Matter of National Fuel Gas Supply Corp. v. SchuecklerMatter of National Fuel Gas Supply Corp. v. Schueckler
PRESENT: CARNI, J.P., LINDLEY, NEMOYER, CURRAN, AND WINSLOW, JJ.
PHILLIPS LYTLE LLP, BUFFALO (CRAIG A. LESLIE OF COUNSEL), FOR PETITIONER-RESPONDENT.
NeMoyer, J.
Appeal from an order of the Supreme Court, Allegany County (Thomas P. Brown, A.J.), entered June 28, 2017. The order, inter alia, granted the petition for the acquisition of easements.
It is hereby ORDERED that the order so appealed from is reversed on the law without costs and the petition is dismissed.
Opinion by NeMoyer, J.:
Petitioner National Fuel Gas Supply Corporation wants to build an interstate gas pipeline that would run, in part, across the land of Joseph A. Schueckler and Theresa F. Schueckler (respondents). The State of New York, however, has blocked the entire pipeline project by denying petitioner the necessary environmental permits. Notwithstanding the barrier posed by the State‘s regulatory action, petitioner still seeks to acquire easements over respondents’ land by eminent domain. This appeal therefore presents a novel question of condemnation law: can a corporation involuntarily expropriate privately-owned land when the underlying public project cannot be lawfully constructed? We answer that question firmly in the negative.
I
This case lies at the intersection of federal law governing interstate pipeline construction and state law governing eminent domain procedure. In order to properly contextualize the underlying facts and the parties’ arguments, we will first sketch out the applicable statutory framework.
A. Federal Interstate Pipeline Construction Law
The regulatory process for constructing a natural gas pipeline across state lines is spelled out in the federal Natural Gas Act (NGA) (
Subsection (e) of section 717f, in turn, says as follows:
“a certificate shall be issued to any qualified applicant therefor, authorizing the whole or any part of the . . . construction . . . covered by the application, if it is found that the applicant is able and willing properly to do the acts and to perform the service proposed and to conform to the provisions of [the NGA] and the requirements, rules, and regulations of the [FERC] thereunder, and that the proposed . . . construction . . . , to the extent authorized by the certificate, is or will be required by the present or future public convenience and necessity; otherwise such application shall be denied. The [FERC] shall have the power to attach to the issuance of the certificate and to the exercise of the rights granted thereunder such reasonable terms and conditions as the public convenience and necessity may require.”
The import of a valid and effective certificate cannot be overstated in this context, for the NGA explicitly provides that “[n]o natural-gas company . . . shall . . . undertake the construction or extension of any [pipeline] facilities . . . unless there is in force . . . a certificate of public convenience and necessity issued by the [FERC] authorizing such acts” (
In exercising its power conferred by
Critically, however, the CWA provides that “[n]o license or permit shall be granted if [a WQC] has been denied by the State” (
B. State Eminent Domain Law
When a “corporation is unable to agree for the purchase of any real property required for the [construction of a pipeline], it shall have the right to acquire title thereto by condemnation” (
“The main purpose of article 2 of the EDPL” — the first step of the eminent domain process — “is to ensure that an appropriate public purpose underlies any condemnation” (City of New York, 6 NY3d at 546; see
The alternative procedure relevant to this case is set forth in
II
With the statutory background in mind, we turn now to the specifics of this case.
In February 2017, the FERC granted petitioner‘s application for a certificate of public convenience and necessity to construct and operate a 97-mile natural gas pipeline from Pennsylvania into western New York. The pipeline‘s proposed route travels directly across respondents’ land in the Town of Clarksville, Allegany County. Within the voluminous certificate, the FERC found that petitioner‘s “proposed [pipeline] project is consistent with the Certificate Policy Statement,” i.e., the public interest. “Based on this finding and the environmental review for the proposed project,” the FERC further found “that the public convenience and necessity require approval and certification of the project.”
The certificate, however, was not unconditional. Throughout the certificate, the FERC emphasized that the authorization conferred thereby was “subject to the conditions described [t]herein,” and that the finding of public necessity was “subject to the environmental and other conditions in this order.” Insofar as relevant here, the “certificate . . . authorizing [petitioner] to construct and operate the [pipeline]” was “conditioned on [petitioner‘s] compliance with the environmental conditions in Appendix B.”
