Northeast Utilities Service Company, as agent of Public Service Company of New Hampshire, Plaintiff v. BENDTEC, INC., Defendant-Appellee. Associated Electric & Gas Insurance Services; Zurich American Insurance Company; Energy Insurance Mutual Limited, all as subrogees of their insured Northeast Utilities Service Company, Plaintiffs v. Northeast Utilities Service Company, as agent of Public Service Company of New Hampshire, Plaintiff-Appellant v. BendTec, Inc., Defendant-Appellee.
Nos. 15-2596, 15-2598.
United States Court of Appeals, Eighth Circuit.
Filed: May 13, 2016.
Rehearing and Rehearing En Banc Denied June 17, 2016.
Submitted: March 16, 2016.
Jonathan P. Schmidt, argued, David A. Schooler, Jonathan P. Schmidt, Daniel N. Moak, W. Knapp Fitzsimmons, on the brief, Minneapolis, MN, for Appellee.
Before MURPHY, BEAM, and GRUENDER, Circuit Judges.
MURPHY, Circuit Judge.
The Public Service Company of New Hampshire hired Siemens to replace a turbine in one of its power plants. BendTec, Inc. manufactured steam pipes for the new turbine as a subcontractor for Siemens. After the turbine was turned on, it became damaged by fine grit. The utility and its insurers sued BendTec for negligence, alleging that its pipes were the source of the grit and had been improperly cleaned. The district court1 granted summary judgment to BendTec, concluding that the negligence claim was barred under the two year limitations period in
I.
Public Service Company of New Hampshire (PSCNH) operates a coal power plant in Bow, New Hampshire. The “Merrimack Station” power plant has two generating units each consisting of a coal fired boiler and a turbine generator. Unit 2 was built in 1968, and PSCNH decided to upgrade it in 2006 by purchasing a new 340 megawatt turbine from Siemens Power Generation. Siemens was to be the supplier of the new generator rotor and turbine, and it also agreed to procure the manufacture, supply, and installation of all necessary components. Siemens warranted that all equipment, materials, and supplies furnished by or through it would be free from defects. The new turbine was installed by Siemens in the spring of 2008.
“Turbine piping” carries high pressure steam from the boiler to the turbine. Siemens had selected BendTec as the subcontractor to fabricate to its specifications the turbine piping for the new PSCNH turbine. The piping consists of twenty one sections of large pipe which are transported by flatbed truck and moved using cranes. BendTec cleaned the interior of the piping using abrasive grit blasting, a process which involves spraying steel grit at the piping under high pressure. It then conducted a visual inspection of the pipes, capped them, and shipped them to the Merrimack Station. The piping was delivered on April 8, 2008 and installed by Siemens. After shipping the pipes, BendTec had no further involvement with the project.
On May 22, 2008 PSCNH started the turbine for the first time. Power output was lower than expected, and eventually the turbine was shut down and an inspection revealed steel grit blast material
On May 21, 2014 PSCNH‘s agent Northeast Utilities Service Company, along with Associated Electric and Gas Insurance Services, Zurich American Insurance Company, and Energy Insurance Mutual Limited, the insurers and subrogees of Northeast Utilities Service Company (collectively, “plaintiffs“), sued BendTec for negligence. The district court granted summary judgment to BendTec, concluding that the plaintiffs’ claim was barred under the applicable statute of limitations. The plaintiffs appeal.
II.
We review a grant of summary judgment de novo. Woods v. DaimlerChrysler Corp., 409 F.3d 984, 990 (8th Cir.2005). Summary judgment is appropriate if there are no genuine issues of material fact when the record is viewed in the light most favorable to the nonmoving party, and the moving party is entitled to judgment as a matter of law. Id.; see
Minnesota has a two year statute of limitations for contract and tort claims “arising out of the defective and unsafe condition of an improvement to real property” and “brought against any person performing or furnishing the design, planning, supervision, materials, or observation of construction or construction of the improvement to real property.”
The questions presented here are whether the turbine piping installed on the new turbine at the Merrimack Station was an “improvement to real property,” and if so, whether BendTec fits the subdivision 1(e) exception for a manufacturer or supplier of equipment or machinery.
A.
The Minnesota Supreme Court has said that courts should use a “common-sense interpretation” of the phrase “improvement to real property” under section 541.051, defining such an improvement as
[A] permanent addition to or betterment of real property that enhances its capital value and that involves the expenditure of labor or money and is designed to make the property more useful or valuable as distinguished from ordinary repairs.
