ELECTRICAL CONTRACTORS, INC. v. INSURANCE COMPANY OF THE STATE OF PENNSYLVANIA
SC 19105
Supreme Court of Connecticut
December 16, 2014
Palmer, Zarella, Eveleigh, McDonald, Espinosa and Robinson, Js.
Argued January 9
******************************************************
The ‘‘officially released’’ date that appears near the beginning of each opinion is the date the opinion will be published in the
All opinions are subject to modification and technical correction prior to official publication in the Connecticut Reports and Connecticut Appellate Reports. In the event of discrepancies between the electronic version of an opinion and the print version appearing in the
The syllabus and procedural history accompanying the opinion as it appears on the Commission on Official Legal Publications Electronic Bulletin Board Service and in the
******************************************************
Steven B. Kaplan, with whom was Paul R. Fitzgerald, for the appellant (plaintiff).
Todd R. Regan, for the appellee (defendant).
Matthew M. Horowitz and Susan Evan Jones filed a brief for the Surety and Fidelity Association of America as amicus curiae.
Opinion
PALMER, J. Under
The record certified by the District Court contains the following undisputed facts and procedural history. The Morganti Group, Inc., was the general contractor on the Newtown High School renovations and expansion project. Morganti entered into a subcontract with the plaintiff, Electrical Contractors, Inc., for the latter to provide labor, equipment, and materials relating to the electrical work for the project. In July, 2009, pursuant to
In April, 2011, the plaintiff submitted to Morganti a request for equitable adjustment to the subcontract price in the amount of $751,190.63 to recoup additional costs allegedly incurred as a result of Morganti’s deficient performance. In May, 2011, the plaintiff updated and adjusted its claim to $746,300.25. Morganti did not respond substantively to these claims.
On June 3, 2011, the plaintiff sent the defendant notice of its claim via certified mail, pursuant to
On September 16, 2011, the plaintiff commenced an action in the United States District Court for the District of Connecticut, claiming, inter alia, that: (1) the defendant was obligated to pay the full sum of $746,300.25 allegedly due under the payment bond; and (2) the defendant, acting in bad faith and without legal basis, had failed to (a) make any payment under the surety bond, (b) assert a good faith dispute, or (c) serve notice on the plaintiff denying liability for the unpaid portions of the claim. The parties subsequently filed cross motions for summary judgment. In its motion, the plaintiff alleged that because the defendant had failed to make payment, dispute the claim in good faith, or deny liability on the claim within the ninety day notice period provided by
The District Court determined that the proper resolution of the parties’ claims turns on the correct interpretation of
Resolution of this question involves an issue of statutory interpretation over which we exercise plenary review. Parrot v. Guardian Life Ins. Co. of America, 273 Conn. 12, 18, 866 A.2d 1273 (2005). We therefore begin our analysis with the language of
On its face, the statute contains no default provision and nowhere provides that a surety waives its right to raise substantive defenses or is subject to automatic forfeiture if it fails to satisfy the ninety day response requirement. Indeed,
Although ‘‘we generally will not look for interpretative guidance beyond the language of the statute when the words of that statute are plain and unambiguous . . . our past decisions have indicated that the use of the word shall, though significant, does not invariably create a mandatory duty.’’9 (Internal quotation marks omitted.) State v. Trahan, 45 Conn. App. 722, 730, 697 A.2d 1153, cert. denied, 243 Conn. 924, 701 A.2d 660 (1997). Indeed, we frequently have found statutory duties to be directory, notwithstanding the legislature’s use of facially obligatory language such as ‘‘shall’’ or ‘‘must.’’ See, e.g., Weems v. Citigroup, Inc., 289 Conn. 769, 788–94, 961 A.2d 349 (2008) (employer’s use of improper form did not invalidate wage deductions); United Illuminating Co. v. New Haven, 240 Conn. 422, 462–67, 692 A.2d 742 (1997) (assessor’s failure to provide notice within thirty days of hearing did not invalidate assessment); Metropolitan District Commission v. AFSCME, Council 4, Local 184, 237 Conn. 114, 122, 676 A.2d 825 (1996) (failure to hold executive session did not require that arbitrators’ award be vacated); Katz v. Commissioner of Revenue Services, 234 Conn. 614, 617, 662 A.2d 762 (1995) (commissioner’s failure to act on refund claim within ninety days did not preclude denial of claim); Leo Fedus & Sons Construction Co. v. Zoning Board of Appeals, 225 Conn. 432, 446, 623 A.2d 1007 (1993) (zoning board of appeals not subject to automatic approval doctrine on basis of its failure to hold public hearing within statutory time limit); Jones v. Mansfield