INTRODUCTION
Plaintiff and appellant Diaa Yassin (Yassin), a contractor, was hired by defendants and respondents Vinicio Solis and Sonia Solis (collectively Solises) to do improvement work on the Solises’ home. Yassin sued for money he claimed was owed him, and the Solises cross-complained, inter alia, for breach of contract in connection with the work performed. The trial court awarded Yassin nothing and the Solises $50,000 in damages and, pursuant to Civil Code section 3260, subdivision (g) (penalties and attorney fees for wrongfully withheld retention payments in certain construction contracts), attorney fees of $36,205.14. 1 On appeal, Yassin contends, inter alia, that the claim for the last payment due under the contract upon completion of the work and issuance of the certificate of occupancy did not involve a retention under section 3260, and therefore the trial court erred in awarding attorney fees under that section. In the published portion of this opinion we hold that although a party does not have to plead that it is seeking attorney fees in order to recover those fees, the last contractual payment due Yassin was not a retention under section 3260, and therefore the Solises, as the prevailing parties in the Solises’ claim to recover that amount, were not entitled to attorney fees under section 3260, subdivision (g). We also hold that section 3260.1 does not authorize the award of attorney fees. In the unpublished portion of the opinion, we hold that there was substantial evidence of damage. Accordingly, we affirm the award of damages, but reverse the attorney fees award.
BACKGROUND
Yassin, a licensed contractor, contracted with the Solises to construct an addition on the Solises’ home and to do additional work on the home for a total of $75,000. The contract provided as follows: “The contractor shall furnish to the owner all of the labor and material required for the construction of a new addition . . . [according to building department approved plans and specifications .... The owner shall pay to the contractor for furnishing the labor and materials and for the construction of this residence the sum of $75,000, paid as follows: $7,500 downpayment on the signing of this Agreement; $22,500 Foundation placement; $22,500 Rough Framing Inspection; $15,000 Final Inspection; $7,500 Certificate of Occupancy. 3. The final payment shall be made upon completion of the work and before occupancy. . . .” There were some change orders. After the city inspector signed a
Yassin sued the Solises for the $30,900 he claimed was owed him. The Solises cross-complained for damages. Yassin submitted evidence attributing the alleged construction defects to preexisting conditions on the property. The Solises contended that it would cost $63,728.10 to repair the damage caused by Yassin.
The trial court awarded Yassin nothing on his claim and awarded the Solises on their cross-complaint $50,000 in damages. After a posttrial motion based on sections 3260 and 3260.1, the trial court awarded the Solises $36,205.14 in attorney fees under section 3260, subdivision (g) on the theory that the Solises prevailed on Yassin’s claim for $7,500 due and payable upon completion of the work and issuance of a certificate of occupancy, 2 which payment the trial court deemed to be a retention under section 3260.
Yassin asserts on appeal that there was a lack of substantial evidence to support the Solises’ claim for damages; that sections 3260 and 3260.1 are inapplicable to this action because there was no withholding of progress payments or retention of monies due under the contract; that the failure of any of the parties to invoke in their pleadings sections 3260 and 3260.1 precludes an award of attorney fees under those sections; and that any liability under section 3260.1 is barred by the one-year statute of limitations. (Code Civ. Proc., § 340, subd. (a).)
DISCUSSION
A. Standard of Review
We review a contention that evidence does not support a damage award under the substantial evidence standard of review. (See
Major v. Western
B. Substantial Evidence of Damage *
C. Attorney Fees
1. Applicable Facts
There was no attorney fees clause in the contract. The Solises moved for attorney fees under sections 3260 and 3260.1. The trial court awarded the Solises $36,205.14 in attorney fees pursuant to section 3260, subdivision (g), reducing the amount requested.
Section 3260.1, subdivision (b) provides, “Except as otherwise agreed in writing, the owner shall pay to the contractor, within 30 days following receipt of a demand for payment in accordance with the contract, any progress payment due thereunder as to which there is no good faith dispute between the parties. In the event of a dispute between the owner and the contractor, the owner may withhold from the progress payment an amount not to exceed 150 percent of the disputed amount. If any amount is wrongfully withheld in violation of this subdivision, the contractor shall be entitled to the penalty specified in subdivision (g) of Section 3260.” Section 3260, in relevant part, provides: “(b) The retention proceeds withheld from any payment by the owner from the original contractor, or by the original contractor from any subcontractor, shall be subject to this section, [f] (c) Within 45 days after the date of completion, the retention withheld by the owner shall be released. ... [f] ... [f] (g) In the event that retention payments are not made within the time periods required by this section, the owner or original contractor withholding the unpaid amounts shall be subject to a charge of 2 percent per month on the improperly withheld amount, in lieu of any interest otherwise due. Additionally, in any action for the collection of funds wrongfully withheld, the prevailing party shall be entitled to his or her attorney’s fees and costs.”
The Solises paid Yassin a downpayment and various progress payments. The Solises refused to pay Yassin the $15,000 required after the “Final
The trial court concluded that Yassin sought to recover retention proceeds held by the Solises—specifically the $7,500 due upon the issuance of certificate of occupancy—and therefore, as the “prevailing parties” on that claim, the Solises were entitled to an award of attorney fees under section 3260, subdivision (g). The trial court stated that section 3260.1 did not provide for attorney fees.
2. Rules of Interpretation
“Our task in interpreting these statutes is ‘to ascertain and effectuate legislative intent.’ [Citation.]”
