Lead Opinion
OPINION
In late 2001 and early 2002, appellant Jaenty, Inc. (Jaenty) brought an action against respondents Northern States Power Co. (NSP), Seren Innovations, Inc. (Seren), Cable Constructors, Inc. (CCI) and Sirti, Ltd. (Sirti) to recover for damages sustained in a gas explosion in December of 1998. The district court granted respondents’ motions for summary judgment based on the two-year statute of limitations found in Minn.Stat. § 541.051, subd. 1(a) (2004). The court of appeals, in a split decision, affirmed the district court. Lietz v. N. States Power Co., No. A04-901,
On December 11, 1998, while installing a utility pole support anchor (the anchor) in St. Cloud, Minnesota, employees of CCI pierced a gas line owned by NSP, causing a natural gas leak. The installation of the anchor was part of a project by Seren to construct a fiber-optic communication system in the area. Seren had hired Sirti to plan the project, and CCI was hired to do the actual installation. The anchor was a steel rod, five feet six inches in length, with a helix at the bottom that acted as a bit during installation. The anchor was intended to support the utility pole via a guy line. The anchor and guy line were intended to balance the weight of the fiber-optic cable and keep the pole upright. On the date of the explosion, CCI was installing anchors in St. Cloud in preparation for the installation of fiber-optic cable.
After breaking a hole in the sidewalk with a jackhammer, the CCI workers placed an auger, or “anchor cranker,” on top of the anchor and began to auger the anchor into the ground. After the anchor had bored to a depth of approximately one and one-half to two feet, it hit a hard object, later determined to be a large slab of granite. In an attempt to break through the obstruction, the workers removed the auger and struck the top of the anchor with a sledgehammer. They then placed the auger on top of the anchor and resumed boring. Everything appeared normal until the top of the anchor was roughly 12 to 18 inches above the surface of the ground. At that time, the workers smelled gas and noticed dirt blowing from the anchor hole. Realizing they had pierced a gas line, the workers stopped the auger, and the crew foreman telephoned his supervisor.
Less than an hour after the anchor struck the gas line, an explosion occurred. Four people were killed in the explosion, a number of others suffered injuries, and the surrounding buildings sustained damage. In late 2001 and early 2002, Jaenty commenced this action against CCI, Seren, Sirti, and NSP for damages to its restaurant. The district court granted the defendants’ motions for summary judgment, finding that, because Jaenty’s injuries were caused by an improvement to real property (the anchor), Jaenty’s claim was barred by the two-year statute of limitations in Minn.Stat. § 541.051, subd. 1(a). The relevant part of the statute provides:
[N]o action by any person in contract, tort, or otherwise to recover damages for any injury to property * * * arisingout of the defective and unsafe condition of an improvement to real property, * * * shall be brought against any person performing or furnishing the design, planning, supervision, materials, or observation of construction or construction of the improvement to real property or against the owner of the real property more than two years after discovery of the injury.
MinmStat. § 541.051, subd. 1(a). The court of appeals, in an unpublished split decision, affirmed the district court’s grant of summary judgment. Lietz,
Jaenty argues that the lower courts’ determination that section 541.051 barred its action is erroneous in two respects: (1) the anchor was not an “improvement to real property” because it was not completely installed at the time of the accident, and (2) Jaenty’s damages arose out of negligent construction activities, not the defective and unsafe condition of an improvement to real property. We address each of these arguments in turn.
I.
On appeal from summary judgment, this court determines “whether there are any genuine issues of material fact, and whether the lower court erred in its application of the law.” Olmanson v. LeSueur County,
When defining an “improvement to real property” for the purposes of section 541.051, this court has said that a “common-sense interpretation” should be used. Pac. Indem. Co. v. Thompsortr-Yaeger, Inc.,
“[A] permanent addition to or betterment of real property that enhances its capital value and that involves the expenditure of labor or money and is designed to make the property more useful or valuable as distinguished from ordinary repairs.”