For its part, Appendix B required petitioner, before beginning construction, to “file . . . documentation that it has received all applicable authorizations required under federal law.” One of the “authorizations required under federal law” is, of course, a WQC from any affected State. In short, as required by federal law (see
In March 2017, while its WQC application was still pending in Albany, petitioner commenced the instant vesting proceeding pursuant to EDPL article 4 to acquire, by eminent domain,
Shortly after petitioner commenced the vesting proceeding, however, the New York State Department of Environmental Conservation (DEC) denied petitioner‘s application for a WQC. The WQC application, held the DEC, “fails to demonstrate compliance with New York State water quality standards.” Petitioner has taken various steps to challenge the WQC denial, including the filing of a petition for judicial review in the Second Circuit pursuant to
Respondents answered the vesting petition several days after the DEC‘s ruling. Insofar as relevant here, respondents denied that petitioner‘s FERC certificate was currently effective or that such certificate satisfied “the requirements for an exemption under . . .
Supreme Court ultimately granted the petition in its entirety and authorized the acquisition of the easements necessary for the construction and operation of the pipeline. In its written decision, the court first held that petitioner “has shown that FERC has issued it an order granting a certificate of public convenience for its pipeline project, exempting it from the requirements of Article 2 of the EDPL.” Supreme Court also found that respondents’ third affirmative defense was “without merit” because “the [WQC] condition applied to the construction of the pipeline and not to the initiation of eminent domain proceedings.” The court did not elaborate on that conclusion, nor did it explain how petitioner‘s legal entitlement to initiate condemnation proceedings could be divorced from petitioner‘s legal entitlement to build the pipeline that, by its own
Respondents appeal, and we now reverse.
III
The main thrust of respondents’ appellate arguments can be distilled to a single central point: petitioner is not exempt from EDPL article 2 because, following the State‘s WQC denial, petitioner no longer holds a qualifying federal certificate for purposes of the
Petitioner obviously did not conduct a hearing under
Accordingly, as a result of the State‘s WQC denial, petitioner does not currently hold a qualifying federal permit for purposes of
Our conclusion is consistent with the WQC‘s key role in the federal regulatory scheme. As the United States Supreme Court wrote in S.D. Warren Co. v Maine Bd. of Envtl. Protection, the CWA “recast pre-existing law and was meant to continue the authority of the State to act to deny a permit and thereby prevent a Federal license or permit from issuing to a discharge source within such State” (547 US 370, 380 [2006] [internal quotation marks, ellipsis, and brackets omitted]). Consequently, as the DC Circuit elaborated, the CWA “gives a primary role to states to block [construction] projects by imposing and enforcing water quality standards that are more stringent than applicable federal standards. . . . FERC‘s role is limited to awaiting, and then deferring to, the final decision of the state. Otherwise, the state‘s power to block the project would be meaningless” (City of Tacoma, Wash. v FERC, 460 F3d 53, 67 [DC Cir 2006] [internal quotation marks omitted]). So too here; if petitioner is allowed to continue its pursuit of eminent domain in furtherance of a project that has been lawfully blocked by the State, then “the state‘s power to block the project would be meaningless” (id.).
Petitioner‘s contrary arguments are meritless. Initially, petitioner argues throughout its brief that the WQC requirement is only a condition precedent for the construction of the pipeline, not a condition precedent of the certificate itself. And because the certificate itself does not condition petitioner‘s eminent domain power on the issuance of a WQC, petitioner continues, respondents cannot defend this vesting proceeding in reliance on the State‘s denial of the WQC. But this entire line of argument is a non sequitur. Of course the pipeline‘s construction is conditioned on the issuance of a WQC — that is the entire point of the certificate. The certificate has no purpose except to authorize construction of the pipeline and to set the conditions precedent for such construction, and petitioner‘s effort to erect a distinction between a condition precedent of the certificate and a condition precedent for construction is a semantical
Petitioner‘s further attempt to cleave a distinction between a condition of the certificate‘s authorization of construction and a condition of its purported authorization of eminent domain is also wholly unavailing. The certificate itself is not the source of petitioner‘s authority to condemn, and it thus can neither authorize nor prohibit the acquisition of property by eminent domain. Rather, the lodestar of petitioner‘s eminent domain power is the public project authorized by the certificate (
Finally, the fact that respondents might be adequately compensated for their forced sale is entirely beside the point. As the owners of the land at issue, it is up to respondents — and respondents alone — whether or not to convey an interest
IV
At the end of the day, this seemingly complicated case can be explained in these straightforward terms: petitioner is trying to expropriate respondents’ land in furtherance of a pipeline project that, as things currently stand, cannot legally be built. Such an effort turns the entire concept of eminent domain on its head. If the State‘s WQC denial is finally annulled or withdrawn, then petitioner can file a new vesting petition. But until that time, petitioner cannot commence a vesting proceeding to force a sale without going through the entire EDPL article 2 process. Accordingly, the order appealed from should be reversed and the petition dismissed. Respondents’ remaining contentions are academic in light of our determination.
