History
  • No items yet
midpage
943 F.3d 1161
8th Cir.
2019

George Wise; Matthew Pekar; Uta Meyer; David Martindale; Robert Walker v. Department of Transportation, United States; Federal Highway Administration; Arkansas Department of Transportation

No. 18-3016

United States Court of Appeals, Eighth Circuit

December 6, 2019

Before SMITH, Chief Judge, WOLLMAN and ERICKSON, Circuit Judges.

United States Court of Appeals

For the Eighth Circuit

___________________________

No. 18-3016

___________________________

George Wise; Matthew Pekar; Uta Meyer; David Martindale; Robert Walker

lllllllllllllllllllllPlaintiffs - Appellants

v.

Department of Transportation, United States; Federal Highway Administration;

Arkansas Department of Transportation

lllllllllllllllllllllDefendants - Appellees

____________

Appeal from United States District Court

for the Eastern District of Arkansas - Little Rock

____________

Submitted: September 26, 2019

Filed: December 6, 2019

____________

Before SMITH, Chief Judge, WOLLMAN and ERICKSON, Circuit Judges.

____________

WOLLMAN, Circuit Judge.

This action arises from the widening of Interstate Highway 630 from six to

eight lanes from Baptist Hospital to University Avenue (approximately 2.5 miles)

within the City of Little Rock, Arkansas (the I-630 project). George Wise and others

filed suit against the U.S. Department of Transportation, the Federal Highway Administration (FHWA), and the Arkansas Department of Transportation (Arkansas

DOT), alleging violations of the National Environmental Policy Act of 1969 (NEPA),

42 U.S.C. § 4321 et seq., and NEPA’s implementing regulations, 40 C.F.R. §§ 1500-

1508. Wise also filed a motion for a temporary restraining order, seeking to enjoin

the defendants from working on the I-630 project. Wise appeals from the denial of

injunctive relief, arguing that the district court1 erred in determining that the I-630

project qualified for a categorical exclusion under 23 C.F.R. § 771.117(c)(22). We

affirm.

I. Background

NEPA requires federal agencies to prepare an environmental assessment or an

environmental impact statement for “major Federal actions significantly affecting the

quality of the human environment.” 42 U.S.C. § 4332(2)(C). “NEPA itself does not

mandate particular results, but simply prescribes the necessary process.” Robertson

v. Methow Valley Citizens Council, 490 U.S. 332, 350 (1989). Categories of actions

“which do not individually or cumulatively have a significant effect on the human

environment and which have been found to have no such effect” do not require an

environmental assessment or an environmental impact statement. 40 C.F.R. § 1508.4;

see Friends of Richards-Gebaur Airport v. FAA, 251 F.3d 1178, 1185-87 (8th Cir.

2001) (setting forth the regulatory background that allows agencies to “categorically

exclude certain types of federal activities from [NEPA’s] case-by-case environmental

assessment review”). FHWA has identified certain actions that do not involve

significant environmental impacts and thus qualify for categorical exclusion from

NEPA’s requirements. See 23 C.F.R. § 771.117. At issue here is the categorical

exclusion for projects that take place “entirely within the existing operational right-

of-way.” See id. § 771.117(c)(22).

Eastern District of Arkansas.

-2-

In October 2016, the defendants reported that the I-630 project qualified for a

categorical exclusion from NEPA’s environmental assessment or environmental

impact statement requirements. The categorical exclusion report outlined the

improvements proposed along I-630, including increasing the travel lanes from six

to eight and replacing all bridges within the project’s limits. The report noted that the

“[e]xisting right of way width varies, ranging from 220 to 400 feet” and explained

that the project did not require any “additional permanent right of way.” Arkansas

DOT already owned the land that would be used for the I-630 project.

Arkansas DOT issued a press release on July 13, 2018, stating that construction

on the I-630 project would begin on Monday, July 16. Wise filed suit and moved for

a temporary restraining order two days later. During a status conference held on

Friday, July 19, 2018, Wise characterized the demolition of the Hughes Street

Overpass as the harm that would be done “between now and Monday,” when the

hearing on Wise’s motion for a temporary restraining order would be held. Wise

asked the district court to disallow demolition of the overpass and immediately enjoin

the defendants from working on the I-630 project. The district court declined to do

so, and the Hughes Street Overpass was demolished that weekend.