Training School, 220 Conn. 721, 726–28, 601 A.2d 507 (1992) (use of word ‘‘shall’’ was directory and did not create exclusive remedy for injured worker); Ghent v. Planning Commission, supra, 219 Conn. 516 and n.4 (commission’s failure to file transcript of hearing with court did not invalidate appeal); Tramontano v. Dilieto, 192 Conn. 426, 433, 472 A.2d 768 (1984) (acts of public official performed at time beyond limit prescribed are nonetheless effective); Broadriver, Inc. v. Stamford, 158 Conn. 522, 529–30, 265 A.2d 75 (1969) (redevelopment agency’s failure to file return within ninety days of notice to property owner did not invalidate statutory taking), cert. denied, 398 U.S. 938, 90 S. Ct. 1841, 26 L. Ed. 2d 270 (1970); Gallup v. Smith, 59 Conn. 354, 356–58, 22 A. 334 (1890) (that judge of adjoining district was cited in by disqualified judge, rather than by clerk, did not invalidate subsequent appointment of trustee); see also J. Evans, ‘‘Mandatory and Directory Rules,’’ 1 Legal
Our prior cases have looked to a number of factors in determining whether such requirements are mandatory or directory. These include: (1) whether the statute expressly invalidates actions that fail to comply with its requirements or, in the alternative, whether the statute by its terms imposes a different penalty; (2) whether the requirement is stated in affirmative terms, unaccompanied by negative language; (3) whether the requirement at issue relates to a matter of substance or one of convenience; (4) whether the legislative history, the circumstances surrounding the statute’s enactment and amendment, and the full legislative scheme evince an intent to impose a mandatory requirement; (5) whether holding the requirement to be mandatory would result in an unjust windfall for the party seeking to enforce the duty or, in the alternative, whether holding it to be directory would deprive that party of any legal recourse; and (6) whether compliance is reasonably within the control of the party that bears the obligation, or whether the opposing party can stymie such compliance.10 See, e.g., Weems v. Citigroup, Inc., supra, 289 Conn. 790–91; Teresa T. v. Ragaglia, 272 Conn. 734, 744, 746, 865 A.2d 428 (2005); Katz v. Commissioner of Revenue Services, supra, 234 Conn. 617–19; Broadriver, Inc. v. Stamford, supra, 158 Conn. 529–31; Kindl v. Dept. of Social Services, 69 Conn. App. 563, 568, 795 A.2d 622 (2002). Each of these factors supports the defendant’s interpretation of the statute.
The first two factors are addressed to the statutory text. ‘‘A reliable guide in determining whether a statutory provision is . . . mandatory is whether the provision is accompanied by language that expressly invalidates any action taken after noncompliance with the provision.’’ Katz v. Commissioner of Revenue Services, supra, 234 Conn. 617. By contrast, where a statute by its terms imposes some other specific penalty, it is reasonable to assume that the legislature contemplated that there would be instances of noncompliance and did not intend to invalidate such actions. id., 618; Ghent v. Planning Commission, supra, 219 Conn. 515–16. ‘‘Furthermore, a requirement stated in affirmative terms unaccompanied by negative words . . . generally is not viewed as mandatory.’’ Teresa T. v. Ragaglia, supra, 272 Conn. 744.
In the present case, the statute does not provide any express penalty for a surety that fails to comply with the ninety day response requirement. This ‘‘lack of a penalty provision or invalidation of an action as a consequence for failure to comply with the statutory directive is a significant indication that the statute is directory.’’ Weems v. Citigroup, Inc., supra, 289 Conn. 791. That conclusion is bolstered here by the fact that
The next factor we consider ‘‘in determining whether a statute is mandatory or directory is whether the prescribed mode of action is the essence of the thing to be accomplished, or in other words, whether it relates to a matter of substance [as opposed to] a matter of convenience. . . . If it is a matter of substance, the statutory provision is [generally held to be] mandatory. If, however, the legislative provision is designed to secure order, system and dispatch in the proceedings, it is generally held to be directory . . . .’’ (Internal quotation marks omitted.) Metropolitan District Commission v. AFSCME, Council 4, Local 184, supra, 237 Conn. 120. In the present case, the defendant contends that the purpose of the ninety day response period is simply to create order and facilitate the claim process by providing a brief opportunity for a surety to evaluate and potentially resolve a claim prior to the initiation of litigation. The plaintiff, on the other hand, maintains that the ninety day response deadline is substantive, and hence mandatory, because, in its view, an essential purpose of the act is to guarantee that subcontractors who perform work on public construction projects in Connecticut receive prompt payment for their labor and materials. We agree with the defendant.
