OPINION
This contract dispute is currently before the court on defendant’s Motion For Summary Judgment and plaintiffs Cross-Motion For Summary Judgment. For the reasons set forth herein, defendant’s Motion For Summary Judgment is hereby granted and plaintiffs Cross-Motion for Summary Judgment is accordingly denied.
BACKGROUND
I. Factual Background
The parties have filed joint stipulations of fact and accordingly, the following facts are undisputed, unless otherwise indicated. Plaintiff, Conner Brothers Construction Company, Inc. (Conner), is an Alabama corporation. On June 28, 1996, the United States Army Corps of Engineers, Savannah
The Hospital is located at Fort Benning, Georgia, and was constructed in 1958, with an adjacent warehouse and a two-story outpatient clinic constructed in 1977, and exteri- or stair towers constructed in 1978. In 1992, the Corps sought to renovate the Hospital, in part, to address potential Life Safety Code concerns. The most serious deficiencies were in corridor wall protection. Those deficiencies included lack of effective smoke partitions for compartmentalization of fire zones, inadequate protection of hazardous areas, lack of exit capacity on patient sleeproom floors, and a fire alarm system which was inaudible from the outpatient clinic. The Corps sought to correct the Life Safety Code deficiencies by, among other things, replacing existing doors and frames to ceiling corridors and other partitions from floor levels to the structure above in order to achieve the necessary fire rating; providing a protected path to exits; adding fire alarm pull boxes at strategic locations; replacing plain glass at view windows and door vision panels with required wire glass; and removing and replacing asbestos-containing materials.
Most of the ceilings in the Hospital were of a locked-in-place, concealed spline design. In some areas of the Hospital, the ceilings were constructed of plaster. During the solicitation of the contract, and prior to the submission of bids, the Corps amended its solicitation by issuing Bid Amendment 0002, dated May 15, 1996, which advised bidders, in relevant part, that they would be responsible for the demolition of the old, existing Hospital ceilings and the reinstallation of new ceilings throughout the Hospital while the Hospital remained an occupied and functioning medical facility.
The contract called for the successful bidder to install a new sprinkler system and replace existing 1' x 1' and 2' x 4' ceiling tile systems with a new 2' x 2' lay-in ceiling tile system. Included in the replacement work was the replacement of existing grilles, diffusers, and light fixtures, as indicated in the contract specifications and drawings.
A diffuser is a circular, square or rectangular air distribution outlet, generally located in the ceiling, and comprised of deflecting members to discharge supply air in various directions. A grille is a louvered or perforated panel used to cover an air duct opening in a wall, ceiling or floor. Diffusers and grilles are mechanical instruments regulating air
The diffusers and grilles at the Hospital varied in size and shape in accordance with the design air flow. The contract drawings showed that the new diffusers and grilles were intended to have the same air flow as the old diffusers and grilles, as indicated in contract drawing, Plate M-8, sheet 77, listing the neck sizes at the interface between the existing ductwork and the diffusers and grilles. The contract also specified that “[djiffuser types shall be as indicated ---- Duct collar connecting the duct to diffuser shall be airtight and shall not interfere with volume controller. Return or exhaust units shall be similar to supply diffusers.” Def.’s App. at 54.
The contract also contained the following clauses: (1) Federal Acquisition Regulation (FAR) 52.243-4, Changes, see 48 C.F.R. § 52.243-4 (1987) (hereinafter changes clause); (2) FAR 252.236-7001, Contract Drawings, Maps and Specifications, see 48 C.F.R. § 252.236-7001 (1991) (hereinafter omissions clause); (3) FAR 52.236-2, Differing Site Conditions, see 48 C.F.R. § 52.236-2 (1987) (differing site conditions clause); (4) FAR 52.236-3, Site Investigation and Conditions Affecting the Work, see 48 C.F.R. § 52.236-3 (1984) (hereinafter site investigation clause); and (5) FAR 52.236-27, Site Visit (Construction), see 48 C.F.R. § 52.236-27 (1995) (hereinafter site visit clause).
Mr. Donald Conner, president of Conner, made three pre-bid site visits to the project site.
