ELECTRICAL CONTRACTORS, INC. v. 50 MORGAN HOSPITALITY GROUP, LLC, ET AL.
AC 44475
Appellate Court of Connecticut
April 12, 2022
Alvord, Cradle and Lavine, Js.
***************************************************
The “officially released” date that appears near the beginning of each opinion is the date the opinion will be published in the Connecticut Law Journal or the date it was released as a slip opinion. The operative date for the beginning of all time periods for filing postopinion motions and petitions for certification is the “officially released” date appearing in the opinion.
All opinions are subject to modification and technical correction prior to official publication in the Connecticut Reports and Connecticut Appellate Reports. In the event of discrepancies between the advance release version of an opinion and the latest version appearing in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports, the latest version is to be considered authoritative.
The syllabus and procedural history accompanying the opinion as it appears in the Connecticut Law Journal and bound volumes of official reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be reproduced and distributed without the express written permission of the Commission on Official Legal Publications, Judicial Branch, State of Connecticut.
***************************************************
Syllabus
The plaintiff subcontractor sought to recover damages from, among others, the defendant general contractor, G Co., for, inter alia, breach of contract and breach of the implied covenant of good faith and fair dealing. The plaintiff entered into a contract with G Co. in connection with a construction project for the renovation of a property owned by the named defendant, M Co. In its operative complaint, the plaintiff alleged, inter alia, that G Co. had failed to pay for materials and services that the plaintiff had provided. In its special defenses, G Co. asserted that language in the parties’ contract made clear that the G Co.‘s obligation to pay the plaintiff was dependent upon G Co. first receiving payment from M Co. Specifically, the contract stated that the plaintiff expressly agreed that payment by M Co. to G Co. was a “condition precedent” to G Co.‘s obligation to make partial or final payments to the plaintiff. G Co. filed a motion for summary judgment on the counts against it based on that contractual language, arguing that it had no duty to pay the plaintiff because it had not yet received payment from M Co. The trial court granted G Co.‘s motion and rendered summary judgment in favor of G Co., and the plaintiff appealed to this court.
- The trial court properly granted G Co.‘s motion for summary judgment as to the plaintiff‘s breach of contract claim: the clear and unambiguous language of the parties’ contract provided that G Co. was not obligated to pay the plaintiff until it received payment from M Co.; moreover, this court declined the plaintiff‘s invitation to find ambiguity in the payment provision and to interpret it to mean that G Co.‘s obligation to pay the plaintiff merely was postponed for a reasonable period of time; furthermore, the plaintiff did not cite any binding appellate authority to support its assertion that clauses such as the one at issue in the present case are disfavored in Connecticut and, more particularly, in the construction industry.
- The trial court properly granted G Co.‘s motion for summary judgment as to the plaintiff‘s claim for breach of the implied covenant of good faith and fair dealing: the plaintiff failed to allege or to provide any evidence to create a genuine issue of material fact that G Co. acted in bad faith in attempting to collect payment from M Co. or in failing to pay the plaintiff; moreover, this court‘s independent review of the record that was before the trial court when it rendered its summary judgment did not reveal a potential sinister motive or dishonest purpose on the part of G Co.
Argued January 3—officially released April 12, 2022
Procedural History
Action to recover damages for, inter alia, breach of contract, and for other relief, brought to the Superior Court in the judicial district of Hartford, where the court, Moukawsher, J., rendered summary judgment in favor of the defendant Greython Construction, LLC, and the plaintiff appealed to this court. Affirmed.
Edward R. Scofield, with whom, on the brief, were Heather Spaide and Joseph J. Cessario, for the appellee (defendant Greython Construction, LLC).
Opinion
LAVINE, J. The plaintiff, Electrical Contractors, Inc., appeals from the summary judgment rendered by the trial court in favor of the
The record reveals the following relevant undisputed facts and procedural history. Greython served as the general contractor for a project involving the renovation of a property owned by 50 Morgan. The plaintiff served as a subcontractor for Greython. On or about February 3, 2017, Greython entered into a contract with the plaintiff in which the plaintiff agreed to “furnish all labor, material, and equipment to perform all [electrical] work” for the project. The plaintiff provided Greython with requisitions seeking payment for materials furnished and services provided in connection with the project.
