, ¶ 33 (admitting that the change order was denied on August 30, just two days after it was submitted).] Thus, Plaintiffs did not rely on Defendant’s course of conduct to their detriment. Indeed, the course of conduct (such as it was) was not established until well after Defendants rejected the change order at issue here.
Because Plaintiff has not shown that the work was outside the scope of the contract, it cannot establish that its undercutting was extra. Accordingly, Defendant is entitled to summary judgment on this count. Plaintiff has also moved for partial summary judgment on this count, but their motion is better conceptualized as an objection to Defendant’s sequestration of some outstanding funds in partial reimbursement for the disputed liquidated damages (discussed below).
B. Defendant’s Breach of Contract Claim (Counterclaim I)
Defendant’s Counterclaim I seeks to collect almost one million dollars in liquidated damages. The contract provided for a $2,000 per day stipulated penalty for each day that the completion of the project was delayed. Defendant seeks summary judgment, both as to whether the claimed delay constituted a breach and the applicability of liquidated damages. Plaintiff also seeks summary judgment, arguing that the contractual terms are contradictory, and (when properly interpreted) required only that Plaintiff have the facility up-and-running
1. Breach
As explained above, where the language of the contract is unambiguous, that language controls. Central Illinois Light, 213 Ill.2d at 154. The Lump Sum Contract requires that the “Date of Substantial Completion” be no later than 365 days after work has commenced. [97-1 at 3, Art. 3.1.] Elsewhere, the contract defines Date of Substantial Completion as “the date certified by [Defendant] when construction is sufficiently complete in accordance with the Contract Documents and the permanent CO has been obtained, so that [Defendant] may occupy and use the Work or designated portion thereof for the use for which it is intended.” [97-2 at 12, Art. 18 (emphasis added).] The Contract also clarifies that “beneficial use and occupancy” by Defendant “shall not be deemed to be the equivalent of completion.” [97-2 at 31, Art. 51.2.]
Defendant’s argument is simple: because the permanent CO was not issued until 848 days after the project commenced (i.e., 483 days after the stipulated completion date), Plaintiff breached. Plaintiff counters that another contractual provision controls: “Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that O’Reilly can occupy or utilize the Work for its intended use; provided, however, that as a condition precedent to the Substantial Completion, O’Reilly has received all certificates of occupancy * * * necessary for the beneficial occupancy of the Project.” [97-2 at 15, Art. 22.1.] According to Plaintiff, this provision states that temporary CO’s satisfy Plaintiff’s obligation for Substantial Completion, and it is therefore entitled to summary judgment, or that at the very least it demonstrates the existence of an ambiguity that defeats Defendant’s motion for summary judgment.
Defendant has the better argument in regard to whether a permanent CO was required under the terms of the contract. In Illinois, there is no contradiction if “[o]ne [provision] is just more explicit than the other.” BMD Contractors, Inc. v. Fidelity and Deposit Co. of Maryland, 679 F.3d 643, 652 (7th. Cir. 2012). Even if there is a contradiction, “the more specific provision of a contract governs where it arguably conflicts with a more general provision.” Aeroground, Inc. v. CenterPoint Properties Trust, 738 F.3d 810, 816 (7th Cir. 2013) (citing Grevas v. U.S. Fidelity and Guar. Co., 152 Ill.2d 407, 411 (1992)). Although Article 22.1 could be read (albeit with some imagination) to suggest that any CO would satisfy the contract, Article 18 clarifies that a permanent CO is required. There is no conflict, because this more specific provision controls. Id.; see also 15th Place Condominium Ass’n v. South Campus Development Team, LLC, 14 N.E.3d 592, 600–01 (Ill. App. Ct. 2014) (enforcing similar definition of “Date of Substantial Completion” notwithstanding other, vaguer definitions in the contract). Plaintiff argues that its reading gives effect to “each clause and word used” in the contract, but that is entirely backwards: Plaintiff’s reading nixes the word “permanent” from the contract and therefore is disfavored. Land of Lincoln Goodwill, 762 F.3d at 679. In contrast, Defendant’s interpretation gives effect to both Article 22.1 and Article 18—Article 22.1 establishes that the Date of Substantial Completion has not arrived until
But Plaintiff’s failure to obtain this CO does not necessarily mean that Defendant is entitled to summary judgment on the issue of breach. To the contrary: there is one issue of material fact that defeats Defendant’s motion. Plaintiff argues that Defendant caused some of the delays and should not be allowed to benefit from its own dawdling.14 Specifically, Plaintiff’s Rule 30(b)(6) witness Olsen explained in his testimony that O’Reilly had failed to address an “internal” issue with the “[e]gress to the East from the hazardous room” and finalize approval for the “record drawings.” According to Olsen, these tasks were in Defendant’s hands, and contributed to the delay. [73 at 51, 172:4–173:9]; see also [id. at 90–91]. Defendant counters that Plaintiff waived any right to extend its contract period by failing to provide written notice.15 The contract requires, inter alia, “[i]f the [Plaintiff] wishes to make Claim for an increase in the Contract Time, written notice as provided herein shall be given. The [Plaintiff]’s Claim shall include an estimate of costs and of probable effect of delay on progress of the Work.” [97-2 at 6, Art. 8.6.]
