Lead Opinion
Dеfendants La-Van Hawkins and his associated corporations appeal the amount of damages entered under an agreed order. They claim that a provision requiring them to pay an additional $150,000 if their scheduled payments under the order were tardy is an unenforceable penalty clause. The defendants also argue that plaintiffs Checkers Eight Limited Partnership
I. Background
The fаcts underlying this lengthy commercial litigation are complicated and generally not relevant to the legal issues presented in this case and so will receive oniy a concise summary. In 1995, Checkers, Thomas W. Lonergan, James P. Lonergan, Thomas W. Lonergan Trust No. 1, and Tower Food Services, Inс. (the general partner of Checkers) filed suit against La-Van Hawkins, Hawkins Two, Inc., Hawkins Four, Inc., Hawkins Five, Inc., and Hawkins Eight, Inc. Count I of the amended complaint alleged that the defendants owed money to Checkers under a partnership agreement signed by each of the defendants, and Count II allegеd that payments from the defendants were owed to another partnership. The plaintiffs sought $350,747.68 on Count I and $214,597.58 on Count II. The basis of federal jurisdiction was (and is) diversity, since the plaintiffs and the limited partners of Checkers were either citizens of or were incorporated and had their primary places of business in Illinois, New York, or Ohio, while the original defendants were either citizens of or were incorporated and had their primary places of business in Georgia.
The litigation developed with the plaintiffs filing motions for summary judgment. In a June 3, 1997 opinion, the court denied one of these motiоns but found as substantially uncontroverted facts under Fed. R.Civ.P. 56(d) that the defendants owed at least $181,303.68 on Count I and at least $200,162.58 on Count II. In September, 1997, after being granted leave by the court, the defendants filed a counterclaim seeking reimbursement for expenses the defendants allegedly paid on behalf of the partnerships. The counterclaim stated only that the defendants sought more than $50,000 in damages, but the defendants' documented expenses totaled $1,153,484.85.
In February, 1999, the parties settled the case and had the district court enter an order memorializing their resolution. This order dismissed the defendаnts' counterclaim with prejudice and provided that if the defendants paid the plaintiffs a total of $250,000 in a timely manner the complaint would be dismissed with prejudice as well. This $250,000 was to be paid in an initial lump sum and then monthly installments, with the installment amounts due near the end of each month from March, 1999 to Januаry, 2000. The order also stated that if the payments were not made in a timely manner, judgment for $400,000 minus any settlement payments would be entered against the defendants who were parties to the original partnership dispute as well as other associated entities,
The defendants were tardy making some of the payments. The payment of the first late sum, which was due on May 28, 1999 according to the agreed order, was delayed with the permission of the plaintiffs until June 4. However, the defendants did not obtain explicit permission from the plaintiffs for the remaining late payments, the
II. Discussion
The defendants argue that the extra $150,000 they were required to produce for not making timely payments is an unenforceable penalty clause. They claim thаt this sum has no relation to the damages caused by the late payments and that these damages are easily estimated by using prevailing interest rates. They further contend that the only purpose of this provision of the order was to secure performance of the contract and that the amount is insensitive to the gravity of their breach. The plaintiffs claim that the provision in question is a perfectly acceptable liquidated damages clause.
