J.C. CANNISTRARO, LLC vs. COLUMBIA CONSTRUCTION CO. & another.
SJC-13819
Supreme Judicial Court of Massachusetts
June 26, 2026
Norfolk. February 2, 2026. – June 26, 2026.
Present: Budd, C.J., Gaziano, Kafker, Wendlandt, Georges, Dewar, & Wolohojian, JJ.
Arbitration, Authority of arbitrator, Confirmation of award.
Civil action commenced in the Superior Court Department on August 3, 2020.
Motions to vacate and to confirm an arbitration award were heard by Keren E. Goldenberg, J.
The Supreme Judicial Court granted an application for direct appellate review.
Jeff D. Bernarducci (Seth M. Pasakarnis & Lindsey K.P. Black also present) for Columbia Construction Co.
J. Nathan Cole (Ross C. Wecker also present) for the plaintiff.
The following submitted briefs for amici curiae:
Robert W. Stetson for Real Estate Bar Association for Massachusetts, Inc., & another.
Kenneth E. Rubinstein, Nicholas A. Dube, & Michael J. Amato for Associated General Contractors of Massachusetts & others.
Joseph A. Barra for Electrical Contractors Association of Greater Boston, Inc., & others.
WOLOHOJIAN, J. The question is whether an arbitrator exceeded his authority by awarding recoupment of payments to a general contractor, Columbia Construction Co. (Columbia), that (a) did not timely certify its rejection of invoices submitted by a subcontractor, J.C. Cannistraro, LLC (Cannistraro), and (b) asserted defenses to payment before paying the invoices. See Business Interiors Floor Covering Business Trust v. Graycor Constr. Co., 494 Mass. 216, 225 (2024) (Graycor) (establishing payment prerequisite where contractor does not reject invoices in conformity with requirements of prompt pay act,
Background.3
On February 3, 2017, Columbia entered into a contract for the construction and renovation of an office and manufacturing facility located in Walpole (prime contract). The prime contract was a “contract for construction” as defined in
Columbia then entered into two subcontracts with Cannistraro, both of which contained the following arbitration provision:
“At the sole election of [Columbia], any disputes shall be resolved by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association.”
Cannistraro thereafter proceeded to perform work under both subcontracts and submitted regular monthly requisitions for payment.
In addition, in January 2020, Cannistraro submitted change order requests under each subcontract. Columbia timely rejected those requests and conveyed its reasons for doing so. Approximately two months later, Cannistraro submitted applications and certificates for payment for the change orders
Procedural history.
Cannistraro filed suit in the Superior Court seeking damages in the amount of the invoices. Among other things, Cannistraro‘s amended complaint asserted a claim for violation of the prompt pay act, alleging that Columbia failed to make payments in accordance with the requirements of the statute.6
Once in arbitration, and after discovery, the parties cross-moved for summary judgment. Those cross motions raised, among other things, the question of what, if any, legal consequences were to flow from the fact that Columbia had not timely certified that its rejections of the invoices were made in good faith. The arbitrator, knowing that this legal issue was then pending before the Appeals Court in Tocci Bldg. Corp. v. IRIV Partners, LLC, 101 Mass. App. Ct. 133 (2022) (Tocci), deferred ruling on the cross motions until the Appeals Court issued its decision in that case.
The Appeals Court in Tocci concluded that the good faith certification requirement was “an essential component of the
Columbia complied with the arbitrator‘s order. It then moved to assert a counterclaim for recoupment under rule 6(b) of the AAA Construction Rules, which allows counterclaims to be asserted with leave of the arbitrator.10 Over Cannistraro‘s
In response, Cannistraro filed another motion for summary judgment, in essence arguing that the recoupment counterclaim was foreclosed by Tocci. The arbitrator disagreed. The arbitrator concluded that Tocci did not foreclose Columbia‘s recoupment claim, explaining that Cannistraro had received timely notice of the grounds for Columbia‘s rejection of the invoices even though it had not received timely certifications of good faith.