As explained above, Illinois courts interpret unambiguous contracts according to the ordinary meaning of the words used therein, seeking to arrive at a construction that renders no word or phrase superfluous. Land of Lincoln Goodwill Indus, 762 F.3d at 679; see also Fidelity Nat. Title Ins. Co. of New York v. Westhaven Properties Partnership, 386 Ill. App. 3d 201, 215 (1st Dist. 2007) (strictly construing unambiguous written notice provision of partnership agreement to require written notice); but see Myers v. Popp Enterprises, Inc., 216 Ill. App. 3d 830, 835 (2d Dist. 1991) (refusing to require written notice when said provision was arguably ambiguous). Here, a strict construction would strain the meaning of the word “notice” and render the second quoted sentence nonsensical. The ordinary meaning of the word “notice” is an “announcement.”16 But here, it would make
Even if the language were unambiguous, however, summary judgment still would be inappropriate under these circumstances. In Rogers v. Balsley, the ostensibly breaching party sent written notice to the wrong address—to the counterparty’s attorney, as opposed to the counterparty’s home address. 240 Ill. App. 3d 1005, 1011 (2d Dist. 1993). Although that mistaken mailing did not comport with the terms of the contract, the Court reasoned that it was close enough, and that it would be inequitable to strictly enforce this provision. Not surprisingly, the attorney passed the notice along to the client. And “[s]ince plaintiffs received notice, in writing, * * * the object of the notice provision was accomplished.” Id. (citing Myers, 216 Ill. App. 3d at 836). Here, Defendant unambiguously had notice of its own failure to complete certain tasks and the consequences for its delays—it even sent its own written notice to the Plaintiff to that effect. See [73 at 85–91]. Thus, the “object of the written notice provision” was accomplished: Defendant knew what was outstanding, and what the consequences were. Id.17 Because Illinois courts would not require strict adherence to a written notice provision under these circumstances, the Court will not do so either. A reasonable jury could believe Olsen over Defendant’s letters, so there is an issue of material fact in regard to which party caused the delay in obtaining the permanent CO.
2. Liquidated Damages
In the interest of judicial economy, the Court will examine whether the liquidated damages provision is enforceable. The provision at issue here explains that in the event of a delay, “[t]he exact amount of such damages will be extremely difficult to ascertain. Therefore, [Defendant] and [Plaintiff] agree * * * [Defendant] shall be entitled to retain or recover from [Plaintiff], as liquidated damages and not as a penalty, the following per diem amounts commencing upon the first day following expiration of the Contract Time and continuing until the actual Date of Substantial Completion * * * Two Thousand Dollars ($2,000.00) per day.” [97-1 at 3, Art 3.2.]