Two additional bidders responded to the government’s solicitation: (1) Wright Associates, Inc.’s bid of $8,290,500; and (2) Wither-ington Construction Corporation’s bid of $9,070,297. The Corps’ estimate for the project was $8,045,869. Conner’s low bid was 90.3% of the Corps’ estimate, and did not provide a separate estimate for the contemplated mechanical work. Prior to award, the government saw no need for bid verification and did not request that Conner verify its bid. The contract was awarded to Conner on June 28,1996.
During performance of the contract, Conner’s mechanical subcontractor, Phenix, raised the issue of extra compensation for reconnecting the new diffusers and grilles to the Hospital’s existing HVAC system. The precise date that this occurred remains an immaterial dispute between the parties. Conner alleges that the issue was raised on February 11, 1997, while the Corps contends that this issue was first raised on February 14, 1997. During performance of the contract, Phenix found that the existing ducts were “hard piped” to the diffusers and grilles and that the existing HVAC duct system was located too low, or tight, to the new ceiling to permit the re-installation of hard duct-work.
Between March 1997 and September 1997, the parties held at least one meeting and exchanged other correspondence regarding this issue. The substance of the meeting and correspondence is in dispute. Conner alleges that during the meeting, the Corps advised Conner that “the connection between the new diffuser and the existing duct are considered to be part of subject contract and a modification shall not be forthcoming for this portion of work.” Pl.’s Findings of Fact 11152. Conner alleges that the Corps acknowledged that reconnection of the grilles and diffusers was additional work under the contract and that the meeting and correspondence represented an attempt to negotiate a price. The Corps maintains that, at this meeting, Conner merely raised the issue of extra compensation for reconnecting the diffusers and grilles. The Corps’ position throughout these discussions, however, was that Conner was not entitled to an upward adjustment to the contract price because the alleged “extra-work” was simply required work by the contract as awarded.
On October 17, 1997, the Corps advised Conner that if it desired to submit a claim pursuant to the contract, Conner should certify its claim. On November 7,1997, Conner provided its certified claim to the Corps in the amount of $245,954 on behalf of Phenix for alleged increased costs related to - the installation of replacement diffusers and grilles in the Hospital’s HVAC system.
On January 21, 1998, the contracting officer forwarded a letter to Conner indicating her intent to deny the claim and offered Conner the opportunity to present any further matters relating to the diffuser and grille issue. As a result, a meeting was held between the contracting officer and Conner on August 11, 1998, in which Conner again stated its position that it was entitled to an upward adjustment of the contract price. On September 1, 1998, the contracting officer issued her final decision, finding no merit in Conner’s claim and denying the claim in its entirety. The contracting officer concluded that the reconnection of new diffusers and grilles was manifestly necessary to perform the contract as awarded and that any difficulties Conner or Phenix encountered during performance were discoverable by Conner, or its subcontractor, upon their review of the contract and during a reasonable pre-bid site inspection.
On September 4, 1998, Conner received the contracting officer’s final decision via certified mail. Conner filed its complaint in this court on August 26, 1999, seeking review of the contracting officer’s final decision pursuant to the Contract Disputes Act of 1978(CDA), 41 U.S.C. § 601, et seq (2000).
II. Procedural History
This action is an appeal from the contracting officer’s final decision denying Conner’s claim for additional compensation for air duct modifications. Conner received a copy of the contracting officer’s September 1, 1998 Final Decision on September 4, 1998 and filed its complaint, on behalf of its mechanical subcontractor, Phenix, on August 26, 1999. Conner seeks a review of the contracting officer’s final decision pursuant to the CDA.
Conner claims that the government is responsible for $245,954 in costs which were allegedly incurred by Phenix during performance of the contract. Conner alleges that during performance of the contract, Phenix encountered conditions in above-ceiling space that were different from those represented in the contract specifications and drawings. Specifically, Conner alleges that during the demolition and installation of ceilings in the Hospital, and during removal and replacement of HVAC diffusers and grilles (referred to by the parties as “D & Gs”), Phenix performed work not contemplated by the
Conner alleges seven causes of action relating to the D & G reinstallation costs. Specifically, Conner alleges: (1) that the government breached the contract by failing to pay for the additional work conducted; (2) that the government changed the contract under the changes clause by requiring Conner to perform the added work; (3) that the contract specifications and drawings were defective for failing to show the need to demolish existing ductwork or to provide a design for the fabrication and installation of the new ductwork; (4) that the government had superior knowledge concerning the need for the demolition of the existing ductwork, as well as the design, fabrication and installation of the new ductwork; (5) that it was impossible for Conner to complete the work as provided in contract specifications and drawings without a design modification; (6) that the government is estopped from asserting that the work was not changed; and (7) that the government failed to call to Conner’s attention a potential mistake in the bid related to the D & G work.