(Bernard v. Foley
(2006)
“To the extent this examination of the statutory language leaves uncertainty, it is appropriate to consider ‘the consequences that will flow from a particular interpretation. [Citation.]’ [Citation.] Where more than one statutory construction is arguably possible, our ‘policy has long been to favor the construction that leads to the more reasonable result. [Citation.]’ [Citation.] This policy derives largely from the presumption that the Legislature intends reasonable results consistent with its apparent purpose. [Citation.] Thus, our task is to select the construction that comports most closely with the Legislature’s apparent intent, with a view to promoting rather than defeating the statutes’ general purpose, and to avoid a construction that would lead to unreasonable, impractical, or arbitrary results. [Citations.]”
(Copley Press, Inc. v. Superior Court
(2006)
3. Contentions of the Parties
Even though the parties disagree on what was meant by “Final Inspection,” the parties agree that after that inspection, Yassin was required to do more work and that the Solises terminated Yassin from the job before he had completed it. Accordingly, the $15,000 final inspection payment claimed by Yassin was payable under the contract before completion of the work. The final payment due under the contract was the $7,500 to be paid upon completion of the work and issuance of the certificate of occupancy.
Yassin sued for the unpaid portion of the contract price, plus work on change orders and extras. The trial court concluded that at least the final $7,500 payment required under the contract was a retention amount covered by section 3260. The trial court permitted the Solises to recover their attorney fees to defend against the amount claimed that constituted what the trial court considered a retention—i.e., the $7,500 payment due upon the issuance of the certificate of occupancy. Yassin asserts on appeal that neither he nor the Solises ever asserted in the trial court that the claim was brought pursuant to
4. No Pleading Requirement or Applicable Period of Limitations
There is no requirement that a party plead that it is seeking attorney fees, and there is no requirement that the ground for a fee award be specified in the pleadings. (Pearl, Cal. Attorney Fee Awards (Cont.Ed.Bar 2d ed. 2008) § 3.1, p. 68; 7 Witkin, Cal. Procedure (5th ed. 2008) Judgment, § 295, p. 895; but cf.
Alpha Mechanical, Heating & Air Conditioning, Inc. v. Travelers Casualty & Surety Co. of America
(2005)
5. Application of Statute
The last payment of the installment payments was to be made after the completion of the work and issuance of a certificate of occupancy. That last payment did not constitute “retention proceeds withheld from any payment by the owner from the original contractor . . . .” (§ 3260, subd. (b).) By its terms, that statute refers to retention proceeds as being funds withheld from a payment, not the payment itself. Retention amounts are a form of security generally retained by the owner from prior payments due for work previously performed.
If a statute is ambiguous, extrinsic aids in interpretation include statutes in pari materia, i.e., relating to the same matter or subject. (See
Altaville Drug Store, Inc.
v.
Employment Development Department
(1988)
Thus, the usage of the term “retention” in construction contracts does not contemplate that the final payment constitutes a retention. The final payment for work done does not involve an amount “retained” from any
The trial court stated that since the final payment was not due until a certificate of occupancy was issued, the final payment is a retention because the amount was to be withheld until the work was approved. This position is tenable, but does not, in our view, comport with the usage and purpose of the term “retention.” The contract contemplated that the work would not be considered completed until a certificate of occupancy was issued. The final payment under the contract was to be for completed work. Holding the final payment until the lien period has expired is a different matter, for there, the retention bears no relationship to the progress of the work. Miller and Starr make this distinction when referring to installment payments. They do not label the payment due upon the recordation of the notice of completion as a retention but only refer to the amount held until the completion of the lien period as a “retention.” (10 Miller & Starr, Cal. Real Estate, supra, § 27:50, pp. 135-136.)
In Murray’s Iron Works, Inc. v. Boyce, supra, 158 Cal.App.4th at pages 1298-1299, the court said that the downpayment and final payment are not progress payments under section 3260.1, which provides for a penalty for amounts wrongfully withheld from progress payments. But that does not mean that a final payment due at the conclusion of performance under an installment contract is a retention. It is simply the last installment. If the last installment payment is considered a retention just because it is the last payment for the work already completed, then every progress payment for work completed would be a retention. This, of course, makes no sense.
To interpret section 3260 as meaning the final progress payment is a retention would not carry out the goals of the statute and would lead to questionable results. The purpose of the statute is to insure prompt payment to contractors and subcontractors of amounts withheld, which amounts are in reality a form of security. When the owner, pursuant to the contract, withholds amounts from progress payments as security, the failure to pay timely those amounts, if not justified, would result in a penalty and an award of attorney fees. As section 3260.1 imposes a penalty for the wrongful withholding of a progress payment, it makes sense that section 3260 imposes a penalty on the wrongful withholding of amounts retained from the progress payments—i.e., the retention. The remedy for the failure to pay a last installment payment upon completion of the services is simply damages for a breach of contract.
DISPOSITION
The judgment in favor of the Solises on liability and damages is affirmed, and the award of attorney fees is reversed. No costs are awarded.
Armstrong, Acting P. J., and Kriegler, J., concurred.
Notes
All further statutory references are to the Civil Code unless otherwise indicated.
“The certificate of occupancy, which is issued only after completion of a structure and its inspection by a building inspector, evidences that what has been accomplished is in compliance with the building code, and with the nonuse provisions of the [zoning] ordinance.” (4 Ziegler, Rathkopf’s The Law of Zoning and Planning (4th ed. 2010) § 69:24, p. 69-73.)
See footnote, ante, page 524.
See
Murray’s Iron Works, Inc. v. Boyce
(2008)
