COMMONWEALTH of Virginia and Commonwealth of Virginia, Department of Transportation v. AMEC CIVIL, LLC.
Record Nos. 2061-08-2, 1961-08-2
Court of Appeals of Virginia, Richmond
June 16, 2009
677 S.E.2d 633
Affirmed.
Gregory S. Martin (Brian P. Heald; Roger C. Brown; J. William Watson, Jr.; Moye, O‘Brien, O‘Rourke, Pickert & Martin, LLP; Watson & Morrison, P.C., Halifax, on briefs), for AMEC Civil, LLC.
Present: KELSEY and HALEY, JJ., and BUMGARDNER, S.J.
KELSEY, Judge.
Pursuant to
The circuit court rejected all of VDOT‘s arguments and awarded AMEC a general verdict of $21,181,941, the entire amount AMEC sought at the time of trial. AMEC requested, but the court disallowed, an award of prejudgment interest. The parties’ cross-appeals bring each of these issues to us for review. We reverse in part, affirm in part, and remand for further proceedings consistent with this opinion.
I.
In 2000, VDOT awarded AMEC a contract for the construction of the Route 58 Clarksville Bypass in Mecklenburg County. The contract price, approximately $72.5 million, included widening four miles of roadway, constructing interchanges and overpasses, and building four new bridges, the largest spanning the John H. Kerr Reservoir. The contract called for completion of the project in November 2003. The contract‘s actual completion occurred in 2005. During the five-year project, AMEC encountered difficulties meeting deadlines and completing tasks within its original cost estimates.
After the completion of the project, AMEC requested an additional $24 million in cost overruns. Though bundled as a single administrative claim, AMEC‘s request for damages included over a dozen specific allegations arising out of various aspects of the five-year project. When VDOT rejected AMEC‘s administrative claim, AMEC filed suit in the circuit court. In its amended complaint, AMEC alleged damages caused by:
- “differing site conditions” involving the drilled shaft work on the Kerr Reservoir bridge, Amended Complaint ¶¶ 36-63,
- high lake water levels in the Kerr Reservoir, id. ¶¶ 64-71,
- Work Orders 4, 6, 7, 12, and 16 authorizing deadline extensions, id. ¶¶ 72-80,2
- work performed during two “winter periods,” id. ¶¶ 81-89,
- “differing site conditions” involving “boulders at the B640 bridge,” id. ¶¶ 90-95,
- work site interference from “overhead power lines” at bridge B641, id. ¶¶ 96-104,
- problems with the “drilled shaft concrete mix design,” id. ¶¶ 105-16,
replacing the pier 17 foundation cap on the Kerr Reservoir bridge, id. ¶¶ 117-22, - a pier cap plan error involving pier 23 on the Kerr Reservoir bridge, id. ¶¶ 123-27,
- shaft layout problems with pier 18 on the Kerr Reservoir bridge, id. ¶¶ 128-33,
- repair to a pier 2 column on bridge B643, id. ¶¶ 134-36, and
- acceleration efforts, id. ¶¶ 144-50.
Seeking damages for each of these claims, AMEC relied on
In its responsive pleadings, VDOT asserted that AMEC failed “to satisfy legal and contractual conditions precedent to the initiation of legal action” and failed to “exhaust administrative remedies.” Prior to trial, VDOT filed a “Motion for Leave to File Pleas in Bar.” The pleas in bar contended that many of AMEC‘s claims violated
AMEC resisted the motion for leave on several grounds, including the assertion that the pleas in bar would involve a “full blown evidentiary hearing, based on a year‘s worth of voluminous discovery, which will properly occur at trial anyway.” AMEC Brief in Response to VDOT‘s Motion for Leave to File Pleas in Bar at 6. For this reason, AMEC argued, “a full and fair determination of whether notice was provided is best suited for trial.” Id. at 8.
On December 13, 2007, the circuit court held a hearing on VDOT‘s motion for leave. Without addressing the merits of the underlying pleas, the court held the motion for “leave to file pleas in bar will be denied.” On January 23, 2008, the court entered a written order denying VDOT‘s motion for leave to file the pleas in bar.5 About a month later, the parties received a letter opinion from the circuit court addressing the merits of the pleas in bar which the court earlier held could not be filed. The letter began with a reference to “oral argument” on “July 10, 2007” and ended with this conclusion: “Accordingly, the court finds that AMEC‘s actual notice was sufficient enough to satisfy the statutory and written notice provisions a[t] issue.” AMEC Civil, LLC v. Commonwealth, 74 Va. Cir. 492, 507 (2008).
