FINCA SANTA ELENA, INC., et al., Plaintiffs, v. U.S. ARMY CORPS OF ENGINEERS, et al., Defendants.
Civil Action No. 11-cv-296 (RLW)
United States District Court, District of Columbia.
July 9, 2012.
878 F. Supp. 2d 363
ROBERT L. WILKINS, District Judge.
Peter Kryn Dykema, Michele L. Walter, U.S. Department of Justice, Washington, DC, for Defendants.
MEMORANDUM OPINION
ROBERT L. WILKINS, District Judge.
Plaintiffs Finca Santa Elena, Inc. (“Finca“), the Roman-Mas Foundation, and Angel Roman-Mas (collectively “Plaintiffs“) have sued Defendants U.S. Army Corps of Engineers and its Chief, Lt. Gen. Robert L. Van Antwerp (“Corps“), in connection with the Corps’ Rio de la Plata stream stabilization/flood control project (“the Project“). Although the Project covers a seven-mile portion of the Rio de la Plata River, only Phase 1A—the first phase of the project covering the two most downstream miles of the river—has commenced. In their ten-count Complaint, Plaintiffs challenge the entire Project, claiming violations of the Clean Water Act (“CWA“), the National Environmental Policy Act (“NEPA“), and the National Historic Preservation Act (“NHPA“).
Defendants’ partial motion to dismiss is based on two theories: 1) Counts VIII and X should be dismissed because Plaintiff Finca lacks standing to challenge Phase 1A; and 2) Plaintiffs’ claims should be dismissed to the extent they challenge any phase of the Project beyond Phase 1A (referred to in this Opinion as the “Upstream Project Components“). At a status conference with the Court on April 25, 2012, the parties agreed that it was not appropriate at this time for the Court to rule on whether Plaintiffs have standing with respect to Counts VIII and X. Accordingly, Defendants’ Motion as to those two counts has been denied without prejudice. Thus, the only issue before the Court is whether Plaintiffs’ claims should be dismissed to the extent those claims challenge the Upstream Project Components. For the following reasons, Defendants’ Partial Motion to Dismiss is GRANTED.
FACTUAL SUMMARY
The Rio de la Plata (the “River“) is located approximately 11 miles west of San Juan, Puerto Rico. See First Amended Complaint (“FAC“) ¶ 1. The Corps has undertaken the Project to address flooding in residential areas located within the River‘s floodplain. (FAC ¶ 1). The Project includes seven miles of channel modifications to the River, 7.6 miles of levee construction, and the replacement of three bridges. (Id.). Although it was originally proposed as a single-phase project, the Project is now divided into four phases and five construction contracts. (FAC ¶ 63). Currently, only Phase 1A has received funding and has been scheduled for construction. (FAC ¶¶ 2-3).
The “study, design and approval” of the Project has been modified over decades, during which, according to Plaintiffs, there have been “numerous changes” in the Project‘s scope. (FAC ¶ 5). The Court will not recount the entire complex factual history of the Project, but will note some significant events. Between 1982 and 1988,
In 2004, the Corps proposed and approved additional changes to the Project. (FAC ¶ 99). In connection with these changes, the Corps issued a Supplemental Environment Assessment (“2004 SEA“), followed by another FONSI (“2005 FONSI“) in 2005. (FAC ¶¶ 101, 108; Scarborough Decl. ¶ 13). In 2008, the Department of Natural and Environmental Resources of Puerto Rico took control of the Project and applied for a
It was not until 2009, when
Defendants contend through a number of uncontroverted affidavits that several steps must occur before construction on any of the Upstream Project Components can proceed. Defendants contend that there is currently no funding for the Project other than Phase 1A and that separate Congressional appropriations would need to be made. (Scarborough Decl. ¶ 18). Moreover, there is no guarantee that funds will ever be appropriated for the Upstream Project Components. (Tolle Decl. ¶ 7; Ornella Decl. ¶ 10; Griffith Decl. ¶ 16).
