MCI COMMUNICATIONS, INC. and MCIMETRO ACCESS TRANSMISSION SERVICES CORP., Plaintiffs, v. CARL BOLANDER & SONS LLC, Defendant.
Civil No. 18-2986 (JRT/SER)
UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA
June 12, 2019
JOHN R. TUNHEIM
MEMORANDUM OPINION AND ORDER
James J. Proszek, HALL, ESTILL, HARDWICK, GABLE, GOLDEN, & NELSON, P.C., 320 South Boston Avenue, Suite 200, Tulsa, OK 74103, and Seth J. S. Leventhal, LEVENTHAL PLLC, 527 Marquette Avenue South, Suite 2100, Minneapolis, MN 55402, for plaintiffs.
Eric J. Steinhoff, LIND JENSEN SULLIVAN & PETERSON, PA, 901 Marquette Avenue South, Suite 1300, Minneapolis, MN 55402, for defendant.
Plaintiffs MCI Communications Services, Inc. and MCImetro Access Transmission Services Corp. (collectively “MCI“) bring an action for trespass, negligence, statutory liability as an excavator, and breach of contract/third-party beneficiary against Defendant Carl Bolander & Sons LLC (“Bolander“). MCI seeks damages because Maverick Cutting & Breaking LLC (“Maverick“), a subcontractor hired by and working at the direction of Bolander, severed two of MCI‘s fiber-optic telecommunications cables while performing concrete sawcutting on April 14, 2015. MCI filed this action more than three years later, on October 22, 2018.
The Court will find that
BACKGROUND
I. FACTUAL BACKGROUND
MCI is a telecommunications company that owns and operates a nationwide network of mostly underground fiber-optic cables. (Compl. ¶ 8, Oct. 22, 2018, Docket No. 1.) The injury underlying this action arose when two of MCI‘s fiber-optic cables were cut during a construction project to replace several bridges in the City of St. Paul (the “Project“). (Id. ¶¶ 11, 24.) The Project included the removal and replacement of the bridge at the intersection of Wabasha Street and Kellogg Boulevard (the “Intersection“). (Id. ¶ 11.) The City of St. Paul contracted with Kraemer North America, LLC, (“Kraemer“) to serve as the general contractor for the Project. (Id. ¶ 14.) Kraemer entered into a subcontract agreement with Bolander to perform some of the work on the Project, including removal of the bridge at the Intersection. (Id. ¶ 18.) Removing the bridge, however, first required the removal of pavement around the Intersection. (Id.) Bolander subcontracted with Maverick to complete this task. (Id. ¶ 20.)
II. PROCEDURAL BACKGROUND
MCI first brought an action against Maverick on April 11, 2017, alleging trespass, negligence, and statutory liability as an excavator. MCI Commc‘ns Servs., Inc. v. Maverick Cutting & Breaking LLC, No. CV 17-1117 (JRT/SER), 2018 WL 4562471, at *1 (D. Minn. Sept. 24, 2018). On April 26, 2018, a little over a year after MCI brought claims against Maverick and more than three years after the incident occurred, MCI moved to amend its complaint to assert claims for relief against Bolander and Kraemer. Id. Maverick opposed MCI‘s motion, arguing that (1) MCI failed to meet
United States Magistrate Judge Steven E. Rau denied MCI‘s motion to amend based on MCI‘s failure to meet
Bolander filed its Motion to Dismiss on November 8, 2018. (Mot. to Dismiss, Nov. 8, 2018, Docket No. 7.)
DISCUSSION
I. STANDARD OF REVIEW
In reviewing a
Minnesota law applies in this case based on diversity jurisdiction. See Integrity Floorcovering, Inc. v. Broan–Nutone, LLC, 521 F.3d 914, 917 (8th Cir. 2008). “In resolving any substantive issues of state law, [the Court is] bound by the decisions of the Minnesota Supreme Court.” Id. “If the Minnesota Supreme Court has not spoken on a particular issue, [the Court] must attempt to predict how the Minnesota Supreme Court would decide an issue and may consider relevant state precedent, analogous decisions, considered dicta[,] . . . and any other reliable data.” Id. (omission in original) (internal quotation omitted).
II. MINNESOTA STATUTE § 541.051
Bolander seeks dismissal of MCI‘s entire action, arguing that MCI‘s claims are time-barred by
Except where fraud is involved, no action by any person in contract, tort, or otherwise to recover damages for any injury to property, real or personal or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an improvement to real property, shall be brought against any person performing or furnishing the design, planning, supervision, materials, or observation of construction or construction of the improvement to real property or against the
owner of the real property more than two years after the cause of action accrues. . .