At the heart of this appeal is the meaning of the following language of the contract between the plaintiff and Greython. Article 2 of the contract provides that Greython will pay the plaintiff fixed sums of money in accordance with article 6 of the contract. Article 6 provides in relevant part: “[The plaintiff] shall submit to [Greython] a requisition, on forms provided by [Greython] . . . . Partial payments shall be due following receipt of payment [from] [50 Morgan] to [Greython] in the amount of 95 [percent] of the material in place for which payment has been made to [Greython] by [50 Morgan]. [The plaintiff] expressly agrees that payment by [50 Morgan] to [Greython] is a condition precedent to [Greython‘s] obligation to make partial or final payments to [the plaintiff] as provided in this paragraph. . . .” (Emphasis added.)
On January 31, 2018, the plaintiff commenced this action seeking payment for the costs of the materials it had furnished and the services it had provided in connection with the renovation project. On July 6, 2018, the plaintiff filed the amended complaint, which is the operative complaint. In the complaint, the plaintiff alleged that it performed its obligations under the subcontract by providing labor, materials, and equipment for the project. Greython, however, failed to pay the plaintiff for all amounts due for the work it had completed on the project. The plaintiff asserted that “the sum of $350,616.65, plus attorney‘s fees, accrued interest, and costs remains due and owing to [the plaintiff].”
The plaintiff alleged the following relevant counts against Greython:2 breach of contract for failing to pay the plaintiff the contract balance of $350,616.65 (count
On March 4, 2019, Greython filed an amended answer and special defenses to the operative complaint, in which it asserted two special defenses, both of which contended that the relevant language in article 6 made clear that Greython‘s obligation to pay the plaintiff was dependent upon Greython first receiving payment from 50 Morgan. On the same date, Greython filed a motion for summary judgment as to the second, third, fourth, and sixth counts of the operative complaint. Greython filed a memorandum of law in support of its motion, in which it argued that the language in article 6 of the contract was clear and unambiguous that it was not obligated to pay the plaintiff until it received payment from 50 Morgan. Because it had not yet received payment from 50 Morgan, Greython argued, “[it] ha[d] no duty to pay [the plaintiff] . . . .” On April 5, 2019, the plaintiff filed an objection to Greython‘s motion and an accompanying memorandum of law. The gist of the plaintiff‘s argument was that the payment provision in article 6 was ambiguous as to which party bore the risk of 50 Morgan‘s nonpayment. Thus, the plaintiff argued, this provision should be interpreted to mean that nonpayment by 50 Morgan “merely postpone[s] for a reasonable period of time” Greython‘s obligation to pay the plaintiff. On April 18, 2019, Greython filed a reply to the plaintiff‘s objection.
On April 24, 2019, the court heard oral argument on Greython‘s motion for summary judgment. On April 30, 2019, the court issued a memorandum of decision granting Greython‘s motion for summary judgment in its entirety as it pertained to the plaintiff. The court concluded that, pursuant to article 6 of the contract, Greython was not obligated to pay the plaintiff until 50 Morgan paid Greython. The court stated: “[The plaintiff] say[s] the court should read the language at issue [in article 6 of the contract] to mean that [Greython] will pay [the plaintiff] within a reasonable period of time even if the owner never pays [Greython].” The court noted that “courts have deviated from this view and read into some contracts the reasonable time language based upon the implications of labelling a provision . . . ‘pay-when-paid’ . . . or . . . [‘pay-if-paid‘].4 But
The court further stated: “The obvious import of the contract language in this case is that if [Greython] never gets paid then neither do its subcontractors. Because [50 Morgan‘s] payment is labelled a condition precedent—a thing that must happen first—the contract needed no additional words to make this consequence clear to a reader of ordinary intelligence.” (Emphasis in original.) The court concluded: “So [the plaintiff can-not]—under the present circumstances—win under the plain language of the contract.”
Regarding the count alleging breach of the covenant of good faith and fair dealing, the court stated: “[T]he [plaintiff] certainly express[es] dissatisfaction with Greython‘s efforts [to collect payment from 50 Morgan] but [does not] offer any evidence sufficient to create an issue of fact over whether Greython acted in bad faith. Instead, [although] questions have been raised about Greython‘s efforts, the [plaintiff has] cited no evidence that could possibly support a claim that Grey-thon has acted from some interested or sinister motive.”
On May 15, 2019, the plaintiff, pursuant to Practice Book §§ 11-11 and 11-12, filed a “motion for reargument/reconsideration and articulation” of the court‘s decision on Greython‘s motion for summary judgment. On May 20, 2019, the court denied that motion. This appeal followed.5 Additional facts and procedural history will be set forth as necessary.