Sartori v. Harnischfeger Corp.,
If a statute is ambiguous, this court may look to other factors, such as the occasion and necessity for the law, to determine legislative intent. Minn.Stat. § 645.16. In a decision interpreting a prior version of section 541.051, this court presumed, based on the timing of the enactment of section 541.051 and similar statutes enacted in other states, that section 541.051 was enacted because of the recent erosion of the privity of contract doctrine and the “resulting exposure of architects and builders to potential liability of indefinite duration from third-party tort claims.” Kittson County v. Wells, Denbrook & Assocs., Inc.,
The legislature has already indicated, however, that section 541.051 is intended to bar a broader range of claims than those prohibited before the erosion of the privity of contract doctrine. The original version of section 541.051 did not specify the types of actions barred. See Minn. Stat. § 541.051, subd. 1 (1965) (“[N]o action to recover damages for any injury to property * * * arising out of the defective and unsafe condition of an improvement to real property * * * shall be brought * * * more than two years after discovery thereof * * *.”). This court limited the statute’s coverage to tort actions in which the defendant asserting section 541.051 as a defense was not in privity with the plaintiff. Kittson County, 308 Minn, at 242,
When the plain language of a statute is ambiguous, another factor considered in the search for legislative intent is the consequence of a particular interpretation. Minn.Stat. § 645.16(6). If this court adopts Jaenty’s argument that installation must be “complete” for something to qualify as an “improvement to real property,” difficult distinctions will need to be drawn between “partially-installed” items that are not covered by section 541.051 and “completely-installed” improvements that are covered by section 541.051. Based on the legislature’s decision to broaden the scope of section 541.051 and based on the negative consequences of Jaenty’s proposed interpretation, we hold that an object need not be completely installed in order to qualify as an “improvement to real property” within the meaning of Minn.Stat. § 641.051.
II.
Having concluded that the anchor qualifies as an improvement to real property, the next issue before the court is whether Jaenty’s damages “arose out of the defective and unsafe condition” of the anchor. If the damages “arose out of the defective and unsafe condition” of the anchor, Jaenty’s claims are barred by the two-year statute of limitations. Jaenty argues that its injuries arose out of “negligent construction activities” rather than the defective and unsafe condition of the anchor and thus Jaenty’s claims should not be subject to the two-year statute of limitations. We address this issue in two ways: (1) whether the condition of the anchor was “defective and unsafe,” and (2) whether Jaenty’s alleged injuries “arose out of the condition” of the anchor.
We have previously said that whether an injury arises out of a defective
This court has already held that negligence during the installation process can lead to a “defective and unsafe condition of an improvement to real property.” See Pac. Indem. Co.,
Having determined that the anchor was in a “defective and unsafe condition” at the time of Jaenty’s alleged injuries, the remaining inquiry is whether Jaenty’s claimed injuries “arose out of’ this condition. Jaenty argues that “there is no causal connection between the injuries sustained by Jaenty and the condition of the anchor” and that the accident was caused by respondents’ negligence. Because we reaffirm that negligence during installation can create a “defective and unsafe condition of an improvement to real property,” this claim is without merit. This court has not yet been required to define the exact parameters of the definition of “arising out of’ in section 541.051; this case does not require us to do so. The anchor was in a defective and unsafe condition because during installation it was bent out of alignment and punctured a gas line. There is proximate cause between a negligent act and an injury when the act is “ ‘one which the party ought, in the exercise of ordinary care, to have anticipated was likely to result in injury to others.’ ” Canada v. McCarthy,
Affirmed.
Notes
. In their joint brief, Sirti, Seren and CCI claim that, before the district court, Jaenty failed to argue that the anchor was not an improvement to real property based on the lack of complete installation. Because of this failure, Sirti, Seren and CCI argue that this court should not consider this issue on appeal. In general, an issue will not be considered on appeal if it was not first raised below. Putz v. Putz,
. As noted in Pacific Indemnity Co.,
. In Kittson County, this court interpreted section 541.051 using a rule of strict construction. 308 Minn, at 240-41,
. We recognize that in Sartori this court stated that section 541.051 was designed to "eliminate suits against architects, designers and contractors who have completed the work, turned the improvement to real property over to the owners, and no longer have any interest or control in it.” Sartori,
.We note that the Minnesota Court of Appeals has come to the same conclusion when interpreting section 541.051. See O’Connor v. M.A. Mortenson Co.,
. The only support Jaenty cites for its argument is Wiita v. Potlatch Corp.,
. Because we conclude that all of Jaenty's claims against respondents arose out of the defective and unsafe condition of the anchor, we need not reach NSP’s claim that Jaenty’s claims against NSP are barred on the separate basis that the gas line struck by the anchor qualifies as an improvement to real property under section 541.051.
Dissenting Opinion
(dissenting).
I respectfully dissent. While the court correctly points out that we are to use a “common-sense interpretation” when defining what constitutes an improvement to real property, the court fails to apply any common sense in defining the anchor here, which was in the process of being put in place when it struck the gas pipeline, to be an improvement to real property. As a result, Jaenty’s negligence claims based on respondents’ act of drilling the anchor into the gas pipeline causing its rupture are defeated by the statute of limitations. This result is one that the statute does not contemplate.