The parties do not dispute that MCI brought this action more than three years after the cause of action accrued. They dispute (1) whether Maverick‘s sawcutting constitutes an “improvement to real property” and, if so, (2) whether MCI‘s injury arose from a “defective and unsafe condition” of the improvement. The Court will find that Maverick‘s sawcutting constitutes an “improvement to real property” but that MCI‘s injury did not arise from a “defective and unsafe condition” of that improvement. As such, the Court will deny Bolander‘s Motion to Dismiss.
A. Improvement to Real Property
The Minnesota Supreme Court has defined an “improvement to real property” under
Instead of considering each part of a construction project separately, the Eighth Circuit has interpreted Minnesota law to require consideration of the “overall process of construct[ion].” Lederman v. Cragun‘s Pine Beach Resort, 247 F.3d 812, 815-16 (8th Cir. 2001). If the construction project as a whole constitutes an improvement to real property and the portion of the project at issue is an “integral part of the construction,” then the challenged portion also constitutes an improvement to real property under
Bolander argues that, because the pavement removal was an integral part of a larger project that would qualify as an improvement to real property, the pavement removal must also be considered an improvement to real property under the Eighth Circuit‘s decision in Lederman. See id. at 816 (“[B]ecause the trench at issue here was an integral part of building the Shoreline Suites, we hold that the trench, although merely temporary, was an ‘improvement to real property’ under Minnesota law.“).
MCI disputes Bolander‘s assessment for two reasons. First, MCI cites Lowry Hill Props. v. Ashbach Constr. Co., 194 N.W.2d 767, 775 (Minn. 1971), for the proposition that pavement removal is not an improvement to real property under
Because Lowry provided no analysis for its conclusion that
As to Brandt, the Court is bound only to follow state supreme court decisions. See Integrity Floorcovering, Inc., 521 F.3d at 917. Brandt‘s holding, while persuasive, does not overcome the Court‘s obligation to follow the binding precedent of Lederman, which requires the Court to consider the construction as a whole.
Following Lederman, taking the Minnesota Supreme Court‘s common sense approach, and applying the Minnesota Supreme Court‘s definition of an improvement to real property, the Court concludes that Maverick‘s sawcutting constitutes an improvement to real property under
It is also undisputed that the pavement removal done by Maverick and Bolander was “required” for the overall project to proceed, making the pavement removal an integral part of the entire construction process. (Compl. ¶ 18.); see Lederman, 247 F.3d at 815. The
B. Arising Out of a Defective and Unsafe Condition
Having determined that Maverick‘s sawcutting constitutes an improvement to real property under
The Minnesota Supreme Court has “not yet been required to define the exact parameters of the definition of ‘arising out of’ in
Black‘s Law Dictionary defines a “condition” as: “A state of being; an essential quality or status.” CONDITION, Black‘s Law Dictionary (10th ed. 2014). It defines a “dangerous condition” as “[a] property defect creating a substantial risk of injury when the property is used in a reasonably foreseeable manner.” Id. Merriam-Webster‘s Dictionary defines “condition” as “a state of being” or “a state of physical fitness or readiness for use.” Merriam-Webster‘s Collegiate Dictionary 240 (10th Ed. 1993).
Eighth Circuit case law supports this conclusion. In Lederman, the plaintiff was injured when an already-dug trench caused a walkway to collapse. 247 F.3d at 813-14. The digging of the trench itself was not deemed “defective and unsafe,” it was the condition of trench—i.e. the improvement to real property—that was defective and unsafe, which caused plaintiff‘s injuries. Id. at 817 n.4.
Two persuasive cases from the Minnesota Court of Appeals also support this conclusion. In Brandt, a construction worker was injured when a subcontractor failed to de-energize pre-existing electrical wires within a building that was being renovated. 560 N.W.2d at 402. The Minnesota Court of Appeals held that
In Wiita v. Potlatch Corp, 492 N.W.2d 270, 270-71 (Minn. Ct. App. 1992). The Wiita court reasoned that
That said, Lietz provides some indication that the Minnesota Supreme Court might move toward including negligent construction activities, not just defective “conditions,” within the purview of
It is possible that the Minnesota Supreme Court, in employing a broader interpretation of
CONCLUSION
The Court finds that, because the pavement removal here was an “integral part” of a construction project that would otherwise qualify as an “improvement to real property,” it too qualifies as an “improvement to real property” under
ORDER
Based on the foregoing, and all the files, records, and proceedings herein, IT IS HEREBY ORDERED that Defendant Bolander‘s Motion to Dismiss [Docket No. 7] is DENIED.
DATED: June 12, 2019
at Minneapolis, Minnesota
JOHN R. TUNHEIM
Chief Judge
United States District Court