On September 10, 2002, the government filed its Motion for Summary Judgment, arguing that the plain terms of the contract unambiguously required Conner to replace the existing diffusers and grilles with new diffusers and grilles. The government argues that the ordinary meaning of the contract terms required Conner to install the new diffusers and grilles into the existing HVAC system. Accordingly, defendant argues, Conner cannot demonstrate that it is entitled to an upward adjustment of the contract. The government farther contends that despite Conner’s claimed discovery of additional above-ceiling work during performance, all of the work necessary to replace and install the diffusers and grilles was required under the contract.
On October 11, 2002, plaintiff filed its Response to Defendant’s Motion for Summary Judgment, and at the same time, its Cross-Motion for Summary Judgment. With respect to defendant’s Motion for Summary Judgment, plaintiff argues that the government misunderstands Conner’s claim as simply relating to the reconnection of the diffusers and grilles. Conner contends that the issue, instead, is whether the extensive demolition and removal of the existing duct-work running out to the diffuseis and grilles was also required under the contract. With respect to plaintiffs Cross-Motion for Summary Judgment, plaintiff argues that the facts and law support entry of summary judgment in its favor.
DISCUSSION
I. Standard of Review
The parties have filed cross-motions for summary judgment on the complaint under Rule 56 of the Rules of the United States Court of Federal Claims (RCFC). Summary judgment is appropriate “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” RCFC 56(c). A genuine issue of material fact is one that would change the outcome of the litigation. Anderson v. Liberty Lobby, Inc.,
In the capacity of opposing the moving party’s motion, the non-moving party has the burden of providing sufficient evidence to show that a genuine issue of material fact
The initial burden on the party moving for summary judgment to produce evidence showing the absence of a genuine issue of material fact may be discharged if the moving party can demonstrate that there is an absence of evidence to support the nonmov-ing party’s case. Celotex, All U.S. at 325,
The court addresses the issues and burdens surrounding pending cross-motions for summary judgment. Separate motions for summary judgment from each party are not an admission that no material facts remain at issue. See Massey v. Del Labs., Inc.,
The court addresses both parties’ motions for summary judgment simultaneously as to each issue raised. Defendant requests that this court rule in favor of its motion for summary judgment on the basis that the material facts in this matter are not in dispute. Defendant contends that the court should interpret the contract and rule that as a matter of law, Conner cannot establish a claim for an equitable adjustment. Plaintiff argues that because the contract incorporated a standard changes clause, the contracting officer is required to make an equitable adjustment and modify the contract.
II. Analysis
A. Jurisdictional Threshold
Contract disputes in which the government is a party are resolved under the CDA. The CDA authorizes a contractor to bring an action directly on a claim in this court or to file an appeal with the agency board of contract appeals. 41 U.S.C. §§ 606, 609(a). The CDA requires that a contractor submit its claim to the contracting officer prior to commencing suit. Id. § 605(a). In this instance, Conner submitted a certified claim to
It is important to note that findings of fact made by the contracting officer are neither binding upon the court, nor are they evidence. Wilner v. United States,
B. Standard of Contract Interpretation
Issues of contract interpretation, such as the issues presented by the parties in the matter at hand, raise questions of law that are uniquely appropriate for summary judgment. See Varilease Tech. Group, Inc. v. United States,
Contract interpretation begins with the plain language of the contract. Gould, Inc. v. United States,
If, however, an ambiguity arises when interpreting a contractual provision, the proper interpretation is the reasonable and internally consistent one. See Brunswick Corp.,
An ambiguity may be either patent or latent. A patent ambiguity is considered so obvious as to raise the duty to inquire, whereas a latent ambiguity is not glaring or substantial. See Grumman Data Sys. Corp. v. Dalton,
Keeping in mind the above-stated principles, the court must discern the scope of work under the operable language of the contract and whether there exists any ambiguity under the terms of the contract requirements. In order to conduct this analysis, the court will rely, for the most part, on the relationship of the parties established in writing. The court will examine the relevant contract documents which contain the parties’ respective obligations. See SIPCO Services,
The government argues that the terms of the contract unambiguously required Conner to replace the existing diffusers and grilles and connect the new ones to the HVAC system. In that regard, the government argues that any additional expenditure made by Conner to successfully connect the new diffusers and grilles to the HVAC system should be borne by plaintiff. Conner, on the other hand, does not deny that it was required to replace and install the new diffusers and grilles. It agrees that this was a required task under the contract. However, Conner proclaims that it was required to undertake extensive demolition of the existing ductwork in order to remove the old diffusers and grilles and connect the new diffusers and grilles to the HVAC system. In that regard, Conner claims that the schedule of neck sizes shown in the contract drawings was not compatible with existing ductwork and, thus, instead of joining new diffusers and grilles to the existing ductwork by means of a duct collar, it was necessary to remove the existing duct and reroute it, requiring demolition of several feet of existing duct, and the installation of new ductwork and new transitions for the diffusers. Conner claims that it is entitled to an equitable adjustment to the contract to compensate it for this extra work.