Further administrative and environmental review would also be needed. Based on administration policy, the Corps would be required to update the project evaluation. (Griffith Decl. ¶ 16). According to the Corps, this will involve preparing a Limited Reevaluation Report (“LRR“), which would “assess the current economic viability of the project, update environmental compliance, and validate (or change) the initial investment recommendation.” (Id.). Although budget requests have been submitted for the preparation of an LRR, those requests have not been acted upon. (Scarborough Decl. ¶ 19). Until an LRR has been prepared, the future portions of the Project cannot compete for funds. (Id.).
Because the design work for the Upstream Project Components has not been completed, even Phase 1B is not ready for construction. (Scarborough Decl. ¶ 15). Further design work would need to be completed before the Upstream Project Components are implemented. (McCullough Decl. ¶ 10). Further hydrologic modeling would also need to be conducted. (Nelson Decl. ¶ 5). Additional NHPA 106 consultation may also be required and, pursuant to the District Office‘s Project Management Business Process, the solicitation and contracting process would need to be initiated and concluded. (McCullough Decl. ¶ 10; Tolle Decl. ¶¶ 5, 7).
ANALYSIS
A. Parties’ Arguments
Defendants argue that the only portion of the Project that has actually been “funded, finally designed and fully approved” is Phase 1A. (Dkt. No. 18 at 8). Defendants argue that any work upstream of Phase 1A is “a highly uncertain prospect” and whether any of the Upstream Project Components will ever receive funding is “a matter of speculation.” (Id. at 8, 13). Moreover, the Upstream Project Components will require “funding, design work, and additional environmental and archeological review,” before any may proceed. (Dkt. No. 18 at 23). Because the likelihood of the Upstream Project Components going forward is mere speculation, Defendants contend all claims regarding those portions of the Project are unripe and must be dismissed without prejudice. (Id. at 23, 26).
According to Plaintiffs, the Corps’ 2005 FONSI,2 authorization of river modifications and wetland filling, and finding that the Project would not affect historic prop
B. Standard of Review
The Corps has moved for partial dismissal under
When the movant‘s purpose is to challenge the substance of the jurisdictional allegations, he may use affidavits and other additional matter to support the motion.... [There are] a wide array of cases from the four corners of the federal judicial system involving the district court‘s broad discretion to consider relevant and competent evidence on a motion to dismiss for lack of subject matter jurisdiction to resolve factual issues ... [O]nce a factual attack is made on the federal court‘s subject matter jurisdiction, the district judge is not obliged to accept the plaintiff‘s allegations as true and may examine the evidence to the contrary and reach his or her own conclusion on the matter.
5B CHARLES ALAN WRIGHT AND ARTHUR MILLER, FEDERAL PRACTICE AND PROCEDURE: CIVIL § 1350, 159-198 (3d ed.2004) (citations and footnotes omitted) (emphasis added).
Before reaching the merits of a claim, the Court must satisfy itself that the dispute “lies within the constitutional and prudential boundaries of the court‘s jurisdiction.” Ctr. for Biological Diversity v. Interior, 563 F.3d 466, 475 (D.C. Cir. 2009) (quoting Util. Air Regulatory Group v. EPA, 320 F.3d 272, 277 (D.C. Cir. 2003)). “Ripeness, while often spoken of as a justiciability doctrine distinct from standing, in fact shares the constitutional requirement of standing that an injury in fact be certainly impending.” Nat‘l Treasury Emp. Union v. United States, 101 F.3d 1423, 1427 (D.C. Cir. 1996); see also Wyoming Outdoor Council v. U.S. Forest Service, 165 F.3d 43, 50 (D.C. Cir. 1999) (ripeness doctrine closely associated with standing doctrine). For a claim to be ripe under
Even if the “constitutional requisites for
[The] basic rationale is to prevent the courts, through avoidance of premature adjudication, from entangling themselves in abstract disagreements over administrative policies, and also to protect the agencies from judicial interference until an administrative decision has been formalized and its effects felt in a concrete way by the challenging parties.