The provision at issue explicitly states that it is for “liquidated damages and not [] a penalty” and is a “reasonable pre-estimate of damages.” [97-1 at 3, Art. 3.2(a).] The first requirement is therefore satisfied, because “[t]he provision evinces the parties’ joint effort to fix a determinable sum as damages at the time of contracting.” John Hancock Life Insurance Company v. Abbott Laboratories, 863 F.3d 23, 42 (1st Cir. 2017) (applying Illinois law and finding that a less explicit provision satisfied the first prong); see also Penske Truck Leasing Co., L.P. v. Chemetco, Inc., 311 Ill. App. 3d 447, 455 (5th Dist. 2000) (“The inclusion of the term liquidated damages indicates to us an arrangement by the parties that takes into consideration the possibility of breach and the necessity to take into account damages for such a breach.“). Plaintiff’s argument that the contract does not contain a liquidated damages provision thus is belied by the text of the contract itself. Contra [79 at 15].
With regard to the third requirement, Illinois courts regularly conclude that prospective damages in new projects are difficult to prove or uncertain in amount. John Hancock Life Insurance, 863 F.3d at 43–44 (collecting “heartland” cases). Plaintiff has not even asserted that, at the time of contracting, it would have been simple to ascertain the extent of damages in the event of delay. See [79 at 16 (arguing that damages were easy to quantify ex-post)]. Thus, Plaintiff has failed to carry its burden on this point. Ace Hardware Corp. v. Marn, Inc., 2008 WL 4286975, *14 (N.D. Ill. Sept. 16, 2008) (explaining that under Illinois law, the party seeking to avoid enforcement must “bear the burden of demonstrating that the damages claimed * * * were not difficult or impossible to quantify.“). In any event, damages were uncertain and difficult to ascertain prospectively. The proposed distribution center was designed to supply parts to local retail stores; presumably, the benefits to Defendant would accrue from improved efficiency in distributing its parts across the Chicagoland area. Any retrospective estimate of damages would have to contend with the individual factors affecting sales and inventory at each store and Defendant’s fleet deployment—to the extent that increases in efficiency can be quantified and monetized at all.
The second prong—the reasonableness of the liquidated damages provision—presents a close call. The reasonableness of liquidated damages is analyzed in light of “[t]he purpose of damages[, which] is to place the nonbreaching party
In practice, Illinois courts sometimes refuse to enforce large lump-sum liquidated damages that are triggered by any delay in performance. See, e.g., GK Development, 3 N.E. 3d at 817–818 (holding that contractual damages for the entire purchase price for any delay in securing permits was windfall and therefore a penalty); see also Energy Plus, 371 F.3d at 910 (applying Illinois law and concluding that similar lump-sum payment for delay was unreasonable). Defendant points out that reasonable per-diem liquidated damages that vary by the length of delay are generally enforceable. See [71 at 12–15 (discussing Weiss v. U.S. Fidelity & Guaranty Co., 300 Ill. 11 (1921) and Bethlehem Steel Corp. v. City of Chicago, 350 F.2d 649 (7th Cir. 1965) (applying Illinois law))]. Bethlehem Steel is particularly instructive, as it concerned a contractor who worked on a portion of what is now the Dan Ryan Expressway. Id. at 650. The contractor was one of many who worked successively on that portion of the highway, such that any delay would push back future contractors. Id. at 650–51. The Seventh Circuit upheld the lower court’s enforcement of a per-diem liquidated damages award based on the contractor’s delays. Even though the portion of the highway in question opened on time, the court found that the liquidated damages arrangement was reasonable at the time of contracting and the city may have incurred losses as a result of the contractor’s delays. Id. at 651–52.