With respect to the statutory written notice requirement, the circuit court held that “AMEC did not provide VDOT with written notice of its claims as required by
VDOT filed a motion for reconsideration pointing out that no hearing had been held on “July 10, 2007” as the court‘s letter opinion stated.7 More important, VDOT argued, the letter opinion “contained findings of fact and conclusions of law on issues on which no evidence has been taken” and concluded with a judicial ruling on pleas in bar “which the Court did not allow VDOT to file.” A few days later, the trial court entered an order denying without comment VDOT‘s motion to reconsider.
At trial, VDOT repeated its assertion that the lack of written notice barred many of AMEC‘s claims. When VDOT
After trial, the court issued a short letter stating it would enter a “general verdict” in favor of AMEC for $21,181,941, the entire amount of AMEC‘s request at trial. See Letter Opinion at 1 (July 1, 2008). The court refused AMEC‘S request for prejudgment interest. Reaffirming its pretrial ruling on VDOT‘s unfiled pleas in bar, the court stated that every “factual assumption” made in its pretrial ruling turned out to be true. Id. at 2. The court did not identify any specific exhibits or witnesses supporting this conclusion. The court instead referred generally to “memoranda addressing the issues” and “minutes” of meetings. Id. These unspecified documents, the court held, provided whatever “written notice” AMEC was required to give during the period of contract performance. Id.
II.
The cross-appeals in this case raise an array of issues, with the resolution of some mooting the need to resolve others. We believe the dispute on appeal can be clustered into four principal subjects:
- TIMELY, WRITTEN NOTICE OF AMEC‘S INTENTION TO FILE CLAIMS PURSUANT TO
CODE § 33.1-386(A) . - VDOT‘S CONTRACTUAL CHALLENGE TO SEVERAL OF AMEC‘S CLAIMS.
- VDOT‘S CHALLENGE TO THE TRIAL COURT‘S DAMAGE AWARD.
- AMEC‘S REQUEST FOR PREJUDGMENT INTEREST.
Our holdings on the issues we address render it unnecessary to offer advisory opinions on the issues we do not address. “In this case, as in all others, we seek to decide cases ‘on the best and narrowest ground available’ from the record.” Kirby
A. TIMELY, WRITTEN NOTICE OF AMEC‘S INTENTION TO FILE CLAIMS PURSUANT TO CODE § 33.1-386(A)
Under
Under
In its pretrial ruling, the circuit court held that “AMEC did not provide VDOT with written notice of its claims as required by
In its post-trial ruling, the court reaffirmed its pretrial ruling that “actual notice was an acceptable substitute for written notice.” Letter Opinion at 1 (July 1, 2008). The court added, however, a few sentences offering an alternative holding: From “minutes” of meetings and “memoranda” exchanged between the parties, VDOT “also had written notice of the plaintiff‘s claims.” Id. at 2 (emphasis added). On several levels, we disagree with both the circuit court‘s pretrial and post-trial rulings.
To begin with, the circuit court‘s pretrial ruling began its statutory analysis under the heading, “Legal Function Trumps
Governed by the “well-settled law that courts do not engage in rewriting statutes,” George v. Commonwealth, 276 Va. 767, 773, 667 S.E.2d 779, 782 (2008), neither we nor the circuit court have the power to excise the “written notice” requirement out of
As to what the written notice must say,
A written notice under
That said,
Under Flory, each written notice of intent must be examined individually. “By identifying more than one event that triggers the filing of an intent to file a claim, the statute acknowledges that not all claims will arise under the same circumstances.” Flory, 261 Va. at 238, 541 S.E.2d at 919. It necessarily follows that the “timing and form” of a putative notice of intent “requires an examination of the circumstances of each case.” Id. Guided by these principles, we review on appeal each of AMEC‘s claims that VDOT contends did not satisfy the written notice requirement of
- Claim Involving Drilled Shaft Work
This claim involved difficulties AMEC encountered while performing the drilled shaft work for the Kerr Reservoir bridge. Various letters and meeting minutes, some as early
As in Flory, the earlier exchange of documents concerning the problems with the drilled shaft work did not comply with
- Claim for Defects in the Drilled Shaft Concrete Specification
During the drilled shaft work, AMEC encountered problems with the concrete mix it used in an effort to comply with the applicable contractual specification. In its administrative claim, AMEC asserted the specification was defective and VDOT should have known about it. No evidence at trial, however, showed that AMEC ever provided any written notice during the performance of the contract of an intention to later file a claim for damages caused by the allegedly defective concrete specification.12
Claim for Concrete Formwork for Foundation Caps, Piers & Columns
In its administrative claim, AMEC sought damages for work associated with setting and stripping concrete formwork for foundation caps, piers, and columns. At no point during the contract performance, however, did VDOT ever receive written notice of AMEC‘s intention to file independent claims for these alleged additional costs.13
- Claim for Pier 17 Foundation Cap Repair
In December 2002, AMEC began constructing a foundation cap for pier 17 at the Kerr Reservoir bridge. Lake water leaked into the form during the concrete pour. The water weakened the concrete and rendered the foundation cap defective. AMEC eventually had to demolish the defective cap and replace it with a new one.