Keli Wylie, the program administrator of Arkansas DOT’s Connecting

Arkansas Program, testified at the hearing on Wise’s motion. She explained that the

existing operational right-of-way included traffic lanes and clear zones, “which, in

layman’s terms, [are the areas] outside of the shoulder of the roadway[, and] . . . in

this case it’s 30 feet beyond the edge of the travel way.” Wylie testified that the

existing operational right-of-way was not limited to those areas, however, because it

also included “mitigation areas, drainage areas, interchange ramps, anything that we

maintain or use for transportation purposes.” She explained that the right-of-way for

the I-630 project was clear, but that Arkansas DOT would remove any other trees, if

necessary, to complete the project. According to Wylie, the existing operational

-3-

right-of-way was “property line to property line”—i.e., the entire 220- to 400-foot

expanse owned by Arkansas DOT.

After reviewing the evidence, “particularly the testimony of Keli Wylie,” the

district court concluded that Wise had “failed to establish that any part of the I-630

project construction would go outside of the existing operational right-of-way” and

that it was therefore reasonable for the defendants to conclude that the project

qualified as a categorical exclusion under the regulation. D. Ct. Order of July 27,

2018, at 6. The district court thus denied injunctive relief because, among other

things, Wise had not shown he was likely to succeed on the merits of his claim that

the defendants violated NEPA.

II. Analysis

We reject the defendants’ argument that we lack jurisdiction over this

interlocutory appeal. We have jurisdiction under 28 U.S.C. § 1292(a)(1) because the

district court’s order had the practical effect of denying a preliminary injunction. See

Abbott v. Perez, 138 S. Ct. 2305, 2319 (2018) (“We have previously made clear that

where an order has the ‘practical effect’ of granting or denying an injunction, it

should be treated as such for purposes of appellate jurisdiction.”); Sampson v.

Murray, 415 U.S. 61, 86-88 (1974) (treating an order labeled a temporary restraining

as a preliminary injunction because it had the same practical effect as a preliminary

injunction). We also reject Arkansas DOT’s argument that the appeal should be

dismissed as moot because the action that Wise sought to enjoin has been completed.

Arkansas DOT contends that Wise merely sought to enjoin the demolition of the

Hughes Street Overpass. The record and the district court’s order make clear,

however, that Wise sought to enjoin any further work on the I-630 project, and

Arkansas DOT’s argument to the contrary is misguided.

-4-

“A plaintiff seeking a preliminary injunction must establish that he is likely to

succeed on the merits, that he is likely to suffer irreparable harm in the absence of

preliminary relief, that the balance of equities tips in his favor, and that an injunction

is in the public interest.” Winter v. Nat. Res. Def. Council, Inc., 555 U.S. 7, 20

(2008); see also Dataphase Sys., Inc. v. C L Sys., Inc., 640 F.2d 109, 114 (8th Cir.

1981) (en banc). We review the denial of a preliminary injunction for abuse of

discretion. Richland/Wilkin Joint Powers Auth. v. U.S. Army Corps of Eng’rs, 826

F.3d 1030, 1035-36 (8th Cir. 2016). A district court abuses its discretion if it “rests

its conclusion on clearly erroneous factual findings or if its decision relies on

erroneous legal conclusions.” Id. at 1036 (quoting PCTV Gold, Inc. v. SpeedNet,

LLC, 508 F.3d 1137, 1142 (8th Cir. 2007)).

Wise argues that the district court erred in concluding that he would not

succeed on the merits of his NEPA claim. He contends that the I-630 project required

FHWA to complete an environmental assessment or an environmental impact

statement, because the project did not take place within the “existing operational

right-of-way” and thus did not satisfy the categorical exclusion set forth in 23 C.F.R.

§ 771.117(c)(22). According to Wise, the I-630 project’s additional travel lanes

would require expanded clear zones, which would necessarily be built in areas

outside the existing operational right-of-way.