We acknowledge that where the legislature has imposed a statutory deadline we may assume that it intends for the action in question to be accomplished expeditiously. Nevertheless, the inclusion of a relatively brief deadline does not necessarily imply that expediency is an essential purpose of the statute. Indeed, in a number of cases, both this court and the Appellate Court have concluded that such statutory deadlines are directory where there is no express legislative guidance to the contrary and no indication that the legislature intended the deadline to be jurisdictional. Compare United Illuminating Co. v. New Haven, supra, 240 Conn. 463 (requirement that assessor provide notice of assessment within thirty days of hearing held directory), Katz v. Commissioner of Revenue Services, supra, 234 Conn. 617 (requirement that commissioner act on tax refund claim within ninety days held directory), Leo Fedus & Sons Construction Co. v. Zoning Board of Appeals, supra, 225 Conn. 446 (zoning board of appeals not subject to automatic approval doctrine on basis of its failure to hold public hearing within statutory time limit), Broadriver, Inc. v. Stamford, supra, 158 Conn. 529–30 (requirement that redevelopment
The legislative history of the act is instructive in this regard. Prior to 1987,
The 1987 amendments to the act did nothing to alter this legal remedy. See Public Acts 1987, No. 87-345 (P.A. 87-345). The amendments merely extended the prematurity period during which the parties may resolve the dispute among themselves prior to the commencement of litigation, and imposed a formal structure for this process: adding the requirement that the claimant provide the surety with notice of the claim and a detailed description of the project, and that the surety in turn notify the claimant of its response. Noth- ing in the legislative history suggests that the legislature viewed the new ninety day response requirement as an essential, substantive component of the act, as amended, or that it intended to impose thereby a judicial default provision.11 If anything, the 1987 amendments support the opposite conclusion, as the legislature at that time elected to impose various other penalty provisions designed to encourage parties to resolve their disputes promptly, without the need for litigation, but did not impose the penalty that the plaintiff seeks. In fact, in 2006, the legislature rejected proposed language that would have amended
We next consider whether holding a requirement to be mandatory would result in an unjust windfall for the party seeking to enforce the duty or, in the alternative, whether holding it to be directory would deprive that party of any legal recourse. Compare Weems v. Citigroup, Inc., supra, 289 Conn. 794 (treating rule requiring use of authorized forms for payroll deductions as mandatory would result in unwarranted windfall for employees), with Angelsea Productions, Inc. v. Commission on Human Rights & Opportunities, 236 Conn. 681, 692–93, 674 A.2d 1300 (1996) (time limits held mandatory where neither party could take further legal action until commission had made finding of reasonable cause or no reasonable cause); see also J. Evans, supra, 1 Legal Stud. 245 (purpose of mandatory/directory distinction is to avoid injustice and honor purposes of statute while not imposing unreasonably harsh consequences for trivial breaches). In the present case, we agree with the defendant and the amicus supporting the defendant’s position that this balancing weighs heavily in favor of treating the ninety day response period as directory.
At oral argument, the plaintiff conceded that when a surety first receives notice of a claim under a payment bond, the surety may have little, if any, familiarity with the specifics of the project, and in particular is likely to be ignorant as to the details and history of the dispute between its principal and the claimant. Moreover, the statute itself requires only that the claimant provide the surety with a ‘‘notice of claim [stating] with substantial accuracy the amount claimed and the name of the party for whom the work was performed or to whom the materials were supplied, and [providing] a detailed description of the bonded project for which the work or materials were provided.’’
Accordingly, upon receiving notice, the surety has just ninety days to educate itself as to the particulars of the project, investigate the claim, collect all relevant documentation, and then determine which portions of the claim to pay and which to deny. To accomplish these tasks, the surety is heavily dependent on the expeditious cooperation of its principal and the claimant, who will typically possess most, if not all, of the relevant information and documentation. Furthermore, if a surety were to prematurely deny a claim without having completed a thorough and adequate investigation, it could be found to have acted ‘‘without substantial basis in fact or law,’’ thereby incurring liability for the claimant’s attorney’s fees.