Curran and Winslow, JJ., concur with NeMoyer, J.;
Lindley, J., dissents and votes to affirm in the following opinion in which Carni, J.P., concurs: We respectfully dissent and would affirm. The majority concludes that the petition in this eminent domain proceeding should be dismissed because, “as things currently stand,” the underlying public project, a natural gas pipeline, “cannot be lawfully constructed.” The pipeline cannot lawfully be constructed, the reasoning goes, because the New York State Department of Environmental Conservation (DEC) has denied petitioner‘s application for a water quality certificate (WQC), the issuance of which is one of the many conditions that must be satisfied before petitioner can build the pipeline.
It is undisputed, however, that the Federal Energy Regulatory Commission (FERC) has determined, in an order issued August 6, 2018, that the DEC waived its WQC certification authority under
Even if we were to ignore the most recent FERC order, the DEC‘s denial of the WQC does necessarily not mean that petitioner cannot build the pipeline. As respondents recognize in their post-argument submission, petitioner could obtain the WQC by mitigating environmental concerns expressed by the DEC. For instance, petitioner could use horizontal directional drilling (HDD) to cross various streams, as proposed by the DEC, or it could alter the path of the pipeline to avoid the streams. Although petitioner has stated that using HDD technology is too expensive for its liking, the seminal point here is that the DEC‘s decision does not vitiate the certificate of public convenience and necessity issued by the FERC, nor does it sound the death knell of the pipeline project.
In any event, although the issuance of a WQC by the DEC is a condition that must be met prior to construction of the pipeline, it is not, in our view, a condition precedent to the commencement of this eminent domain proceeding (see Constitution Pipeline Co., LLC v A Permanent Easement for 0.42 Acres and Temporary Easements for 0.46 Acres, in Schoharie County, New York, 2015 WL 12556145, *2 [ND NY, Apr. 17, 2015]). The Natural Gas Act (NGA) grants private natural-gas companies the power to acquire property by eminent domain. A natural gas company may build and operate a new pipeline if it obtains a certificate of public convenience and necessity from the FERC. Here, petitioner‘s proposed pipeline is authorized by a FERC order issued on February 3, 2017, which includes a certificate of public convenience and necessity for the pipeline. As the majority points out, the FERC order is subject to various conditions, one of which requires petitioner to obtain “all applicable authorizations required under federal law.” That condition has
There are, however, various other conditions in the authorizing FERC order, many of which cannot be met until after petitioner has obtained possession of the rights of way for the pipeline. If petitioner is prohibited from exercising its eminent domain authority until it satisfies all of the conditions of the FERC order, as the majority holds, the pipeline can never be built (see Constitution Pipeline Co., LLC, 2015 WL 12556145, *2).
Finally, we note that the FERC has clearly and unambiguously stated that the conditions in its initial order need not be satisfied prior to petitioner commencing a taking proceeding under the eminent domain law. Paragraph 22 of the recent FERC order states that “it is Congress, speaking directly in
The FERC‘s interpretation of its own order is consistent with federal case law. As the Fourth Circuit Court of Appeals has explained, “[o]nce FERC has issued a certificate, the NGA empowers the certificate holder to exercise ‘the right of eminent domain’ over any lands needed for the project” (East Tenn. Nat. Gas Co. v Sage, 361 F3d 808, 818 [4th Cir 2004], quoting
Entered: November 9, 2018
Mark W. Bennett
Clerk of the Court
Notes
The dissent faults us for disregarding the new FERC ruling because it is “no less final than the DEC‘s denial of the WQC.” But the dissent overlooks a crucial distinction between the WQC denial and the new FERC ruling: the former is part of the appellate record and was before Supreme Court at the time of its determination; the latter is dehors the appellate record and did not exist when Supreme Court rendered its determination. It thus makes perfect sense to consider the WQC denial, but not the new FERC ruling, when reviewing the particular determination now before us. After all, our function is to decide whether Supreme Court properly granted the instant petition based on the record before it, not whether its determination could or should have been different had it been made under different circumstances with a different record. The dissent‘s ad hoc approach to intervening developments on appeal would effect a marked departure from longstanding norms of orderly procedure (see generally Rives v Bartlett, 215 NY 33, 39 [1915], rearg denied 215 NY 697 [1915]). Those norms carry particular weight here, where petitioner filed a vesting petition before it even knew whether it could actually build the underlying pipeline project. Flouting norms of orderly procedure by giving effect to the new FERC ruling in this appeal would effectively reward petitioner for its premature filing, and that we decline to do. If petitioner wants to argue that the new FERC ruling has revived the pipeline project, it is free to do so — in a new EDPL article 4 petition in Supreme Court.