History
  • No items yet
midpage
211 Conn.App. 724
Conn. App. Ct.
2022
Read the full case

Background

  • Electrical Contractors, Inc. (subcontractor) contracted with Greython Construction, LLC (general contractor) to perform electrical work on a 50 Morgan Hospitality Group, LLC (owner) renovation project.
  • Article 6 of the subcontract stated: payment by the owner to Greython is a “condition precedent” to Greython’s obligation to make partial or final payments to the subcontractor.
  • Subcontractor claimed Greython failed to pay $350,616.65 for work performed and sued for breach of contract and breach of the implied covenant of good faith and fair dealing, among other counts.
  • Greython moved for summary judgment, arguing the contract’s unambiguous condition-precedent language relieved it of any payment obligation until Greython was paid by the owner.
  • The trial court granted summary judgment for Greython on breach of contract and implied covenant claims; the court found the clause clear and that the subcontractor produced no evidence of Greython’s bad faith in collecting from the owner.
  • On appeal, the Connecticut Appellate Court affirmed, holding the contract language unambiguous (a pay‑if‑paid condition precedent) and that the record contained no evidence of dishonesty or bad faith by Greython.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the subcontract’s payment clause is a condition precedent (i.e., pay‑if‑paid) or only postpones payment for a reasonable time (pay‑when‑paid) The clause is ambiguous and should be read as pay‑when‑paid; Connecticut disfavors clauses that transfer owner nonpayment risk to subcontractors Clause expressly labels owner payment a “condition precedent,” so it unambiguously makes Greython’s duty to pay contingent on owner payment Clauses are enforced as written here; article 6 unambiguously creates a condition precedent (pay‑if‑paid), so Greython had no contractual duty to pay until it was paid by the owner
Whether there was a genuine factual dispute that Greython acted in bad faith (breach of implied covenant) Greython failed to demonstrate it made substantive collection efforts and may have caused or contributed to the owner’s nonpayment; omission shows bad faith Subcontractor produced no evidence of dishonest purpose or that Greython acted from a sinister motive; Greython submitted requisitions and communications supporting collection efforts No genuine issue of material fact as to bad faith; subcontractor offered no clear‑and‑convincing evidence of dishonest purpose, so summary judgment for Greython was proper

Key Cases Cited

  • Murtha v. Hartford, 303 Conn. 1 (Conn. 2011) (principles of contract interpretation; clear, unambiguous language governs intent)
  • DeCarlo & Doll, Inc. v. Dilozir, 45 Conn. App. 633 (Conn. App. 1997) (distinguishes pay‑when‑paid language; clause at issue there was not a condition precedent)
  • Wells Fargo Bank, N.A. v. Lorson, 341 Conn. 430 (Conn. 2021) (definition and effect of a condition precedent)
  • Geysen v. Securitas Security Services USA, Inc., 322 Conn. 385 (Conn. 2016) (freedom of contract and definition of bad faith requiring dishonest purpose)
  • Renaissance Management Co. v. Connecticut Housing Finance Authority, 281 Conn. 227 (Conn. 2007) (implied covenant of good faith and fair dealing applies to contractual discretion)
  • Buehler v. Newtown, 206 Conn. App. 472 (Conn. App. 2021) (summary judgment standard and appellate review)
Read the full case

Case Details

Case Name: Electrical Contractors, Inc. v. 50 Morgan Hospitality Group, LLC
Court Name: Connecticut Appellate Court
Date Published: Apr 12, 2022
Citations: 211 Conn.App. 724; 273 A.3d 726; AC44475
Docket Number: AC44475
Court Abbreviation: Conn. App. Ct.
Log In
    Electrical Contractors, Inc. v. 50 Morgan Hospitality Group, LLC, 211 Conn.App. 724