Minnesota Statutes § 541.051, subd. 1(a) (2004), in relevant part provides:
Except where fraud is involved, no action by any person in contract, tort, or otherwise to recover damages for any injury to property, real or personal, or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an improvement to real property * * * shall be brought * * * more than two years after discovery of the injury * ⅜ *.
The phrase “improvement to real property” as used in the statute and as interpreted in our case law means “ ‘a permanent addition to or betterment of real property that enhances its capital value and that involves the expenditure of labor or money and is designed to make the property more useful or valuable as distinguished from ordinary repairs.’ ” Pac. Indem. Co. v. Thompson-Yaeger, Inc.,
The anchor at issue in this case, at the time it was drilled into the gas pipeline, was not a “permanent addition to or betterment of real property.” Webster’s Third New International Dictionary, Unabridged, defines “permanent” as “continuing or enduring (as in the same state, status, place) without fundamental or marked change: not subject to fluctuation or alteration: fixed or intended to be fixed: lasting, stable.” Webster’s Third New International Dictionary 1683 (1993); see also Merriam-Webster’s Collegiate Dictionary 863 (10th ed.2001) (defining “permanent” as “continuing or enduring without fundamental or marked change: Stable”). The word “addition” is defined as “a part added to or joined with a building.” Webster’s Third New International Dictionary 24; see also Merriam-Webster’s Collegiate Dictionary 13 (defining “addition” as “a part added (as to a building or residential section)”). The word “betterment” is defined as “a making or becoming better: * * * an improvement of an estate (as by
Common sense dictates that an anchor that is drilled into a gas pipeline while in the process of being installed cannot constitute a permanent improvement to real property for purposes of section 541.051, subdivision 1(a). Because the anchor here was still in the process of being installed and was not yet “stable,” that is, not continuing or enduring without fundamental or marked change and not fixed or intended to be fixed at the time, it was not, in fact could not have been, a permanent addition or betterment of real property at the time the pipeline was ruptured. Although the anchor might at some point have become a permanent addition to real property, at the time it was being drilled into the pipeline causing the rupture, it was not. Therefore, the anchor does not qualify as an improvement to real property.
This is not to say that negligence during installation will always preclude an object from being treated as an improvement to real property. For instance, in Pacific Indemnity, the negligent installation of a furnace led to a fire that occurred 20 years later and destroyed portions of a strip mall. Pac. Indem.,
In order for the limitations provisions of section 541.051, subdivision 1(a), to apply, the injury at issue must also arise out of a defective and unsafe condition. That did not happen here. As the opinion correctly points out, whether an injury arises out of a defective and unsafe condition “turns on the individual facts alleged in the complaint.” See Griebel v. Andersen Corp.,
Further, because of the legislature’s use of the conjunctive “and” in the phrase “defective and unsafe condition,” the anchor must have been both defective and unsafe for the limitations period in section 541.051, subdivision 1(a), to apply. While it can be argued that, as a result of being bent as it was being installed, the anchor was in a defective condition when it struck the pipeline, it cannot be seriously argued that the anchor was in an unsafe condition. What made the anchor unsafe was not its condition but the act of drilling it into the gas pipeline. Had the anchor not been drilled into the pipeline, the harm inflicted here would not have occurred no matter what the condition of the anchor. Therefore, the injury did not arise out of a defective and unsafe condition. Because the damage Jaenty sustained did not arise out of a defective and unsafe condition of an improvement to real property, the statute of limitations found in section 541.051, subdivision 1(a), does not bar Jaenty’s claims.
That Minn.Stat. § 541.051, subd. 1(a), does not act to bar Jaenty’s claims is supported by our statement in Sartori that “[t]he statutory limitation period [found in section 541.051, subdivision 1] is designed to eliminate suits against architects, designers and contractors who have completed the work, turned the improvement to real property over to the owners, and no longer have any interest or control in it.”
Finally, I note that the statute of limitations found in section 541.051, subdivision 1(a), is short — two years as opposed to the six-year limitations period applicable to ordinary negligence actions. Minn.Stat. § 541.05, subd. 1 (2004). This shortened limitations period can, as in this case, work a harsh result. Yet the court broadens the application of the statute based in part on “the legislature’s decision to broaden and clarify the scope of section 541.051.” The court’s broadening of the application of section 541.051 is, at best, misguided. In clarifying and broadening the scope of the statute, the legislature did nothing more than make clear that the statute covers more types of actions than simply tort actions. The legislature did nothing to change, modify, broaden, or clarify the statute’s “arising out of the defective and unsafe condition of an improvement to real property” language. Moreover, the legislature’s changes did nothing to address the concerns raised by this court in Kittson County v. Wells, Denbrook & Associates, Inc., that “the statute has the potential of working a harsh result * * * because of the shortness of the 2-year” statute of limitations.