At trial, an AMEC witness testified that an unidentified AMEC representative, on an unspecified date, verbally informed VDOT of AMEC‘s intention to file a claim for damages arising out of the extra work associated with the pier 17 foundation cap repair. VDOT denied any such conversation took place. The record contains no written notice from AMEC to VDOT that can be reasonably interpreted as stating any intention by AMEC to file a claim based upon the repair work to pier 17‘s foundation cap.14
Claim for Work Authorized by Work Orders 4, 6, 7 & 16
The contract anticipated the need for additional work not specified in the bid or award. When the need arose, the contract authorized the issuance of a work order after the parties reached agreement on what was to be done, when it would be done, and at what additional cost.15 Over sixty work orders were issued during the project.
Work Orders 4, 6, 7, and 16 collectively authorized additional work, compensated AMEC at contractual unit prices, and extended the project completion date. When AMEC and VDOT agreed to these work orders, AMEC made no written request for any compensation other than the unit pricing specified in the contract. Nor did AMEC at that time communicate in writing any intention to later file a claim seeking damages related to these work orders. AMEC claimed it provided written notice in July 2004, see Trial Ex. D-135, at 7-8, but that notice came after commencement of the work authorized by Work Orders 4, 6, 7, and 16.16
- Claim for Acceleration Damages
On various aspects of the job, AMEC accelerated its efforts to keep on track with expected timelines. AMEC claimed this accelerated effort began in January 2002.
In 2003, one of AMEC‘s representatives engaged VDOT “in a talking process” concerning AMEC‘s acceleration efforts. The first written notice of any intention to assert an accelera
- Claim for Damages During the First Winter Period
The original contract term of performance contemplated three winter periods from 2000 to 2003. Anticipating the possibility of an extension of the completion date, VDOT Road and Bridge Specification § 108.09(h) provided that delays caused by “unforeseen causes” pushing work into later winter seasons could render winter working conditions “unsuitable” for completing the job. If that occurred, “consideration may be given to granting an extension of time that will encompass a suitable period during which such work can be expeditiously and acceptably performed.” Id. (emphasis added).17
In March 2003, AMEC provided VDOT with written notice of its intent to claim damages for the winter extension from November 30, 2003, to April 1, 2004 (the “first winter period“). This first winter period extension was necessary, AMEC stated, given the time extensions previously granted by VDOT in Work Orders 6, 7, 12, and 16. VDOT acknowledged receipt of the written notice and directed AMEC to keep daily records of its work and actual costs during the extension period.18
* * * * * *
As for AMEC‘s acceleration claim, it turns on the timing and scope of the April 2004 written notice. This notice was untimely as to acceleration efforts prior to April 2004 but timely as to acceleration efforts after April 2004 to the extent they were reasonably attributable to contractually compensable delays not “correctly and fully addressed by Work Order No. 39.” On remand, the circuit court should determine whether any such post-notice efforts existed consistent with our views of the contractual compensability of AMEC‘s claims. See Part II(B), infra at 18-28.