Plaintiff argues that the liquidated damages provision in the instant contract is unenforceable because it does not vary with the gravity of its breach. According to Plaintiff, Defendant had full use of the facility very close to the contract date (as evidenced by the temporary CO), and the only outstanding issues were technical in nature and did not interfere with Defendant’s use of the property. Defendant counters that the per-diem damage calculation was reasonable at the time of contracting, and is therefore enforceable even if the center opened on time. Both sides are half right. As Defendant contends, the liquidated damages varies upon one axis of breach (the length of delay). But it does not vary upon another, equally important axis—the usability of the facility. As Defendant repeatedly concedes, the contract explicitly recites that liquidated damages
The case at hand, then, is quite similar to SMK Associates, 2018 WL 3344540, cited above. In that case, the plaintiff sought enforcement of a liquidated damages provision that entitled it to a 10% refund if the defendant’s monthly shipment of cigarettes was late or non-conforming. Id. at *7. Although the stipulated damages provision was somewhat proportional (it varied month-to-month based on the price of the goods), it was “invariant to the gravity of the breach. In particular, “the provision entitles [plaintiff] to 10% of the purchase price whether no cigarettes were delivered, or whether all of the cigarettes were delivered but some did not meet the specifications in any manner. * * * [T]he 10% amount could be assessed whether the monthly delivery were a few days late or not delivered at all.” Id. (quoting Checkers Eight Ltd. Partnership v. Hawkins, 241 F.3d 558, 562 (7th Cir. 2001). So too here. The same penalty was to be assessed whether the distribution center was utterly useless or entirely functional, and was therefore invariant to the gravity of the breach. Such invariance was also known at the time of contracting, because the contract itself requires invariant damages regardless of Defendant’s access to and use of the facility. [85, ¶¶ 4, 8, 12, 17, 21, 26, 27]. Finally, even if this is a “doubtful” case, the Court must still “construe the stipulated sum as a penalty.” GK Development, 3 N.E.3d at 816. Accordingly, Plaintiff is entitled to summary judgment on the unenforceability of the liquidated damages provision.
The Court may now turn to Plaintiff’s partial motion for summary judgment on its own Claim I. Plaintiff argues that it is entitled to funds Defendant withheld in partial satisfaction of the anticipated liquidated damages award. Neither party, however, has briefed whether the contract language allowing Defendant to “deduct liquidated damages * * * from any unpaid amounts then or thereafter due [Plaintiff]” [97-1 at 3, Art. 2(b)] would survive this Court’s refusal to enforce the liquidated damages provision as written. Accordingly, the Court will refrain from reaching out to decide this issue of Illinois contract law, which may benefit from further briefing or more pointed citations to discovery documents.
In sum, neither party is entitled to summary judgment on the issue of whether Plaintiff breached by failing to obtain a permanent CO by August 2014. Though the contract required a permanent CO, a disputed issue of material fact exists in regard to whether (and to what extent) Defendant unilaterally caused the delay. That said, Plaintiff is entitled to summary judgment on the unenforceability of the liquidated damages provision.
3. Indemnification (Counterclaim II)
Defendant seeks indemnification for attorneys’ fees and any damages it may be on the hook for resulting from Plaintiff’s breach of contract claim (that is, the damages Defendant itself caused). It moved for summary judgment on the ground that the contract unambiguously
If an indemnification clause is facially unambiguous, its words “must be given their plain, ordinary, and popular meaning.” Central Illinois Light, 213 Ill.2d at 154. That said, Illinois courts require that “an indemnity agreement must be given a fair and reasonable interpretation based upon a consideration of all of its language and provisions.” Open Kitchens, Inc. v. Gullo Intern. Development Corp., 126 Ill. App. 3d 62, 65 (1st Dist. 1984) (quotation marks and citation omitted). The indemnity clause cannot be read in isolation—it must be interpreted with the entire contract. Id.; Allianz Global Corporate and Specialty Marine Ins. Co. v. Host Intern., Inc., 2013 WL 1629437, *6 (N.D. Ill. Apr. 16, 2013) (quoting Gallagher, 226 Ill.2d at 233).
Although Illinois contract law recognizes the availability of first-party indemnification, whether a contract authorizes such indemnification is fact specific. Absent any language or provisions to the contrary, Illinois courts hold that capacious indemnity provisions may be enforced against parties to the contract. E.g., Higgins v. Kleronomos, 121 Ill. App. 3d 316, 321 (1st Dist. 1984) (enforcing an indemnity provision that applied to “all claims” against parties to the contract); see also Walgreen Co. v. Panasonic Healthcare Corporation of North America, 2017 WL 6731973, *6–7 (N.D. Ill. Dec. 29, 2017) (applying Illinois law and concluding that indemnification provision that listed different procedures for first- and third-party claims required limited first-party indemnification); Water Tower Realty Co. v. Fordham 25 E. Superior, L.L.C., 404 Ill. App. 3d 658, 666 (1st Dist. 2010) (“[A] party wishing to narrow an indemnification clause to third-party damage is obligated to limit the scope of the clause expressly.“) (internal quotation marks and citation omitted).