The arbitrator then conducted a three-day evidentiary proceeding on the recoupment counterclaim, found that Columbia met its burden to prove that Cannistraro‘s invoices were not fair and reasonable, and ruled that Columbia was entitled to recover $576,855.05 plus interest. A final award issued to this effect on April 3, 2024.
Cannistraro next filed in the Superior Court a motion to vacate the final award, pursuant to
“a party does not waive its defenses by failing to approve or reject an invoice within the strict time requirements established by the act. However, a party that neither approves nor rejects a payment application within the requisite time must first make the payment in order to pursue any defenses in a subsequent proceeding related to the invoices, as the invoices have been deemed ‘approved.’ The invoice payments must be made prior to, or contemporaneous with, the raising of the defenses, or the defenses cannot be raised.”
Id. at 217-218. Accordingly, where the general contractor never had paid the disputed invoices, it was precluded from invoking common-law defenses to the subcontractor‘s breach of contract claim for failure to pay. Id. at 225.
Pointing to Graycor, the Superior Court judge concluded that the arbitrator‘s award exceeded his authority because
Discussion.
The question before us is whether, assuming that the sequence of events here was inconsistent with the payment prerequisite established in Graycor,12 the judge erred in vacating the arbitration award on the ground that it exceeded the arbitrator‘s authority. We review a trial judge‘s decision to uphold or vacate an arbitration award de novo. Pittsfield v. Local 447 Int‘l Bhd. of Police Officers, 480 Mass. 634, 637 (2018).
The parties’ agreement to arbitrate is governed by the
As relevant here, one of the limited grounds upon which an arbitration award may be vacated is where an arbitrator exceeds his authority.
Thus, we deal here only with whether the arbitrator exceeded his authority by awarding relief prohibited by law. Awarding relief prohibited by law is not the same thing as awarding relief that constitutes, or results from, an error of law. And, in reviewing an arbitration award, it is essential not to conflate or confuse these two distinct concepts because, while a judge may vacate an arbitration award that is prohibited by law, a judge may not, absent fraud, vacate an award that is an error of law. See Katz, Nannis & Solomon, P.C., 473 Mass. at 795 (“If [an] arbitrator[] in assessing damages commit[s] an error of law or fact, but do[es] not overstep the limits of the issues submitted to [him], a court may not substitute its judgment on the matter” [citation omitted]); Thompson, 435 Mass. at 61. “The fact that an arbitrator has committed an error of law does not alone mean that he has exceeded his authority.” Concerned Minority Educators of Worcester v. School Comm. of Worcester, 392 Mass. 184, 187-188 (1984). See Boston v. Boston Police Patrolmen‘s Ass‘n, 443 Mass. 813, 818 (2005) (Patrolmen‘s Ass‘n) (consistent with strong policy favoring arbitration, arbitrator‘s award is to be upheld “even where it is wrong on
An arbitrator awards relief prohibited by law where the relief “offends public policy or . . . directs or requires a result contrary to express statutory provision.” Plymouth-Carver, 407 Mass. at 1007. Neither situation is presented here. Turning to the latter first, we begin by noting that the prompt pay act does not by its express terms state if or when a recoupment counterclaim may be raised after an invoice is deemed to be approved due to a failure to provide a timely certification of good faith. See
What remains is whether the arbitration award offends public policy. See Lawrence v. Falzarano, 380 Mass. 18, 29 (1980) (arbitration award may be vacated if relief is “contrary to legislative or other public policy“). “[B]ecause the public policy [exception] allows courts to by-pass the normal heavy deference accorded to arbitration awards and potentially to ‘judicialize’ the arbitration process, the judiciary must be
Cannistraro has not met its burden here. The particulars of this case make clear that the arbitrator‘s award does not rise to the level of a violation requiring judicial relief. The public policy that Cannistraro relies on is essentially the statutory requirement of a timely rejection of an invoice that
Conclusion.
The arbitrator did not exceed his authority in awarding recoupment of payments to Columbia, and thus the judge should not have vacated the arbitration award. The judgment is reversed, and the matter is remanded to the Superior Court for entry of a judgment confirming the arbitration award.
So ordered.