Abbott Labs. v. Gardner, 387 U.S. 136, 148-49 (1967) (emphasis added). Premature review of an agency action “denies the agency an opportunity to correct its own mistakes and to apply its expertise.” Wyoming Outdoor Council, 165 F.3d at 50 (quoting Ohio Forestry Ass‘n Inc. v. Sierra Club, 523 U.S. 726, 735 (1998)). Therefore, a controversy is not prudentially ripe if further administrative processes would aid in the development of any facts needed by the court to decide the question presented. New York State Ophthalmological Soc‘y v. Bowen, 854 F.2d 1379, 1386 (D.C. Cir. 1988). Further, a claim is not ripe where the “possibility that further consideration will actually occur before [implementation] is not theoretical, but real.” Ohio Forestry, 523 U.S. at 735. “Put simply, the doctrine of prudential ripeness ensures that
In deciding whether a challenge to an agency‘s decision is prudentially ripe, the court must examine “the fitness of the issues for judicial decision” and the “hardship to the parties of withholding court consideration.” Wyoming Outdoor Council, 165 F.3d at 48 (quoting Abbott Labs., 387 U.S. at 149). Accordingly, courts must consider: “1) whether delayed review would cause hardship to the plaintiffs; 2) whether judicial intervention would inappropriately interfere with further administrative action; and 3) whether the courts would benefit from further factual development of the issues presented.” Wyoming Outdoor Council, 165 F.3d at 48-49 (quoting Ohio Forestry, 523 U.S. at 733).
C. Plaintiffs’ Challenge to the Upstream Project Components is Not Prudentially Ripe
Although it is doubtful whether Plaintiffs have met their burden to show
Plaintiffs have failed to establish that their challenges to the Upstream Project Components are prudentially ripe. As discussed above, it is uncontested that, among other things: 1) there is currently no funding for any of the Upstream Project Components, nor any guarantee that the Corps will ever receive funding; 2) further administrative and environmental review would need to be completed before the Upstream Project Components could go forward; 3) there has been no funding approved even to perform the additional administrative review; 4) the Upstream Project Components are still in the design phase; and 5) the solicitation and contracting process still needs to be initiated and concluded. Defendants’ declarations, moreover, reflect that construction on the Upstream Project Components may never go forward. Plaintiffs have failed to controvert or oppose Defendants’ declarations in any way. Nor have Plaintiffs asked this Court to allow Plaintiffs to take limited discovery to probe those declarations. Instead, Plaintiffs simply state that, because the Corps issued a 2005 FONSI as to the entire Project, Plaintiffs claims as to the entire Project are ripe.4
The fitness requirement of the prudential inquiry “is primarily meant to protect ‘the agency‘s interest in crystallizing its policy before that policy is subjected to judicial review and the court‘s interests in avoiding unnecessary adjudication and in deciding issues in a concrete setting.‘” American Petroleum Inst., 683 F.3d at 387 (quoting Wyoming Outdoor Council, 165 F.3d at 49). As the Circuit recently held, “[c]ourts decline to review tentative agency positions because doing so severely compromises the interests the ripeness doctrine protects....” Id. (internal quotation marks omitted).
Plaintiffs have failed to show that their challenge to the Upstream Project Components is fit for review. Plaintiffs’ challenge is not a pure legal challenge, and (as stated above) Plaintiffs do not contest Defendants’ sworn statements that the Corps will likely conduct additional administrative and environmental review. In fact, the history of this case—as documented in
Given that it is currently unknown whether any of the Upstream Project Components will ever go forward, Plaintiffs have not shown that delayed review would cause them “immediate and significant” hardship. See American Petroleum Inst., 683 F.3d at 389. There is no imminent threat of injury to Plaintiffs from the Upstream Project Components. Moreover, to the extent that Plaintiffs may claim hardship in being required to bring more than one legal challenge, “the Court has not considered this kind of litigation cost saving sufficient by itself to justify review in a case that would otherwise be unripe.” Ohio Forestry, 523 U.S. at 734-35 (rejecting Sierra Club‘s argument that it would be easier and cheaper to just mount one legal challenge now); see also American Petroleum Inst., 683 F.3d at 389 (“Considerations of hardship that might result from delaying review will rarely overcome the finality and fitness problems inherent in attempts to review tentative positions.“) (internal quotation marks and citations omitted).
Having considered the factors on prudential ripeness, and for the foregoing reasons, this Court finds that Plaintiffs’ claims as they relate to the Upstream Project Components are not prudentially ripe for adjudication. Defendants’ Partial Motion to Dismiss is, therefore, GRANTED. An Order accompanies this Memorandum.
ROBERT L. WILKINS
District Judge