C. Contract Language
The court turns to the operable contract language. There are a number of clauses that are applicable to this matter. The first of these is the site visit clause contained in
The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigation and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
Site visits may be arranged during normal duty hours by contacting----
FAR 52.236-27.
Second, the parties stipulate that the contract contained the site investigation clause, which states that:
(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost ____ The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site ... as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
(b) The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based upon the information made available by the Government.
FAR 52.236-3.
Third, the contract contained a clause regarding the omissions and misdescriptions of drawings and specifications of the work. The omissions clause states that:
(d) Omissions from the drawings or specifications or the misdescription of details or work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdes-cribed details of the work, but shall be performed as if fully and correctly set forth and described in the drawings and specifications.
FAR 252.236-7001(d).
Fourth, the parties stipulate that the contract contained the differing site conditions clause, which states that:
(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.
(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.
(c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in (a) above for giving written notice may be extended by the Contracting Officer.
(d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.
FAR 52.236-2.
Fifth, the contract also contained the changes clause, which states that:
*668 (d) If any change under this clause causes ' an increase or decrease in the Contractor’s cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing.
FAR 52.243-4. It is under this clause that plaintiff claims entitlement to an equitable adjustment.
In addition to these standard contracting clauses, the contract also specified the required work to be done by the successful bidder. The contract required Conner to the replace the 1' x 1' concealed spline ceiling system and the 2' x 4' existing ceilings with a new 2' x 2' lay-in ceiling tile system. In conjunction with the ceiling replacement by another Conner subcontractor, Phenix had to replace the diffusers and grilles. This requirement was incorporated into the contract through Bid Amendment No. 0002, dated May 16, 1996. The original contract language required the contractor to “verify all supply and return grilles.” Def.’s App. at 53. However, Amendment 0002 deleted this language, and required Conner, in relevant part, to:
Remove all 1' X 1' and 2' X 4' ceiling tiles and replace with new 2' X 2' ceiling tiles. Remove and replace 2' X 2' ceiling tiles as necessary for sprinkler, medical gas and duct installations and/or renovation.
Supply air diffusers and return air grilles in all 1' X 1' and 2' X 4' ceiling grids are to be removed and replaced with new diffusers and grilles. Remove and provide new diffusers and grilles in plaster ceilings where work is being performed above ceilings. See mechanical plate M-8 for schedule. Remove and reinstall diffusers and grilles in 2' X 2' ceiling grids where work is being performed above ceilings. Balance new air terminals.
Def.’s App. at 5.
Plaintiff claims that the Corps breached the contract when the government ordered Conner to perform changed or added work, and when a formal change order for the additional claimed work was never issued. However, in reviewing the aforementioned clauses, the court finds that Conner is not entitled to an equitable adjustment for additional costs incurred in connecting the new diffusers and grilles.