With respect to the remaining items contested on appeal (AMEC‘s claims for drilled shaft work; drilled shaft concrete specification; concrete formwork for foundation caps, piers, and columns; pier 17 foundation cap repair; and Work Orders 4, 6, 7, and 16),20 we hold the court erred as a matter of law in concluding AMEC gave timely “written notice” of its “intention to file” a claim “at the time of the occurrence or beginning of the work upon which the claim and subsequent action is based.” See
B. VDOT‘S CONTRACTUAL CHALLENGES TO SEVERAL OF AMEC‘S CLAIMS
At trial, VDOT challenged AMEC‘s recovery of damages caused by elevated lake water levels, two winter periods, unanticipated boulders at the B640 bridge, interference from overhead power lines, and premium costs for a bond. No provisions of the contract, VDOT argued, provided any remedy for these claims.
- Damages for Elevated Lake Water Levels
Another provision of the contract, however, directly addressed the issue of fluctuating lake water levels. Under the heading “Site Information,” the contract stated:
The Contractor should be aware that due to the method of operating the John H. Kerr Reservoir and other factors beyond the control of the Department, the power pool elevation in the reservoir routinely fluctuates by several feet. These fluctuations can take place within a few days. It is the responsibility of the Contractor to avail himself of the historical records of the water levels maintained by the U.S. Army Corps of Engineers, Wilmington District and determine the impacts possible fluctuations may have on planned construction methods and operation. Information
on past water levels is available through the Corps website at http://www.saw.usace.army.mil while current and predicted water elevations can be obtained by contacting the John H. Kerr Powerhouse at (804) 738-6371....
Contract Order No. F77 at 142.21 VDOT argued this provision precluded high lake water fluctuations from being deemed a differing site condition under Specification § 104.03.
We cannot discern from the record how the circuit court reconciled these two provisions. AMEC draws our attention to a remark from the bench on the last day of trial in which the court said the high water was a “major condition,” making it “very difficult to believe that anyone could reasonably be expected to plan for a period of high water at the level this water was.” The ostensible clarity of that remark, however, is clouded by another statement, only a moment or two earlier, in which the court acknowledged: “I‘m not sure there were differing site conditions or not.” And both comments were made in a soliloquy which began, “Let me give you a couple of observations because I‘m still not totally pessimistic you can find a way to work this out.”
However one interprets the court‘s remarks, we hold the contract defeats AMEC‘s high-water claim as a matter of law. Specification § 104.03 authorized a recovery of costs caused (i) by “subsurface or latent physical conditions” encountered during the work which differ materially “from those indicated in the contract,” or (ii) by ”unknown physical conditions of an unusual nature” which differ materially “from those ordinarily encountered and generally recognized as inherent in the work....” (Emphasis added.) In the lexicon of government contract law, the first part of § 104.03 is known as a Type I condition and the second as a Type II condition. See general-ly Gerald I. Katz, Virginia General Conditions for Public
Both aspects of Specification § 104.03 must then be placed within the context of the Site Information provision. This provision unmistakably informed AMEC that “factors beyond the control” of VDOT caused the lake water level to “routinely” fluctuate “by several feet.” See Contract Order No. F77 at 142. Inherent in the representation that fluctuations by several feet were routine was the suggestion that non-routine fluctuations might be even higher. The Site Information provision warned AMEC to examine the U.S. Army Corps historical records (which included nearly 50 years of water elevation data) to “determine the impacts possible fluctuations may have on planned construction methods and operation.” Id. (emphasis added).
When read alongside the Site Information provision, neither aspect of § 104.03 justifies the court‘s award. No Type I condition existed because the elevated lake water levels did not differ from any condition “indicated in the contract.” See Specification § 104.03. Only an incongruence between a contract‘s representations and the realities of the worksite triggers a Type I condition under § 104.03. See, e.g., Asphalt Roads & Materials v. Commonwealth, 257 Va. 452, 454, 512 S.E.2d 804, 805 (1999) (finding Type I condition where “contract drawings” badly underestimated the specific amount of unusable soil to be removed by the contractor). The VDOT-AMEC contract established neither a baseline nor even a range of fluctuations. Instead, the contract advised AMEC that the water level of the lake “routinely fluctuates” by several feet and directed AMEC to review the historical records to take into account non-routine “possible fluctuations” of these levels. See Contract Order No. F77 at 142. Because lake water fluctuations were “beyond the control” of VDOT, id., the contract steered clear of making any binding representations on the subject.