Lietz v. N. States Power Co., 718 N.W.2d 865, 869 (Minn.2006); see also Kloster-Madsen, Inc. v. Tafi‘s, Inc., 303 Minn. 59, 226 N.W.2d 603, 607 (1975)(same) (quoting
The installation of the new turbine at Merrimack Station, at a total cost of over $12 million, meets each of the three main factors used by Minnesota courts to ascertain whether something is an improvement to real property. See Siewert v. N. States Power Co., 793 N.W.2d 272, 287 (Minn.2011). The turbine is a “permanent addition” to the power plant. See id. The installation of the turbine involved large expenditures of labor and money. See id. The turbine enhanced the capital value of the power plant because it was “designed to make the real property more useful or valuable, rather than intended to restore the property‘s previous usefulness or value.” See id. Plaintiffs’ own complaint characterizes the project as an “upgrad[e]” designed to “increase power generation capacity,” as opposed to simply a restoration of the existing turbine.
In Harder v. ACandS, 179 F.3d 609, 612 (8th Cir.1999), we considered whether a steam turbine at a power plant was an “improvement to real property” for the purposes of Iowa‘s statute of limitations. Id. (analyzing
We further conclude that the BendTec piping was an improvement to real property. We concluded in Harder that asbestos blankets attached to a steam turbine were improvements because they were permanent additions to the turbine and enhanced the property‘s capital value. See Harder, 179 F.3d at 612-13. Here, the pipes at issue are large integral components of the turbine and therefore permanent additions to it. Purchasing and installing the pipes involved significant expenditures of labor and capital, and enhanced the property‘s value. Because the turbine and the piping are improvements to real property and BendTec furnished the piping, this lawsuit falls within the scope of
B.
The plaintiffs contend that the subdivision 1(e) exception applies to BendTec because it was a “manufacturer or supplier of any equipment or machinery.”
The Minnesota Supreme Court has not yet clarified the test for determining whether a defendant is a manufacturer or supplier of “equipment or machinery” and thus subject to the subdivision 1(e) exception. Minnesota Court of Appeals cases to date have also “provided little guidance or clarity” as to the meaning of that term. Integrity Floorcovering, 521 F.3d at 919. That court has however made a distinction between “ordinary building materials, which are incorporated into construction work outside the control of their manufacturers or suppliers, at the direction of architects, designers, and contractors,” and machinery and equipment which is “subject to close quality control at the factory and may be made subject to independent manufacturer‘s warranties, voidable if the equipment is not installed and used in strict compliance with the manufacturer‘s instructions.” Id. (quoting Cape Henry Towers, Inc. v. Nat‘l Gypsum Co., 229 Va. 596, 331 S.E.2d 476, 480 (1985), adopted by Red Wing Motel Investors v. Red Wing Fire Dep‘t, 552 N.W.2d 295, 297 & n. 2 (Minn.App.1996)).
In Integrity Floorcovering, we noted that classifying a bathroom ventilation fan as either “ordinary building material” or “equipment or machinery” posed a difficult question because the fan shared characteristics of both categories as defined by the Minnesota Court of Appeals. Integrity Floorcovering, 521 F.3d at 919-20. The available limited precedent categorizes items as “ordinary building materials” if they are “integrally incorporated as part of a building structure.” Id. at 920 (collecting cases). Within the category of “equipment or machinery” covered by the exception are items which “are typically large scale items, which are not integral to or incorporated into the building, and could exist separately from the building structure.” Id. (collecting cases).
We believe that the Minnesota courts would not consider BendTec‘s turbine piping to be equipment or machinery covered by the exception. On the one hand, the piping was subject to quality control at BendTec‘s factory and was covered by a warranty. The pipes are also large scale items, and they are not “ordinary” in the same sense as building materials available at retail like the bathroom fan we considered in Integrity Floorcovering. See Integrity Floorcovering, 521 F.3d at 920. On the other hand, the pipes have several of the characteristics of ordinary building materials. The turbine piping was incorporated into the turbine by Siemens outside of BendTec‘s control. Siemens designed the piping and installed it according to its own specifications, not to any instructions from BendTec. Further, the turbine piping was integrally incorporated into the turbine which is itself an improvement to the real property at Merrimack Station. On balance, the category of “ordinary building materials” is a better fit for the turbine piping.
We also note that the statute of limitations explicitly covers “any person ... furnishing ... materials” for improvements to real property.
Because the two year statute of limitations in
III.
For these reasons the judgment of the district court is affirmed.