The standard changes clause at the basis of this dispute, as set forth in the FAR, authorizes the contracting officer to pay additional funds to contractors in the form of an equitable adjustment. See FAR 52.243-4(d). The spirit and purpose of an equitable adjustment, such as that sought by plaintiff here, is to benefit the contractor and make it whole for changes ordered by the government. See N. Am. Constr. Corp. v. United States,
In order for this court to accurately ascertain whether the ductwork claimed by Conner triggered the changes clause, the court must first determine the scope of the work required under the contract. In doing this, the court not only looks to the bidding documents, but also at the materials cited in the bidding documents. McCormick Constr. Co. v. United States,
D. Conner’s Site Visit and Inspection of the Work Area
The court comes to this conclusion first, with a review of the site visit clause. The site visit clause states that “offerors or quo-ters are urged and expected to inspect the site where the work will be performed.” FAR 52.236-27. Additionally, the site investigation clause required Conner to acknowledge “that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost ----” FAR 52.236-3. It also required Conner to acknowledge “that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site ... as well as from the drawings and specifications made a part of this contract.” Id. The site investigation clause released the government from liability, stating that “[a]ny failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.” Id. Lastly, “the Government assumes no responsibility for any conclusions or interpretations made by the Contractor based upon the information available.” Id.
Defendant argues that “Conner and its potential subcontractors were not precluded from investigating conditions above the ceiling which may have impacted their assessment of the difficulty in the removal and replacement of diffusers and grilles.” Def.’s Findings of Fact 1120. In addition, defendant claims that Conner’s pre-bid visits were not just limited to above-ceiling inspections. Id. In other words, defendant’s stance is that Conner had ample opportunity to make prebid inspections of the work site and that an “investigation of the ceiling areas should have revealed that the diffusers and grilles to be replaced were connected to the main horizontal ductwork with fabricated ‘hard’ duct-work rather than flexible duct, which was not in use at the time the building was originally constructed.” Id. ¶ 21.
Conner, on the other hand, maintains that it conducted a reasonable site investigation, which was performed by Conner’s president, Donald Conner, and its subcontractor, Phe-nix. However, despite the site investigation, Conner claims that most of the ceilings were of a locked-in-plaee concealed spline design, and the space above the ceiling was inaccessible at the time of the site investigations. Conner claims that it was able to look into some access doors, but the conditions that are at the heart of this dispute could not be seen from this limited access. Conner claims that it did not observe any conditions that led it to believe that there was any significant work to be performed above and beyond that specifically shown in the contract drawings and specifications. Because of the inaccessibility of the work area, Conner asserts that it could not make an accurate evaluation of the scope of work that needed to be accomplished.
According to Conner, the above-ceiling conditions were dark and obscured by electrical wires, making it hazardous to view the work conditions. When asked whether the conditions that he observed had given him pause for concern about reconnections having to be made in that type of space, Mr. Connor responded:
A. No.
Q. Why not?
A. I didn’t see duct. I saw wire. I saw piping.
A. I don’t recall doing that.
Def.’s Supp.App. at 194, p. 78.
Similarly, Phenix, too, claims that it was unable to access above the ceilings to see the existing conditions before beginning work. More specifically, it maintains that during the bidding period, “all the construction areas were occupied, and above-ceiling access for inspection was very limited.” Def.’s App. at 105. At his deposition, Mr. Charles Turner, the owner of Phenix, stated that despite the presence of access panels in the ceilings, his project superintendent was unable to view the area above the ceiling because “all the pipes and duct just completely fill those, that void area between, above the ceiling.” Def.’s SuppApp. at 166, p. 44. Consequently, Phenix originally maintained that it was required to rely on its “previous knowledge” of the conditions above the Hospital ceiling, which Phenix states led it to believe that the hook-up of diffusers and grilles would be only a minor effort involving a small flexible duct connection.
Q. Did you give Mr. Ashmore, or do you give your superintendents any general instructions or are they supposed to follow any company procedure or manual when they perform a site visit?
A. I told them to go out because I wanted to see how the grilles were connected.
Q. And so that was a concern of yours? A. Correct.
Q. And what did he report back to you?
A. He reported that the ceiling was so full of pipes and other things that he couldn’t see up there.
Q. Well, didn’t that give you reason for concern, as far as whether you should submit a bid?
A. Not particularly, no.
Q. Why not?
A. I figured the A & E had already solved those problems.
Q. When you said that they had solved the problems, why did you think the A & E had solved those problems?
A. They gave us directions on the plan how to do the work, and since we couldn’t get up to see it, we followed those directions.