We begin by setting forth the relevant standard of review, which applies to both of the plaintiff‘s claims. “This court‘s standard of review for a motion for summary judgment is well established. Practice Book § [17-49] provides that summary judgment shall be rendered forthwith if the pleadings, affidavits and any other proof submitted show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. In deciding a motion for summary judgment, the trial court must view the evidence in the light most favorable to the nonmoving party. . . . The party seeking summary judgment has the burden of showing the absence of any genuine issue [of] material facts which, under applicable principles of substantive law, entitle him to a judgment as a matter of law . . . and the party opposing such a motion must provide an evidentiary foundation to demonstrate the existence of a genuine issue of material fact. . . . [I]ssue-finding, rather than issue-determination, is the key to the procedure. . . . [T]he trial court does not sit as the trier of fact when ruling on a motion for summary judgment. . . . [Its] function is not to decide issues of material fact, but rather to determine whether any such issues exist. . . . Our review of the decision to grant a motion for summary judgment is plenary. . . . We therefore must decide
I
The plaintiff first claims that the court erred in granting Greython‘s motion for summary judgment based on language in the contract providing that payment by 50 Morgan was a “condition precedent” to Greython‘s obligation to make payments to the plaintiff. The plaintiff contends that “the overwhelming weight of authority in Connecticut holds that similar provisions in construction contracts do not excuse a general contractor‘s payment obligations to its subcontractors.” We disagree.
The following legal principles govern our interpretation of contracts. “A contract must be construed to effectuate the intent of the parties, which is determined from the language used interpreted in the light of the situation of the parties and the circumstances connected with the transaction. . . .
“[T]he intent of the parties is to be ascertained by a fair and reasonable construction of the written words and . . . the language used must be accorded its common, natural, and ordinary meaning and usage where it can be sensibly applied to the subject matter of the [writing]. . . . Where the language of the [writing] is clear and unambiguous, the [writing] is to be given effect according to its terms. A court will not torture words to import ambiguity where the ordinary meaning leaves no room for ambiguity . . . . Similarly, any ambiguity in a [written instrument] must emanate from the language used in the [writing] rather than from one party‘s subjective perception of the terms. . . . If a contract is unambiguous within its four corners, the determination of what the parties intended by their contractual commitments is a question of law.” (Citations omitted; internal quotation marks omitted.) Murtha v. Hartford, 303 Conn. 1, 7–8, 35 A.3d 177 (2011).
The plaintiff argues that the court incorrectly interpreted the payment provision in article 6 to mean that if Greython never receives payment from 50 Morgan, it is not obligated to pay its subcontractors. Specifically, the plaintiff argues that the court incorrectly interpreted the payment provision in article 6 as a “pay-if-paid” clause. The plaintiff states: ” ‘Pay-if-paid’ provisions in construction contracts seek to transfer the risk of owner default between the general contractor and subcontractor by contractually making the owner‘s payment to the general contractor a condition precedent to the general contractor‘s payment to the subcontractor.” Thus, unlike a “pay-when-paid” clause, if a general contractor never receives payment from an owner, it is not obligated to pay its subcontractors at all. The plaintiff asserts that the court instead should have interpreted the payment provision in article 6 as a “pay-when-paid” clause. A “pay-when-paid” clause merely postpones a general contractor‘s obligation to pay its subcontractors for a reasonable period of time, as opposed to creating a condition precedent to payment. See DeCarlo & Doll, Inc. v. Dilozir, 45 Conn. App. 633, 641 n.4, 698 A.2d 318 (1997) (DeCarlo). Thus, it claims, when a contract contains a “pay-when-paid” clause, a general contractor remains obligated to pay its subcontractors even if it never receives payment from the owner.
The plaintiff argues that clauses like the one in article 6 are “disfavored” in Connecticut and that “[t]he trial court‘s decision . . . represents the minority position not only in Connecticut, but also nationally.” The plaintiff reasons that because such clauses “are disfavored by courts, they will be enforced only where the contract language
The plaintiff, however, is unable to cite any binding appellate authority, and we are aware of none, that supports its assertion that clauses like the one in article 6 are disfavored in Connecticut generally, and particularly, as it argues, in the construction industry.7 In support of its argument that we should interpret the rele-vant language in article 6 as a “pay-when-paid” clause, the plaintiff relies primarily on DeCarlo & Doll, Inc. v. Dilozir, supra, 45 Conn. App. 633, which is distinguishable from the present case.8
Greython counters that the payment provision in article 6 is clear and unambiguous that its obligation to pay the plaintiff is expressly conditioned on it receiving payment from 50 Morgan. Greython notes that article 6 “contains no language or provisions [that] are focused on establish[ing] the time frame in which [the plaintiff] must or shall be paid by Greython.” We agree.