As Specification § 104.03 makes clear, only “unknown physical conditions” can constitute a Type II condition. Known conditions, whether of an unusual nature or not, must be factored into the contractor‘s risk assessment. See, e.g., Steven W. Feldman, Government Contract Guidebook § 28:8(b), at 797-98 (4th ed. 2008-09) (listing “[h]igh water level in a lake where work was to be performed” as a condition not included within the “Differing Site Conditions” provision); Cibinic, Nash & Nagle, supra, at 486-87 (listing “flooding” and “unusually high water” as outside the scope of the “Differing Site Conditions” clause). Under the VDOT-AMEC contract, routine and non-routine water level fluctuations presented known conditional risks associated with the worksite—both categorically placed outside the scope of a Type II condition of Specification § 104.03.
In reply, AMEC argues VDOT conceded its contractual responsibility to compensate AMEC for delays attributable to high water by extending the contract completion date for this very reason. Thus, “AMEC as a matter of logic became entitled to compensation for the delay.” AMEC Appellee Br. at 23 (No. 2061-08-2). We disagree.
VDOT issued work orders granting AMEC extra time to complete the work. The extensions protected AMEC from per diem liquidated damages under Specification § 108.12 for failing to complete the work on time and also protected the
As a general rule, “where the issue is excusable delay as opposed to compensable delay, the government accedes, because alternatives such as default termination are not feasible or otherwise not in the governments best interests.” Feldman, supra, § 29.11, at 827. Similarly, excusable delay provisions generally “protect a contractor only from a default termination or liquidated damages liability.” “These clauses do not entitle the contractor to recover any additional performance costs.” Glen E. Monroe, Government Contract Law Manual § 2.92, at 52 (1979). “Normally, if the delay was caused by events beyond the contractor‘s control, the contractor will be excused for the delay in performance (under the contract‘s “Default” clause) but is responsible for the additional costs caused by the delay.” Feldman, supra, § 16:1, at 488. AMEC‘s view to the contrary, if it had the force of law, would badly disorient the management of government contracts. A contracting agency would be loath to grant time extensions if the invariant consequence of doing so meant the agency thereby stipulated to inestimable damages and forfeited any right to contest the compensability of the contractor‘s claim.23
Claim for Damages During Two “Winter Periods”
The contract initially required AMEC to complete the project by November 2003. On several occasions, VDOT agreed to extend the deadline. The extensions collectively spanned two additional winters. In the circuit court, AMEC argued it had a contractual right to be compensated for damages during these two additional winter periods.
On appeal, VDOT claims the circuit court‘s general verdict included compensation for each day of both winter periods: $1,938,418 for November 30, 2003, to April 1, 2004, and $1,922,530 for November 30, 2004, to April 1, 2005. AMEC disagrees, arguing that it “did not claim, nor was it awarded, damages for the entirety of both Winter Periods, as VDOT claims.” AMEC Appellee Br. at 25 (No. 2061-08-2) (emphasis in original). AMEC asserts its evidence established that, “through AMEC‘s efforts, the ‘Second Winter Period’ did not ultimately affect AMEC‘s completion of the Project.” Id. “Thus, to the extent AMEC overcame any delay event, including the ‘Second Winter Period,’ AMEC did not seek compensation for that time.” Id. (emphasis in original).
The circuit court‘s general verdict did not segregate either or both of the additional winter periods from the aggregate damages awarded to AMEC. Because we reverse many of AMEC‘s claims the circuit court relied upon for its general verdict, we cannot determine how much, if any, of the damage award is attributable to either or both of the additional winter periods. We decline to offer what, in all likelihood, could be an advisory opinion.
Suffice it to say, even when a government contract authorizes recovery of damages for winter weather, the “contractor must demonstrate—through contemporaneous records if possible—the extent of the adverse weather and its impact on
- Claim Related to Boulders at Bridge B640
At trial, AMEC claimed it sustained damages due to drilled shaft problems and unanticipated boulders at the bridge B640 worksite. These conditions allegedly delayed work for 40 days. On appeal, VDOT does not challenge the compensability of the boulders claim. Instead, VDOT contends the evidence viewed in the light most favorable to AMEC proved no more than 8 days of delay attributable to boulders. The remainder, VDOT argues, belongs solely to delays attributable to the drilled shaft claim.
