EAST WEST BANK, Plaintiff and Respondent, v. RIO SCHOOL DISTRICT, Defendant and Appellant.
No. B238618
Second Dist., Div. Six.
Apr. 1, 2015.
742
COUNSEL
Baute Crochetiere & Gilford, David P. Crochetiere, Andrew Michael Gilford; Negele & Associates, James R. Negele and Jonathan R. Hickman for Defendant and Appellant.
Kronick, Moskovitz, Tiedemann & Girard, Christian M. Keiner, Chelsea R. Olson and James P. Wiezel for Education Legal Alliance of the California Schools Board Association as Amicus Curiae on behalf of Defendant and Appellant.
Raisin & Kavcioglu, Bradley A. Raisin, Armenak Kavcioglu, Aren Kavcioglu; Cox, Castle & Nicholson, Kenneth B. Bley, Randy P. Orlik and Susan S. Davis for Plaintiff and Respondent.
OPINION
GILBERT, P. J.-
We disagree with Martin Brothers Construction, Inc. v. Thompson Pacific Construction, Inc. (2009) 179 Cal.App.4th 1401 [102 Cal.Rptr.3d 419] (Martin Brothers), which holds otherwise. We also conclude the doctrine of unclean hands does not apply to
This case arises from a contract for the construction of a school. After the school was completed, the school district and its general contractor engaged in a decade-long legal battle. The result was a judgment for the contractor FTR International, Inc. (FTR), against the Rio School District (District) exceeding $9 million. District appeals.
We conclude the trial court properly assessed penalties against District because it did not timely release retained funds required by
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
We also conclude [[/]]* the trial court erred in awarding fees for work not solely related to FTR‘s cause of action pursuant to
We reverse and remand with instructions in the instances where the trial court erred and affirm in all other respects.
FACTS
FTR has constructed buildings for public entities, including schools, courthouses and libraries for 15 years. In 1999, FTR submitted the winning bid in the amount of $7.345 million to construct a school for District.2
During construction, FTR submitted approximately 150 proposed change orders (PCO). FTR claimed some of the PCOs were necessary because the plans provided by District were inadequate or misleading. District denied most of the PCOs on the grounds that the work was covered under the basic contract, the amounts claimed were excessive or that a PCO was not timely
Pursuant to the contract, District retained 10 percent of each progress payment. At the completion of the work, District held a reserve of $676,436.49. That amount, however, was subject to stop notices filed by FTR‘s subcontractors. The last of the stop notices was released on September 28, 2004.
District refused to pay the balance due under the contract, refused to pay any but a small portion of the amounts claimed by FTR in its PCOs, refused to release any of the retention and refused to compensate FTR for damages allegedly caused by delay and disruption. FTR sued District to recover damages for breach of contract, statutory penalties under
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
After a 243-day court trial, the trial court found in favor of FTR. It awarded $9,356,124.81 to FTR, which includes damages for the balance due under the contract, extra work performed by FTR, delay and disruption caused by District, statutory penalties pursuant to
DISCUSSION
Section 7107 Penalties
District contends the trial court erred in awarding penalties under
Subdivision (f) of
Here the trial court found the project was completed on August 7, 2001. The retention was required to be released within 60 days, on October 5, 2001. Stop notices, however, prohibited District from releasing the funds on that date. The stop notices have since been released, but District has refused to release any funds. District still had the entire retention amount of $676,436 at the time of the statement of decision, over 10 years after the project was completed. The court found District had no justification for retaining the funds after the stop notices were released. It assessed a 2 percent per month penalty from the date the stop notices were released for a total penalty of $1,537,404.96.
The purpose of a retention is to provide security against potential mechanics liens and to insure the contractor will complete the work properly and repair defects. (Yassin v. Solis (2010) 184 Cal.App.4th 524, 534 [108 Cal.Rptr.3d 854].) The retained funds must be paid to the contractor when the security is no longer required. (Ibid.)
Here, after the stop notices were cleared, District points to nothing for which security was required. The dispute on which District relies, FTR‘s claim against District, does not require District to retain FTR‘s funds as security. But District argues there is no language in
District relies on Martin Brothers, supra, 179 Cal.App.4th 1401, decided after the evidence in this case was heard. In Martin Brothers, a general contractor on a public school project retained a portion of the progress payments due a subcontractor. After the subcontractor completed its work, the subcontractor claimed additional money was owed it due to change orders. The subcontractor sought a 2 percent per month penalty against the contractor pursuant to
We decline to follow Martin Brothers. The purpose of
District points to a recodification of
But the Law Revision Commission Comments to
District argues that because it properly withheld the retention funds under stop notices past the 60-day statutory period, it has complied with the statute and cannot be penalized. But the purpose of
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Attorney Fees
The trial court awarded FTR $3.85 million attorney fees. The contract did not contain an applicable attorney fee clause. The only basis for the award was
The trial court found that the $3.85 million award was justified because District raised an “unclean hands” defense to FTR‘s action, including its action under
FTR‘s counsel did not submit itemized time records, estimates of time spent on discrete tasks, billings submitted to the client or records of payments made for work done. Instead, counsel submitted estimates of time spent prepared years after the work was performed.