Q. When you say they gave you directions, what directions are you recollecting right now that they gave you on how to perform the work?
A. I recollect that they said to remove the grille and registers and connect back to the existing duct with a collar.
Q. So in your mind, you thought it was an exact take-it-off, put-it-on type project?
A. Correct.
Def.’s Supp.App. at 161-62, pp. 25-26.
Contrary to the presumptions and suppositions made by Mr. Turner, when Phenix began to remove the existing diffusers and grilles, it found that those units were not connected to the main duct system by flexible connectors, but rather each diffuser and grille was hard-piped to the main duct. In further variance from Mr. Turner’s assumptions, the project was not “an exact take-it-off, put-it-on type project” since the plans and specifications called for changes in location for placement of the diffusers and grilles in the new ceiling. Mr. Turner has acknowledged that he was unaware of these contract requirements when formulating Phenix’s bid estimate but would have been aware of them had he reviewed all of the pertinent plans and specifications.
Under the site investigation clause, Conner is charged with the knowledge available at the pre-bid site inspection. “It is well settled that a contractor is charged with knowledge of the conditions that a prebid site visit would have revealed.” H.B. Mac, Inc. v. United States,
A contractor is held accountable to discover and pursue indications which would put a reasonable and prudent contractor on notice of conditions different than those indicated in contract drawings. Weeks Dredging & Contracting, Inc. v. United States,
It is the rule that a contractor who knows or should have known the facts of the conditions at the site is estopped to claim a changed condition. Where he knows or has opportunity to learn the facts, he is unable to prove ... that he was misled by the contract.
Id. But see D & L Constr. Co. v. United States,
In S.T.G. Constr. Co. v. United States,
In Gevyn Constr. Corp. v. United States,
The Gevyn court went on to discuss that the site investigation clause at issue there referred expressly to “information reasonably ascertainable from an inspection of the site.” Id. The court found that plaintiffs president made an extensive visual inspection prior to bid. Id. Furthermore, the court noted that if certain photographs were as important to a proper interpretation of the drawings as the government claimed, they should have been made a part of the contract documents upon which prospective bidders were asked to rely. Id. Accordingly, under these circumstances, the contractor’s failure to review the photographs prior to bidding did not render plaintiffs investigation unreasonable or inadequate.
The same cannot be said, however, in the case at bar. Unlike in Gevyn, where the contractor made a thorough inspection of the premises, it would be wrong to hold the government responsible for Conner’s inability to recognize the extent of the work to be done under the contract, when, despite a stated inability to inspect the work site, the contractor bid on the project, without raising any pre-bid concerns or questions to the Corps. Bidders were given authorization to inspect the work site as necessary, including inspecting the above-ceiling areas. It is undisputed that bidders were free to inspect the above-ceiling areas by use of the access panels located throughout the Hospital. Conner never sought clarification from the Corps regarding its inability to see above-ceiling conditions prior to submitting its bid. Instead, Conner relied on its subcontractor, Phenix, which not only also failed to raise the issue of inaccessibility of the above-ceiling conditions, but also neglected to review the two sets of contract drawings that indicated the new locations for the diffusers and grilles which would have increased Phenix’s pre-bid estimate of the diffuser and grille reconnection work costs.
The contract incorporated two sets of drawings, the first of which indicated the existing ceiling plan prior to demolition, and a second set of drawings that showed bidders the planned ceiling. These drawings informed the bidders that the new diffusers and grilles would be located in new positions in the ceiling and that the contractor would be responsible for reconnecting the new diffusers and grilles to the existing HVAC system. The court agrees with defendant that a review of these drawings should have placed a reasonable contractor on notice that the new diffusers and grilles were to be placed in different locations than the replaced diffusers and grilles and, that therefore, they could not be simply reconnected in the same exact locations as they had been in the replaced ceilings. This is especially true in light of the fact that the contract documents did not specify the manner of re-installing the new or existing diffusers and grilles and these same documents did not indicate what the existing conditions were above the ceiling. Conner’s interpretation of the contract documents was that new diffusers and grilles were intended to have the same air flow as the old diffusers and grilles. Contract Drawing M-8, Details and Schedules — Mechanical, listed the neck sizes at the interface between the existing ductwork and the diffusers and grilles. Conner mistakenly believed that the schedule of neck sizes would be compatible with the existing ductwork since it erroneously assumed the change in diffusers and grilles was intended to be only cosmetic or there would have been a change in air flow shown in the design. However, as with the case of the above-ceiling conditions, Conner and Phenix should have verified this point before submitting the bid. Conner did not fulfill its duty to inquire until after bid award and complications were encountered.