Wise argues that the district court rested its decision on the erroneous legal

conclusion that “existing operational right-of-way” meant the entire right-of-way

owned by Arkansas DOT. He contends that the term is limited to lanes of travel,

shoulders, and clear zones. This limitation conflicts with the definition provided in

the regulation, which states that an “[e]xisting operational right-of-way refers to right-

of-way that has been disturbed for an existing transportation facility or is maintained

for a transportation purpose.” See 23 C.F.R. § 771.117(c)(22). The regulation

explains that an existing operational right-of-way includes features like mitigation

areas and landscaping. Id. (providing a non-exhaustive list of “features associated

-5-

with the physical footprint of the transportation facility” and “areas maintained for

transportation purposes”).2

Wise claims that his reading of the regulation is supported by the explanatory

text accompanying the notice of the final rule, which states, “a project within the

operational right-of-way that requires the creation of new clear zones or extension of

clear zone areas beyond what already exists would not qualify” for categorical

exclusion. Environmental Impact & Related Procedures, 79 Fed. Reg. 2107-01, 2113

(Jan. 13, 2014). To interpret this text consistently with the regulation, we conclude

that the explanatory text does not apply when the new or extended clear zones are

built within the “existing operational right-of-way,” as defined by the regulation. We

Existing operational right-of-way refers to right-of-way that has been

disturbed for an existing transportation facility or is maintained for a

transportation purpose. This area includes the features associated with

the physical footprint of the transportation facility (including the

roadway, bridges, interchanges, culverts, drainage, fixed guideways,

mitigation areas, etc.) and other areas maintained for transportation

purposes such as clear zone, traffic control signage, landscaping, any

rest areas with direct access to a controlled access highway, areas

maintained for safety and security of a transportation facility, parking

facilities with direct access to an existing transportation facility, transit

power substations, transit venting structures, and transit maintenance

facilities. Portions of the right-of-way that have not been disturbed or

that are not maintained for transportation purposes are not in the existing

operational right-of-way.

23 C.F.R. § 771.117(c)(22). The regulation now states, “Existing operational right-

of-way means all real property interests acquired for the construction, operation, or

mitigation of a project.” Id. (effective Nov. 28, 2018); see Environmental Impacts &

Related Procedures, 83 Fed. Reg. 54,480, 54,487 (Oct. 29, 2018) (revising the

definition of “existing operational right-of-way”).

-6-

thus conclude that the district court properly rejected Wise’s proposed limitation on

the term’s definition.

Applying the plain language of the regulation, the district court concluded that

Wise did not present evidence to establish that the area required for the I-630 project

required expansion beyond the existing operational right-of-way. Wise has offered

calculations regarding the additional area required for the project’s new traffic lanes

and expanded clear zones, and he contends that “basic mathematics” render not

credible Wiley’s testimony that the I-630 project will take place within the existing

operational right-of-way. Appellant’s Br. 13. But Wise again incorrectly limits the

term’s definition to travel lanes, shoulders, and clear zones, and he has not shown that

the additional area previously had not been disturbed or maintained for transportation

purposes. We thus conclude that Wise has failed to show that the district court relied

on any clearly erroneous factual findings in denying Wise’s motion for injunctive

relief.

Finally, Wise argues that the I-630 project does not qualify for a categorical

exclusion because it will have significant noise and air-quality impact and it involves

unusual circumstances. See 23 C.F.R. § 771.117(a)-(b). He has not shown that

FHWA’s determination to the contrary is arbitrary, capricious, an abuse of discretion,

or otherwise not in accordance with law, however. See Friends of Richards-Gebaur

Airport, 251 F.3d at 1187 (“We review an agency’s determination that an action falls

within a categorical exclusion under the arbitrary and capricious standard.”).

Having failed to show that his claim was likely to succeed on the merits, Wise

has not established that the district court abused its discretion in denying his request

for injunctive relief. The order denying Wise’s request for a preliminary injunction

is affirmed.

______________________________

-7-

Notes

1
The Honorable James M. Moody, Jr., United States District Judge for the
2
During the relevant time period the regulation provided:

Case Details

Case Name: George Wise v. Department of Transportation
Court Name: Court of Appeals for the Eighth Circuit
Date Published: Dec 6, 2019
Citations: 943 F.3d 1161; 18-3016
Docket Number: 18-3016
Court Abbreviation: 8th Cir.
Read the detailed case summary
AI-generated responses must be verified
and are not legal advice.
Log In