History
  • No items yet
midpage
East West Bank v. Rio School District
235 Cal. App. 4th 742
| Cal. Ct. App. | 2015
Read the full case

Background

  • FTR International (contractor) built a school for Rio School District (District) under a contract retaining 10% of progress payments; District held $676,436.49 retention after completion and stop notices delayed release until September 28, 2004.
  • After completion (notice of completion Aug. 7, 2001), District refused to pay most of ~150 proposed change orders (PCOs), refused to release retention after stop notices cleared, and denied delay/disruption claims.
  • FTR sued for breach, unpaid contract balance, extra work, delay/disruption, §7107 penalties (2%/month on withheld retention in lieu of interest), attorney fees and prejudgment interest; District counterclaimed under California False Claims Act (FCA).
  • After a 243‑day bench trial, the court awarded FTR >$9.3 million (damages, §7107 penalties, fees, interest); District appealed.
  • The Court of Appeal affirmed most rulings but (1) rejected Martin Brothers' broad reading of §7107, holding a price dispute alone does not justify withholding retention once retention’s security purpose ends; (2) held unclean hands is not a defense to a §7107 claim as a matter of law; (3) found error in requiring prejudice to enforce contract time‑limits for claims and in awarding attorney fees not limited to §7107‑related work.

Issues

Issue Plaintiff's Argument (FTR) Defendant's Argument (District) Held
Whether a dispute over contract price/PCOs permits a public entity to withhold retention under §7107 Retention must be released once its security purpose ends; PCO dispute is not a valid ground to keep retention after stop notices cleared Any bona fide dispute between public entity and contractor justifies withholding up to 150% of disputed amount (relying on Martin Brothers) Rejected Martin Brothers; price dispute alone does not justify continued withholding once security purpose (liens/defects) has ended; §7107 penalty applies when retention improperly withheld
Applicability of unclean hands defense to a §7107 claim N/A for plaintiff — FTR argued defense inapplicable; contended unclean hands cannot defeat statutory protections District invoked unclean hands to defeat §7107 relief and to require broader defenses, arguing equitable bar Court held as a matter of law unclean hands does not apply to §7107 claims because the statute protects contractors; unclean hands cannot bar recovery under §7107
Enforceability of contract clauses imposing short notice/forfeiture periods for claims (Articles 10 and 37D) FTR: contract claims procedures applied but some claims excused (breach prevented compliance); time rules should not be read to require showing of prejudice District: strict enforcement; many awarded claims were untimely under Articles 10/37D, so forfeited Court held forfeiture clauses are enforceable under Gov. Code §930.2; trial court erred by adding prejudice requirement; Article 37D governs extra‑work PCOs; some claims may be untimely and must be reconsidered on remand
Award and apportionment of attorney fees under §7107 FTR: entitled to fees incurred in securing release of retention; no apportionment required where issues intertwined District: award ($3.85M) was excessive, not limited to §7107 work, and unclean hands defense made many issues intertwined so fees should be apportioned Court held fee award must be limited to fees incurred solely for the §7107 claim (issues not "inextricably intertwined"); remanded to apportion fees accordingly; trial court erred in relying on unclean hands to justify broad fee award

Key Cases Cited

  • Martin Brothers Constr., Inc. v. Thompson Pacific Constr., Inc., 179 Cal.App.4th 1401 (Cal. Ct. App.) (held any good‑faith dispute between GC and subcontractor can justify withholding retention)
  • FEI Enterprises, Inc. v. Yoon, 194 Cal.App.4th 790 (Cal. Ct. App.) (statutory purpose of prompt release of retention funds)
  • S & S Cummins Corp. v. West Bay Builders, Inc., 159 Cal.App.4th 765 (Cal. Ct. App.) (remedial nature of retention statute; liberal construction)
  • Fassberg Constr. Co. v. Housing Authority of City of Los Angeles, 152 Cal.App.4th 720 (Cal. Ct. App.) (submission of PCOs alone does not automatically create an FCA claim)
  • Thompson Pacific Constr., Inc. v. City of Sunnyvale, 155 Cal.App.4th 525 (Cal. Ct. App.) (apportionment not required when work is common to fee‑eligible and non‑fee causes only if truly inseparable)
  • Mendoza v. Ruesga, 169 Cal.App.4th 270 (Cal. Ct. App.) (unclean hands inapplicable as matter of law to statutory causes intended to protect a class)
Read the full case

Case Details

Case Name: East West Bank v. Rio School District
Court Name: California Court of Appeal
Date Published: Apr 1, 2015
Citation: 235 Cal. App. 4th 742
Docket Number: B238618A
Court Abbreviation: Cal. Ct. App.