A contract may implicitly limit indemnification to third parties, however, if it contains language inconsistent with first-party indemnification. Thus, blanket indemnification provisions that include a duty to defend generally exclude first-party claims, as it makes little sense to defend a claim against one’s self. Open Kitchens, 126 Ill. App. 3d at 65 (reasoning that requirement that “[c]ontractor shall defend * * * any actions based [on all claims, damages, losses, liabilities and demands]” is inconsistent with first-party indemnification); but see Water Tower Realty, 404 Ill. App. 3d at 666 (distinguishing Open Kitchens because the indemnity provision separated the duty to defend clause with the word “and,” suggesting that the broad indemnification provision is conceptually separate). Other courts applying Illinois law have refused to enforce capacious indemnity provisions against first parties if the contract “would not make sense if the indemnity provision was intended to cover claims between the parties.” See John Hancock Life Insurance Company v. Abbott Laboratories, Inc., 183 F.Supp.3d 277, 326 (D. Mass. 2016) (applying Illinois law and concluding
The indemnification clause here reads in relevant part:
To the fullest extent permitted by law, Contractor agrees to defend, indemnify and hold harmless [Defendant], [Defendant]’s representatives and any subsidiary, related or affiliated companies and the officers, directors, agents and employees of each (collectively “Indemnitees“), from and against any and all liabilities, damages, losses, costs, claims, suits, judgments and expenses (including all attorney’s fees incurred by indemnities) or demands, including those demands arising from damage to property (including loss of use resulting therefrom) and injuries or death of persons (collectively ‘Claims‘), notwithstanding any possible negligence, whether sole or concurrent on the part of [Defendant] or any of the Indemnitees, to the extent caused by, or allegedly caused by, or arising out of, or connected with: [] this Contract or the Work of any Subcontract thereunder ([Plaintiff] hereby assuming full responsibility for all the Work and relations with Subcontractors).
The Contractor shall indemni[fy] and hold harmless all of the Indemnitees from and against any costs, and expenses (including reasonable attorneys’ fees) incurred by any of the Indemnitees in enforcing any of the Contractor’s defense, indemnity, and hold-harmless obligations under this Contract. [97-2, Art 42.]
Here, taken as a whole, the contract is inconsistent with first-party indemnification. Defendant hangs its hat on the “any and all” language, arguing that this unambiguously includes first-party claims. Higgins, 121 Ill. App. 3d at 321. But the Court cannot view these three words in isolation, and instead must consider their context within the page-long indemnity clause, which is itself embedded within a 32-page-long section of an even longer contract. Indeed, including first-party claims within the indemnity provision would render nonsensical General Conditions, Article 8, Sections 7 (“Injury or Damage to Person or Property“), 9 (“Waiver of Consequential Damages“), and 10 (“Mandatory Mediation“), which all concern disputes between the parties, and none of which mention indemnity. For example, Section 9’s requirement that Plaintiff waive consequential damages claims against Defendant would be simultaneously meaningless and redundant—according to Defendant, Plaintiff will always be on the hook for its own damages, so it would not matter if consequential damages are limited. Moreover, the indemnification provision itself includes a blanket duty to defend, which is not set off in a separate, conceptually distinct clause; this therefore militates against requiring first-party indemnification. Compare Open Kitchens, 126 Ill. App. 3d at 65, with Water Tower, 404 Ill. App. 3d at 666 (distinguishing Open Kitchens). Finally, the parenthetical
IV. Conclusion
For the reasons set forth above, the Court grants Defendant’s motion for summary judgment [95] and denies Plaintiff’s cross-motion for partial summary judgment [105]. Plaintiff’s and Defendant’s respective cross motions for summary judgment [113, 115] are each granted in part and denied in part. Plaintiff’s motion for leave to file a sur-reply [111] is granted. The case is set for further status on January 15, 2020 at 9:00 a.m.
Dated: December 30, 2019
Robert M. Dow, Jr.
United States District Judge