Here again, on this record, we cannot resolve this dispute on appeal given the inseverable nature of the circuit court‘s general verdict. Because we find many of AMEC‘s claims statutorily barred (including the drilled shaft claim), we remand the boulders claim to the circuit court with instructions to examine the evidentiary record and to make specific factual findings.25 On remand, the circuit court should apply the maxim: “[W]here there is evidence of damage from several causes, for a portion of which a defendant cannot be held liable, a plaintiff must present evidence that will show within a reasonable degree of certainty the share of damages for which
- Claim for Interference from Overhead Power Lines
The circuit court‘s general verdict included an award of damages AMEC sought as a result of having to wait for Dominion Virginia Power to deenergize overhead power lines near the worksite of pier 1 on bridge B641. AMEC claimed Specification § 105.07 inaccurately stated that “[e]xisting utilities” were indicated on the plans. The plans specifically noted the presence of the “footings for the power line post” near pier 1 on bridge B641 but not the lines strung between the power poles. After the contract was awarded, Dominion Virginia Power moved the power pole pedestal shown on the original plans to make way for AMEC to install the road leading to bridge B641.
In its pretrial motions and at trial, VDOT pointed out that AMEC failed to read the entirety of Specification § 105.07. Though § 105.07 anticipated that all utilities would be indicated on VDOT‘s plans (presumably the poles as well as the lines between them), the provision nonetheless placed the burden on AMEC to conduct its own pre-construction investigation to confirm the information in the plans:
Prior to preparing a bid, the bidder shall contact known utility owners to determine the nature, extent, and location of existing, adjusted, or new utility facilities. Any additional cost resulting therefrom shall be reflected in the bid price for other items in the Contract.
Specification § 105.07. The contract further provided: “The new location of such utilities will not normally be shown on the plans. Some utilities may remain or be adjusted within the construction limits simultaneously with project construction operations.” Id. (emphasis added). The specification required AMEC to “coordinate project construction with planned utility adjustments....” Id.
Except as otherwise specified herein, the Department will not be responsible for any claims for additional compensation from the Contractor resulting from delays, inconvenience, or damage sustained by him attributable to interference by utility appurtenances, or the operation of moving the same, other than a consideration of an extension of time.
If it is determined that interference by utility appurtenances caused a delay of such magnitude or otherwise altered project operations so as to increase significantly the Contractor‘s cost of performing the work, the [VDOT] Engineer may consider additional compensation limited to the actual costs incurred by the Contractor. The determination of the severity of the interference, its impact on the Contractor‘s costs, and the amount, if any, of compensation shall be at the sole discretion of the Engineer.... Nothing herein shall be construed as requiring acceptance of the Contractor‘s presentation or payment of additional compensation.
In short, Specification § 105.07 noted that the plans should indicate the location of utility lines. AMEC does not deny the pre-construction plans depicted the location of the “power line pedestal” or claim the utility lines were not readily apparent from a site visit. At trial, AMEC claimed only that the lines themselves were not drawn in. Even assuming an insufficiency in the plans, Specification § 105.07 obligated the contractor to conduct its own investigation “to determine the nature, extent, and location” of the lines and to “coordinate project construction with planned utility adjustments.” AMEC conceded that it made no effort to do so.
While VDOT reserved the “sole discretion” to provide the contractor either with an extension or compensation, Specification § 105.07 divested AMEC of any right to “additional compensation” beyond that which VDOT has approved. For these reasons, the circuit court erred in awarding any contrac
- Claim for “Bond Premium”
The circuit court awarded AMEC damages for a “bond premium.”26 On appeal, VDOT challenges the bond premium award as factually insupportable.27 We have found no place in the record, however, where VDOT objected to the bond premium.
Rule 5A:18 precludes appellants from raising for the first time on appeal “grounds asserted as a ‘basis for reversal’ of the trial court‘s judgment.” Blackman v. Commonwealth, 45 Va. App. 633, 642, 613 S.E.2d 460, 465 (2005). Exceptions to Rule 5A:18 exist—but we employ them only in rare cases, and we never invoke them sua sponte. See Widdifield v. Commonwealth, 43 Va. App. 559, 564, 600 S.E.2d 159, 162 (2004) (en banc); Edwards v. Commonwealth, 41 Va. App. 752, 761, 589 S.E.2d 444, 448 (2003) (en banc), aff‘d by unpublished order, No. 040019 (Va. Oct. 15, 2004). Consequently, we will not review on appeal the factual or legal basis for the circuit court‘s award of a bond premium.