We decline the plaintiff‘s invitation to find ambiguity in the payment provision in article 6 when we see none. Rather, we rely on the plain language of the contract, which has just one possible reasonable interpretation. To reiterate, the relevant payment provision in article 6 of the contract states: “[The plaintiff] expressly agrees that payment by [50 Morgan] to [Greython] is a condition precedent to [Greython‘s] obligation to make partial or final payments to [the plaintiff] . . . .” (Emphasis added.) It is well settled that “[a] condition precedent is a fact or event which the parties intend must exist or take place before there is a right to performance. . . . A condition is distinguished from a promise in that it creates no right or duty in and of itself but is merely a limiting or modifying factor. . . . If the condition is not fulfilled, the right to enforce the contract does not come into existence. . . . Whether a provision in a contract is a condition the [nonfulfillment] of which excuses performance depends [on] the intent of the parties, to be ascertained from a fair and reasonable construction of the language used in the light of all the surrounding circumstances when they executed the contract.” (Internal quotation marks omitted.) Wells Fargo Bank, N.A. v. Lorson, 341 Conn. 430, 440, 267 A.3d 1 (2021).
The plaintiff has not cited any appellate case holding that the term “condition precedent”
“There is a strong public policy in Connecticut favoring freedom of contract . . . . This freedom includes the right to contract for the assumption of known or unknown hazards and risks that may arise as a consequence of the execution of the contract. Accordingly, in private disputes, a court must enforce the contract as drafted by the parties and may not relieve a contracting party from anticipated or actual difficulties undertaken pursuant to the contract, unless the contract is voidable on grounds such as mistake, fraud or unconscionability. . . . If a contract violates public policy, this would be a ground to not enforce the contract. . . . A contract . . . however, does not violate public policy just because the contract was made unwisely. . . . [C]ourts do not unmake bargains unwisely made. Absent other infirmities, bargains moved on calculated considerations, and whether provident or improvident, are entitled nevertheless to sanctions of the law. . . . Although parties might prefer to have the court decide the plain effect of their contract contrary to the agreement, it is not within its power to make a new and different agreement; contracts voluntarily and fairly made should be held valid and enforced in the courts.” (Emphasis added; internal quotation marks omitted.) Geysen v. Securitas Security Services USA, Inc., 322 Conn. 385, 392-93, 142 A.3d 227 (2016).
In any construction project, there is a risk that an owner will become insolvent and therefore be unable to pay its general contractor. The plaintiff in the present case is a sophisticated construction company.10 It could have added language to the contract specifying that Greython‘s duty to pay would be postponed only temporarily if Greython did not receive payment from 50 Morgan. Instead, the plaintiff now asks this court to write such clarifying language into the contract. We are not inclined to make a new and different agreement by adding terms to which the plaintiff and Greython did not agree. Furthermore, as the court noted in its memorandum of decision, our conclusion “[does not] change the [plaintiff‘s] right to be paid any time Greython gets paid in the future. It just means that not having been paid by [50 Morgan], Greython‘s failure to pay the [plaintiff] now [does not] breach the express contract language.”
We are not being asked whether the contractual language, in hindsight, appears to us to be fair or reasonable. We are simply being asked to determine if the language means what it says. We conclude that the plain language of article 6 of the contract is clear and unambiguous that Greython is not obligated to pay the plaintiff until it receives payment from 50 Morgan. Accordingly, we also conclude that the court properly granted Greython‘s motion for summary judgment as to the plaintiff‘s breach of contract claim.11
II
The plaintiff next claims that the court erred in granting Greython‘s motion for summary judgment because Greython failed to present any evidence demonstrating the absence of a genuine issue of material fact either that it was not the cause of 50 Morgan‘s failure to make payment or that it had made a substantive effort to collect payment. We will address this argument as it relates to the plaintiff‘s breach of the implied covenant of good faith and fair dealing claim against Greython.12 We conclude that the court did not err in granting Grey-thon‘s motion for summary judgment as to this claim.13
“[I]t is axiomatic that the . . . duty of good faith and fair dealing is a covenant implied into a contract or a contractual relationship. . . . In other words, every contract carries an implied duty requiring that neither party do anything that will injure the right of the other to receive the benefits of the agreement. . . . The covenant of good faith and fair dealing presupposes that the terms and purpose of the contract are agreed upon by the parties and that what is in dispute is a party‘s
“Bad faith in general implies . . . actual or constructive fraud, or a design to mislead or deceive another, or a neglect or refusal to fulfill some duty or some contractual obligation, not prompted by an honest mistake as to one‘s rights or duties, but by some interested or sinister motive. . . . Bad faith means more than mere negligence; it involves a dishonest purpose.” (Internal quotation marks omitted.) Geysen v. Securitas Security Services USA, Inc., supra, 322 Conn. 399-400. “The standard of proof applicable to claims of bad faith is clear and convincing evidence.” M.J. Daly & Sons, Inc. v. West Haven, 66 Conn. App. 41, 53, 783 A.2d 1138, cert. denied, 258 Conn. 944, 786 A.2d 430 (2001).