Questioning counsel‘s estimates, the trial court undertook its own analysis of the evidence and the record. Some analysis involved events that occurred prior to the time the case was assigned to the court. The court concluded the reasonable lodestar award of fees is $3.5 million. In consideration of the factors stated in Serrano v. Priest (1977) 20 Cal.3d 25, 49 [141 Cal.Rptr. 315, 569 P.2d 1303], the court added 10 percent to the lodestar, for a total award of $3.85 million.
District argues that without time sheets, billing entries or reliable testimony, the court had no foundation for determining how much time counsel spent over 10 years of litigation. But here the trial court made its own determination of fees based on its analysis and the record. A trial court may award fees solely on the basis of the experience and knowledge of the trial judge. (Fed-Mart Corp. v. Pell Enterprises, Inc. (1980) 111 Cal.App.3d 215, 227 [168 Cal.Rptr. 525].) That some proceedings occurred prior to the assignment of the action to the trial court, does not prevent the court from estimating fees based on the record.
District argues the trial court failed to apportion the fees between those spent on FTR‘s cause of action pursuant to
The linchpin in the trial court‘s finding of inextricably intertwined issues is District‘s unclean hands defense. FTR argued that it was required to prevail on its other causes of action in order to defeat the unclean hands defense to its
The trial court had previously found, however, that the unclean hands doctrine did not apply to any of FTR‘s causes of action. The court stated: “The defense of unclean hands arises from the maxim: ‘He who comes into Equity must come with clean hands.’ Blain v. Doctor‘s Co. (1990) 222 Cal.App.3d 1048 [272 Cal.Rptr. 250]. Whether the doctrine of unclean hands applies is a question of fact. CrossTalk Productions, Inc. v. Jacobson (1998) 65 Cal.App.4th 631 [76 Cal.Rptr.2d 615]. The Blain court enunciated a three-pronged test to determine the effect to be given to the plaintiff‘s unclean hands conduct. Whether the particular misconduct is a bar to the alleged claim for relief depends on (1) analogous case law, (2) the nature of the misconduct, and (3) the relationship of the misconduct to the claimed injuries. Blain, supra, ... at p. 1060; accord, Unilogic, Inc. v. Burroughs Corp. (1992) 10 Cal.App.4th 612, 618-621 [12 Cal.Rptr.2d 741]; CrossTalk Productions, supra, [at pp. 641-643]. FTR contends, and the District concedes, that there is no analogous case law supporting the application of the unclean hands defense to the facts present here. The Court therefore finds that the District failed to meet the first prong stated in Blain. That finding alone is sufficient to warrant the denial of the defense. CrossTalk Productions, Inc., supra, [at pp. 641-642] (defense rejected, court noting that ‘[d]efendant has cited no authority finding unclean hands generally to be a defense to [similar] claims‘); In re Brandie W. (1984) 157 Cal.App.3d 110 [203 Cal.Rptr. 537] (defense rejected because ‘neither party has cited any case from this state applying the clean hands doctrine to facts analogous to those before us. Our own research has likewise been unfruitful.‘).”
FTR argues that because the application of the doctrine of unclean hands is a question of fact, the case had to be tried in order to determine the defense did not apply. It claims that rarely can an unclean hands defense be resolved on a legal basis. (Citing CrossTalk Productions, Inc. v. Jacobson, supra, 65 Cal.App.4th at p. 641.) It points out that the trial court found there is no analogous case law supporting the application of the unclean hands defense “to the facts presented here.”
Although the application of the unclean hands defense is usually a question of fact, under appropriate circumstances it may be determined as a matter of law. (See, e.g., Mendoza v. Ruesga (2008) 169 Cal.App.4th 270, 279 [86 Cal.Rptr.3d 610] [holding as a matter of law unclean hands defense does not apply].) Here because there is no analogous case applying the doctrine of unclean hands as a defense to an action pursuant to
Not only is there no analogous case applying the doctrine to an action pursuant to
In Mendoza v. Ruesga, supra, 169 Cal.App.4th 270, a group of immigrants sued an immigration consultant alleging violations of the
Here
It may be that as to other causes of action in this case, the matter had to be tried to determine whether unclean hands applied. But no factual findings were necessary to determine that the doctrine of unclean hands does not apply to an action under
It is beside the point that District urged the trial court to wait until the end of trial to rule on its unclean hands defense. The question is not when the
CONCLUSION
The matter is reversed and remanded to the trial court with instructions to limit the award of attorney fees to fees incurred solely in relation to FTR‘s cause of action under
In all other respects, the judgment is affirmed.
Each party is to bear its own costs.
Yegan, J., and Perren, J., concurred.