C. VDOT‘S CHALLENGE TO THE TRIAL COURT‘S DAMAGE AWARD
With respect to compensatory damages—both on undisputed claims and those surviving appeal—we must address
- Home Office Overhead Damages
AMEC‘s expert included in his damage model a component for extended, unabsorbed, home office overhead. In a pretrial in limine motion and at trial, VDOT objected to AMEC‘s failure to present any evidence that it was unable to recoup home office overhead expenses by deploying its workforce on other revenue-producing aspects of the project. The court rejected VDOT‘s objection without comment.
Overhead costs include expenses incurred by a contractor “for the benefit of its business as a whole.” Fairfax County Redev. & Housing Auth. v. Worcester Bros., 257 Va. 382, 387-88, 514 S.E.2d 147, 150-51 (1999). The calculation includes, for example, “the salaries of office staff, accounting expenses, dues and subscriptions, equipment costs, and utility services.” Id. When a project takes longer than the contractor estimated, the overhead expenses are “extended” for the period of delay. See generally Cibinic, Nash & Nagle, supra, at 720-26; Branca & Berry, supra, § 11:25, at 369. The overhead costs become “unabsorbed” when the contractor cannot perform other revenue-generating work to cover the lost income from the delayed work. See W. Noel Keyes, Government Contracts § 42.8, at 944-45 & nn. 13 & 15 (3d ed. 2003). “When this occurs, the ‘reduced activity’ contract no longer ‘absorbs’ its share of overhead costs.” Fairfax County Redev., 257 Va. at 388, 514 S.E.2d at 150 (citation omitted).
Not “every instance of delay,” even if attributable to a contractual breach, entitles the contractor to a recovery of home office overhead costs. Id. at 388, 514 S.E.2d at 151. To prevail under Virginia law, the contractor must prove among other things “that it could not otherwise reasonably recoup its pro rata home office expenses incurred while its workforce
On appeal, VDOT contends AMEC failed to offer any evidence that it could not reasonably recoup its home office overhead costs from other revenue-producing work during the periods of delay.28 We agree. AMEC‘s expert described his calculation of home office overhead in cursory terms. His trial exhibit simply did the math: first calculating the ratio of project revenue to company revenue, applying that ratio to home office overhead, creating a per diem rate from the resulting project attribution, and then multiplying the per diem rate by the total days of delay. These mathematical equations, however, relied wholly upon the unstated (and thus unproven) assumption that AMEC could not have recouped its home office overhead from other revenue-producing work. Neither AMEC‘s expert nor any of its fact witnesses addressed this point.
The inadequacy of AMEC‘s factual foundation parallels a similarly insufficient showing rejected by Lockheed. There, a contractor‘s expert allocated “company-wide overhead ex
When a breach by a party causes a delay to the ability of the other party to perform, the injured party is entitled to recover, as damages, unabsorbed overhead expenses. To recover such damages, the injured party must show that it could not otherwise recoup its pro rata home office expenses incurred during the delay and it must prove the amount of these expenses with reasonable certainty.... [T]he plaintiff is required to show that it was reasonably unable to recoup its overhead costs. There is no such evidence in this case.
Id. at 115-16, 524 S.E.2d at 433 (second emphasis added). The same can be said here as well. AMEC‘s evidence failed to address its “ability or inability to reasonably recoup,” id. at 116, 524 S.E.2d at 433, overhead expenses from other revenues. The circuit court, therefore, erred in finding AMEC‘s evidence sufficient to support an award of home office overhead.29
- Actual Costs vs. § 109.05 Mark-Ups
Prior to trial, VDOT filed a motion in limine objecting to AMEC‘s expected expert testimony on damages. AMEC‘s expert, VDOT argued, improperly calculated damages by employing cost mark-ups under Specification § 109.05. These mark-ups included, among other things, enhancements for “administration and profit.” The circuit court denied the motion without prejudice reserving all such issues for resolution at trial.
VDOT renewed its objection at trial to this testimony and contested any damage award based upon it. VDOT argued § 109.05‘s “force account” pricing formula applied not to contractual damages generally but only to “[e]xtra work” pursuant to work orders issued by VDOT during the project. AMEC‘s claims for contractual damages did not seek recovery for force-account work orders.
The circuit court rejected VDOT‘s arguments without comment. The court‘s general verdict adopted in full the damage figures advocated by AMEC‘s expert. On appeal, AMEC defends the circuit court‘s award arguing that “Specification § 109.05 prescribes the method of calculation.” AMEC Appellee Br. at 18 (No. 2061-08-2).