The following additional procedural history is relevant to this claim. In the operative complaint, the plaintiff stated that the contract “contains an implied covenant of good faith and fair dealing requiring that neither party do anything that will injure the right of the other to receive the benefits of the agreement.” The plaintiff alleged that Greython breached its duty of good faith and fair dealing by (1) “failing to make payment of the sums due to [the plaintiff] that are not subject to a good faith dispute,” and (2) “failing to provide notice or response to [the plaintiff] in good faith as to the specific, justifiable reasons for Greython‘s failure to make payment to [the plaintiff].” The plaintiff further alleged: “These acts and omissions by Greython were undertaken in bad faith, solely for the purpose of avoiding Greython‘s express and implied obligations under the parties’ contract.” We reasonably interpret the plaintiff‘s claim before this court as arguing that Greython breached the implied covenant of good faith and fair dealing by not making a “substantive effort” to collect payment from 50 Morgan, thereby injuring the plaintiff‘s right to receive the benefits of its agreement with Greython.14
Viewing the record in the light most favorable to the plaintiff as the nonmoving party, there is no evidence, let alone evidence sufficient to create a genuine issue of material fact, that Greython acted in bad faith when attempting to collect payment from 50 Morgan. Our independent review of the evidence that was before the court when it rendered its summary judgment does not reveal a potential sinister motive or dishonest purpose on the part of Greython.15
The judgment is affirmed.
In this opinion the other judges concurred.
Notes
Several Superior Court cases have cited DeCarlo when interpreting contract clauses that, like the clause in the present case, expressly and unambiguously condition an obligee‘s right to payment on an obligor‘s receipt of payment from a third party. Some of those cases refer to these types of clauses as “pay-if-paid” clauses. Our trial courts have reached different conclusions as to the interpretation of this type of clause. See, e.g., R & L Acoustics v. Liberty Mutual Ins. Co., Superior Court, judicial district of Fairfield, Docket No. CV-00-0380506-S (September 27, 2001) (clause not enforceable as condition precedent even though it stated “[t]he Contractor shall have no liability or responsibility for any amount due or claimed to be due to Subcontractor except to the extent Contractor actually receives funds from Owner specifically designated for disbursement to the Subcontractor as receipt of such funds from the Owner are specifically made a condition precedent to the Contractor‘s obligation to make payments to Subcontractor hereunder” (emphasis added; internal quotation marks omitted)); Lindade Construction, Inc. v. Continental Casualty Co., Superior Court, judicial district of Waterbury, Docket No. CV-05-008767-S (February 25, 2009) (47 Conn. L. Rptr. 323) (“pay-if-paid” clause was enforceable and not void as against public policy given strong public policy in Connecticut favoring freedom of contract). In the present case, the plaintiff does not cite any Connecticut appellate cases, and we are aware of none, that address the enforceability of “pay-if-paid” clauses.
Our independent review of the record before the court at the time it granted the motion for summary judgment indicates that the only evidence that Greython presented about its good faith efforts to collect payment from 50 Morgan came from a portion of the affidavit of Kyle Klewin, Greython‘s president, which states that Greython submitted requisitions seeking payments for the materials and services provided both by Greython and its subcontractors. At the hearing on Greython‘s motion for summary judgment, counsel for Greython detailed its efforts to collect payment from 50 Morgan. In its memorandum of decision, the court appeared to rely in part on those statements by counsel, which are not evidence. Accordingly, the court apparently overstated the scant evidence in the record about Greython‘s efforts to collect payment from 50 Morgan. As we discuss in more detail later in this opinion, however, the plaintiff did not submit evidence of bad faith on the part of Greython. Thus, there was a lack of evidence sufficient to create a genuine issue of material fact as to Greython‘s bad faith. In the absence of such evidence, this mischaracterization in the court‘s memorandum of decision does not affect the outcome of this case.
The plaintiff did not attempt to show that Greython‘s statements about the closing were made in bad faith. It did not allege, for example, that those statements were false or misleading. Although the correspondences about the closing took place after the plaintiff brought its action against Greython, they nevertheless provide evidence of Greython‘s effort to collect payment from 50 Morgan.