We begin by making explicit a few assumptions relied on by the parties. The first of these is that state law, rather than federal, applies to the construction of agreed orders entered by a federal court sitting in diversity. In their briefs, both parties cite only Illinois law and Seventh Circuit and Illinois district court cases interpreting Illinois law. Most of the circuits that have considered the issue have held that questions of the validity or interprеtation of an agreed order resolving state law claims are governed by state law, see, e.g., Bamerilease Capital Corp. v. Nearburg,
Having established these preliminary points, we now move to the merits of the penalty clause argument. In interpreting contract provisions that specify damages, Illinois law draws a distinction between liquidated damages, which are enforceable, and penalties, which are not. See Lake River Corp. v. Carborundum Co.,
Given these legal principles, the provision of the parties' agreed order requiring the defendants to pay an additional $150,000 if the installments are not paid in a timely fashion is an unenforceable penalty clause. Absent exceptional circumstances, actual damages caused by monetary payments being late are not difficult to measure because interest rates can be used to estimate the time value of money. See Lawyers Title Ins. Corp. v. Dearborn Title Corp.,
The plaintiffs' principal argument is that requiring the defendants to pay a total of $400,000 adequately measures the damages caused to the plaintiffs because of the defendants' breach of the timeliness requirement of the agreed order. They base this contention on the district court's findings in its June 3, 1997 order that the defendants owed at least $381,466.26 and the possibility that the defendants could have been liable for as much as $565,345.26. The plaintiffs' argument is unpersuasive. The amount of $400,000 might have been a reasonable estimate of the damages caused by the alleged breach of the partnership agreement, though this is neither certain
The plaintiffs also argue that courts should respect contracts between two sophisticated parties and not reform such agreements so as to give one party a bargain to which the other did not agree. This claim amounts to a generalized assertion that contract provisions between commercially experienced parties should never constitute penalty clauses because the parties are of roughly equal bargaining strength. While we have noted similar criticisms in this circuit’s opinions discussing Illinois penalty clause jurisprudence, see Lawyers Title,
III. Conclusion
Because the damages clause is an unenforceable penalty under Illinois law, the plaintiffs are entitled only to the actual damages caused by the defendants’ late payments, as measurеd by an appropriate interest rate. For the reasons stated herein, we Reverse and Remand for further proceedings consistent with this opinion.
Notes
. The parties who are the defendants in the instant dispute are La-Van Hawkins, Hawkins One, Inc., Hawkins Two, Iiic., Hawkins Four, Inc., Hawkins Five, Inc., Hawkins Eight, Inc., The La-Van Hаwkins Group, Inc., Windy City Construction, Inc., Inner City Foods Company, and La-Van Hawkins & Assoc. of Chicago, Inc. At least two of the entities included in this group but who were not originally defendants, namely, Inner City Foods Company and La-Van Hawkins & Assoc. of Chicago, Inc., are incorporated and have their principаl places of business in Illinois, and thus are not diverse from the plaintiffs. However, since the parties were completely diverse when the action was commenced and these two entities are not indispensable parties, their subsequent addition does not deprive this court of jurisdiction. See Freeport-McMoRan, Inc. v. K N Energy, Inc., 498 U.s. 426,
. Claims raised for the first time at oral argument are normally considered waived. See Berens v. Ludwig,
. Because we accept the defendants' penalty clause argument, we need not address their contentions regarding waiver.
. Despite the district court's finding that their сlaims were worth at least $381,466.26, the plaintiffs quite possibly could have netted much less than $400,000, or even $250,000, if they had continued to litigate. This course would have required the plaintiffs to expend further resources on preparing and conducting a jury trial and would have also exposed them to the pоssibility of being found liable on the defendants' counterclaim. If these expenses were sufficiently large, a reasonable estimate of the expected value of the plaintiffs' suit on the date that they settled could have been $250,000 or less.
Concurrence Opinion
concurring.
I can’t agree that the court-approvеd settlement order, which increased Hawkins’ obligation to $400,000 if he failed to make timely payments, is an unenforceable penalty clause. In fact, it seems to me that this sort of carrot-and-stick settlement agreement, blessed by a court in an order, is fairly routine. Surely, Checkers and Hawkins could hаve agreed to the entry of a judgment for $400,000, dis-chargeable as fully satisfied upon Hawkins paying $250,000 over 10 months. The court order here, in substance, isn’t any different. It is wrong, I submit, to characterize this agreement as one involving “damages.” It’s not. It involves an alternative entitlement if certain conditions are not met. And there is nothing wrong with that, especially here where we are dealing with big boys who ought to be able to freely agree on any mechanism for resolving what the court correctly describes as complicated and “lengthy commercial litigation.”
But that said, I join the court’s opinion beсause I think Checkers, by waiting to spring its $150,000 kicker until after it got all its money, waived its right to insist on strict compliance with the order’s timely payment provisions. So the court, in my view, is correct in rejecting Checkers’ claim (except for a pittance of interest), although I would do so for a different reason.
