MARTIN BROS. CONTRACTORS, INC. v. VIRGINIA MILITARY INSTITUTE
Record No. 081403
Supreme Court of Virginia
April 17, 2009
OPINION BY SENIOR JUSTICE CHARLES S. RUSSELL
Present: Hassell, C.J., Koontz, Kinser, Lemons, Goodwyn, and Millette, JJ., and Russell, S.J. FROM THE CIRCUIT COURT OF ROCKBRIDGE COUNTY, Michael S. Irvine, Judge
Facts and Proceedings
The facts pertinent to this appeal are undisputed and the parties agree that the case presents a pure question of law. In April 2004, Martin Bros. Contractors, Inc. (Martin), a licensed contractor, entered into a construction contract with Virginia Military Institute (VMI), a public educational institution organized as a public corporation pursuant to
Martin claimed $430,242.56 as damages for delay, plus the costs of recovery. VMI admitted that Martin was without fault
Martin brought this action against VMI seeking recovery of the full amount of its claim. The parties submitted the case to the circuit court on cross-motions for summary judgment. By letter opinion, the court ruled that the contract provisions relied on by VMI were enforceable as liquidated damages provisions expressly permitted by
Analysis
This case turns on the interpretation of
Public construction contract provisions barring damages for unreasonable delays declared void.
A. Any provision contained in any public construction contract that purports to waive, release, or extinguish the rights of a contractor to recover costs or damages for unreasonable delay in performing such contract, either on his behalf or on behalf of his subcontractor if and to the extent the delay is caused by acts or omissions of the public body, its agents or employees and due to causes within their control shall be void and unenforceable as against public policy.
B. Subsection A shall not be construed to render void any provision of a public construction contract that:
. . . .
3. Provides for liquidated damages for delay[.]
. . . .
D. A public body denying a contractor‘s claim for costs or damages due to the alleged delaying of the contractor in the performance of work under any public construction contract shall be liable to and shall pay such contractor a percentage of all costs incurred by the contractor to investigate, analyze, negotiate, litigate and arbitrate the claim. The percentage paid by the public body shall be equal to the percentage of the contractor‘s total delay claim for which the public body‘s denial is determined through litigation or arbitration to have been made in bad faith.
In Blake Construction Co. v. Upper Occoquan Sewage Authority, 266 Va. 564, 587 S.E.2d 711 (2003), we construed and applied the foregoing statute. We held that it “means what it says: ‘Any provision . . . to waive, release, or extinguish the rights of a contractor . . . shall be void.’ ” (Emphasis in original.) Id. at 576, 587 S.E.2d at 717-18.
The contract language on which VMI relies appears in the General Conditions (GC) that form a part of the contract. GC 43(b) provides that the contractor may recover damages for owner-caused delay in the work, provided the delay is “unreasonable.” In such an event, the contractor is permitted to submit a change order in accordance with GC 38 adding additional days for completion of the work. GC 38(e)(6) provides:
[T]he following Site direct overhead expenses for the change to the time may be considered . . . :
The Site superintendent‘s prorata salary, temporary Site office trailer expense, and temporary Site utilities including basic telephone service, electricity, heat, water, and sanitary / toilet facilities. All other direct and indirect overhead expenses are considered covered by and included in the Subsection (d) markups above.
GC 38(f)(2) and (3) provide:
(f) Allowable costs for changes in the Work shall not include the following:
. . . .
(2) Home office expenses including payroll costs for the Contractor‘s officers, executives, administrators, project managers, accountants, counsel, engineers, timekeepers, estimators, clerks, and other similar administrative personnel employed by the Contractor, whether at the Site or in the Contractor‘s principal or branch office for general administration of the Work. These costs are deemed overhead included in the percentage markups allowable in Subsection (d) above.
(3) Home and field office expenses not itemized in Subsection 38(e)(6) above. Such items include, but are not limited to, expenses of Contractor‘s home and branch offices, Contractor‘s capital expenses, interest on Contractor‘s capital used for the Work, charges for delinquent payments, small tools, incidental job costs, rent, utilities, telephone and office equipment, and other general overhead expenses.
(Emphasis added.)
Martin claimed site delay damages amounting to $225,937.40 and home office delay damages amounting to $204,305.16. Relying on the limitations above, VMI refused to pay any site damages beyond $99,646.20 and refused to pay any home office damages at all, asserting that the GC provisions quoted above, read with GC 38(d), barred their recovery.
GC 38(d) provides, in pertinent part:
(d) The percentage for overhead and profit to be used in calculating both additive and deductive
changes in the Work (other than changes covered by unit prices) shall not exceed the percentages for each category listed below. Said percentages for overhead and profit shall be applied only on the net cost of the changed Work (i.e. difference in cost between original and revised Work):
(1) If a Subcontractor does all or part of the changed Work, the Subcontractor‘s markup for overhead and profit on the Work it performs shall be a maximum of fifteen percent (15%). The Contractor‘s mark-up on the subcontractor‘s price shall be a maximum of ten percent (10%).
(2) If the Contractor does all or part of the changed Work, its markup for overhead and profit on the changed Work it performs shall be a maximum of fifteen percent (15%).
VMI contends that all the claimed home office expenses and all site expenses beyond $99,646.20 are included in the markups contained in GC 38(d), quoted above. VMI argues that the quoted clauses are, in reality, liquidated damage provisions expressly permitted by
As a general statement, the circuit court‘s observation is valid, but its application to the facts of this case depends on whether the parties had actually entered into any agreement for the calculation of delay damages. The flaw in VMI‘s argument is that the markup provisions quoted above provide compensation to the contractor for added work required
The markup provisions of GC 38(d), quoted above, are liquidated damage provisions to cover additional expense the contractor may incur for administration, plus agreed profit, for extra work required by the owner‘s change orders. They are not an agreed formula for the calculation of damages for delay and, therefore, are not liquidated damage provisions contemplated by
Conclusion
Because we adhere to the analysis of the effect of
Reversed and remanded.
CHARLES S. RUSSELL
SENIOR JUSTICE