As we have already explained, AMEC failed to present a prima facie case for the recovery of home office overhead. To the extent § 109.05‘s force-account pricing formula included a recovery of home office overhead, the circuit court erred by awarding such damages.
We reach the same conclusion with respect to profit margins included within the mark-ups allowed by § 109.05. Because AMEC‘s claims did not (and could not) seek recovery on a force-account basis, § 109.05 has no relevance.30 Instead,
To the extent it relied on § 109.05‘s allowance of profit margin mark-ups, AMEC‘s damage model was systemically flawed. An award of actual costs includes direct costs (like the price of materials and the wages of employees) and indirect costs (like home office overhead). See Fairfax County Redev., 257 Va. at 388, 514 S.E.2d at 151. Actual costs exclude profit margin mark-ups, which by definition go beyond direct and indirect expenditures. Cf. William Schwartzkopf & John J. McNamara, Calculating Construction Damages § 8.03, at 171 (2d ed. 2001) (“Generally, profit may not be recovered when a contractor is simply delayed in the performance of its work.“).
On remand, the circuit court should reexamine the evidentiary record to determine whether the evidence provides a reasonable basis to determine actual costs incurred by AMEC as a result of the claims unaffected by this appeal.32 The
D. AMEC‘S REQUEST FOR PREJUDGMENT INTEREST
The circuit court denied AMEC‘s request for prejudgment interest on its award of compensatory damages. On appeal, AMEC asserts the court erred in doing so. We disagree.
“Interest may be awarded against a sovereign only by its consent.” Bd. of Supervisors v. FCS Bldg. Ass‘n, 254 Va. 464, 466, 492 S.E.2d 634, 636 (1997) (citing Ry. Express Agency Inc. v. Commonwealth, 196 Va. 1059, 1066, 87 S.E.2d 183, 187 (1955)). In Virginia, “so far as we know, it has never been held by this court that a claim asserted against the State ... bears interest where there is no provision in the statute or authorized agreement creating the liability for the payment of interest.” County of Fairfax v. Century Concrete Servs., 254 Va. 423, 425, 492 S.E.2d 648, 650 (1997) (quoting City of Lynchburg v. Amherst County, 115 Va. 600, 608, 80 S.E. 117, 120 (1913)); see Commonwealth v. Safe Deposit & Trust Co., 155 Va. 458, 460, 155 S.E. 897, 898 (1930) (noting that “interest, when not stipulated for by contract, or authorized by statute, ... is not to be awarded against a sovereign government“).33
No express statutory waiver of sovereign immunity exists for AMEC‘s claim for prejudgment interest.
Nothing in the contract authorized a recovery of prejudgment interest on a successful administrative claim. The contract limited payment of interest to situations involving an untimely “final payment” under § 109.09 or a “partial payment” invested with an escrow agent under § 109.07. These payments, however, involve agreed-upon contractual payments—not contested sums asserted in the administrative
III.
In sum, we reverse in part and affirm in part the circuit court‘s final order.
A. Statutory Written Notice Requirements.
B. Contractual Compensability of Several of AMEC‘s Claims.
The circuit court erred in awarding damages for AMEC‘s claims related to elevated lake water levels and interference from overhead power lines.
With respect to AMEC‘s claim related to the two winter periods, we direct the circuit court on remand to review the evidentiary record and to make specific findings on whether AMEC proved any entitlement to damages for conditions
With respect to AMEC‘s claim of damages caused by boulders at bridge B640, we direct the circuit court on remand to review the evidentiary record and to make specific findings on whether AMEC proved damages specifically attributable to this condition.
Applying Rule 5A:18, we affirm the circuit court‘s award of damages associated with AMEC‘s bond premium.
C. Calculation of AMEC‘s Damages.
The circuit court erred in granting AMEC an award for home office overhead and by allowing AMEC to mark up its actual costs with either home office overhead or profit margins. We direct the court on remand to excise such mark-ups from any damage award attributable to claims surviving this appeal.
D. Prejudgment Interest.
We affirm the circuit court‘s denial of AMEC‘s request for an award for prejudgment interest. VDOT raises no challenge on appeal to any award of post-judgment interest, and thus, we do not address this issue.
Reversed in part, affirmed in part, and remanded for further proceedings consistent with this opinion.