On the other side of the scale, we also perceive no prejudice to a claimant who, at the end of the ninety day response period,
Finally, our conclusion that the equities favor treating the response requirement in
At the same time, the claimant may be in a position to stymie the ability of the surety to investigate its claim expeditiously. In the present case, for instance, the defendant contends that the plaintiff repeatedly failed to provide full documentation of its allegations. That factual dispute is not before us, and, in any event it is not material to the purely legal questions the District Court has certified. As a general matter, however, a claimant subcontractor will often be the party best positioned to document the work and materials that it contributed to a project, as well as any losses it allegedly suffered as a result of the principal’s misconduct. Accordingly, to hold that a claimant is automatically entitled to full payment on all of its bond claims whenever a surety is unable to fully assess those claims within ninety days would create a strong incentive for claimants to withhold key information and otherwise fail to cooperate with the surety. We do not believe that the legislature intended to open the door to that sort of mischief. See Broadriver, Inc. v. Stamford, supra, 158 Conn. 530–31 (reasoning that treating ninety day deadline for statutory taking as mandatory would allow property owner to defeat taking through dilatory legal tactics).
Considering all of the relevant factors, then, including the text, legislative history, and purpose of the act, we conclude that the ninety day response requirement contained in
First, the plaintiff contends that it would be unfair to hold that a surety’s duty to respond to a claim under
The plaintiff’s argument also overlooks a number of relevant distinctions between the surety’s response requirement and the claimant’s duty to provide timely notice. The claimant, which has 180 days to serve notice of a claim, need only present its own version of the dispute in order to comply with the statutory deadline. It will presumably already be intimately familiar with the project, as well as the history and nature of its dispute with the principal, and will have access to many of the relevant documents. Indeed, the claimant may have begun to prepare and document a potential claim long before the statutory notice period ever begins to run. Under those circumstances, we are hard pressed to imagine why nearly one half of a year would not afford adequate time for a claimant, acting diligently, to prepare and present such a claim.
As we have described previously herein, the surety, by contrast, may have little familiarity with the details of the project and no knowledge of the dispute giving rise to the claim prior to receiving notice from the claimant. At that point, the surety has just ninety days—one half of the time allotted to the claimant—to educate itself about the project, obtain all relevant documents and accounts of the dispute from the claimant, the principal, and various third parties (all of whose timely assistance may not be forthcoming), and make a determination as to which portions of the claim, if any, are properly payable. However it decides, the surety must anticipate that it may ultimately be drawn into litigation involving one or more parties to the dispute. If it is later found to have denied a claim in bad faith, the surety also will be liable for the claimant’s attorney’s fees. Under those circumstances, it does not strike us as unreasonable to conclude that a surety, acting diligently, may not always be able to determine fully the merits of a claim, in good faith, within ninety days of notice. Accordingly, because the claimant and the surety are not similarly situated with regard to their respective statutory obligations, we do not believe it unreasonable or unfair that the legislature would have imposed a mandatory duty on the one and a directory duty on the other.
The plaintiff’s second argument is that because the act is a remedial statute; Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc., supra, 239 Conn. 716; it should be construed broadly in favor of protecting the interests of claimants. We have indicated that the act is to be liberally construed with regard to whether a particular class of subcontractors or suppliers is eligible for statutory protection. Okee Industries, Inc. v. National Grange Mutual Ins. Co., 225 Conn. 367, 373–74, 623 A.2d 483 (1993). We do not, however, construe remedial statutes so liberally as to provide windfalls for technical violations. Weems v. Citigroup, Inc., supra, 289 Conn. 794. The purpose of the act is to ensure that subcontractors and suppliers on state projects have an adequate remedy at law should the principal contractor fail to pay them moneys properly due. There is no indication that the legislature, in protecting the legitimate interest of these groups in being paid for their work, intended that they would automatically prevail on any claim, no matter how lacking in merit, simply because of a surety’s nonprejudicial delay in evaluating such claim.
The plaintiff’s third argument is that if the ninety day response requirement is deemed to be merely directory, there will be no penalty for noncompliance and sureties will have no incentive to satisfy their statutory obligations. We disagree.
For the foregoing reasons, we conclude that the answer to part (b) of the first certified question is: No. With regard to part (a) of the first certified question, we hold that, assuming, without deciding, that
Part (b) of the first certified question is answered in the negative. Guidance is
In this opinion the other justices concurred.
PALMER, J.