Conner and Phenix should have raised the issue of their inability to see the above-ceiling conditions during their site inspections prior to plaintiff’s bid submission. Plaintiff and its subcontractor were obliged to have taken into account: (1) the absence of any bid document detailing the existing conditions above-ceiling; (2) the inaccessibility of a clear view of those site conditions; and finally (3) the site investigation requirements set forth in the bid documents. These three factors, in conjunction, should have served to put both the contractor and its subcontractor on notice that each obviously lacked sufficient information to formulate a comprehensive bid. Clearly, a potential bidder needed to know the above-ceiling conditions in order to formulate its bid. Where bid documents fail to supply this information, but instead, require a site inspection, an inability to perform that site inspection (through no fault of the bidder) creates a glaring inconsistency. Conner was therefore obliged to have made further inquiry with the Corps to bring this contradictory and ambiguous situation to the attention of government officials who would have then been put on notice that plaintiff lacked information necessary to formulate its bid with respect to site conditions affecting the amount of work and materials necessary to comply with contract requirements.
This duty to inquire into a patent ambiguity, such as the one present in this case, “was established to prevent contractors from taking advantage of the government, protect other bidders by assuring that all bidders bid on the same specifications, and materially aid the administration of government contracts by requiring that ambiguities be raised before the contract is bid, thus avoiding costly litigation after the fact.” See Community Heating,
In SIPCO Services, this court found that the absence of specific language regarding how inaccessible areas were to be treated raised a patent ambiguity because it would have been obvious to the reasonably prudent contractor that the system specified would not successfully deal with the inaccessible areas.
E. Conner’s Obligation under the Contract
Under the terms of the contract, Conner had an unambiguous duty to reconnect the diffusers and grilles to the existing HVAC system at specified locations which were depicted in the contract drawings. The government notes that “the sole dispute here is whether Conner was required by its contract to reconnect the newly installed D & Gs to the HVAC system at locations that were different than the location of the replaced D & Gs, making the D & Gs an operational component of the HVAC system. This dispute simply requires the [c]ourt to interpret the terms of the contract.” Def.’s Opp. to Pl.’s Mot. for Summ. J. at 3 (citing BristolrMyers,
Plaintiff argues that in merely requiring existing diffusers and grilles to be removed and replaced, the contract did not require “the demolition and removal of the existing ductwork ... or the design, fabrication and installation of new ductwork associated with the diffusers and grilles.” Compl. 1115. Conner argues that because the contract specifies no particular method for reconnecting the diffusers and grilles to the existing HVAC system, Phenix was required to perform work which was separate and apart from the contract’s requirement that the new diffusers and grilles be reconnected to the HVAC system. According to plaintiff, its work in demolishing and modifying the duct-work above-ceiling during performance compelled Phenix to incur additional expenses above the contract price, entitling Conner to an equitable adjustment under the CDA.
Conner, however, ignores the plain language of the contract, which specifically requires the successful bidder to “reinstall new diffusers and grilles” in plaster ceilings. Although the contract is silent as to how exactly this was to be accomplished, it is clear that the successful bidder was required to reconnect the new diffusers and grilles to the existing HVAC system in order to make the system operable after the old diffusers and grilles were removed. This was the clear intent and purpose of the contract. The Federal Circuit, in that regard, has held that in resolving disputes which involve contract interpretation, courts must begin with an examination of the plain language of the contract. M.A. Mortenson,
In R.B. Wright Constr. Co. v. United States,
In the case at bar, the intent of the contract was to replace the old diffusers and grilles and connect the new diffusers and grilles to the HVAC system at specified locations. In other words, the government ultimately was to have an operational HVAC system. The operable contract language highlights this fact. Amendment 0002 requires the successful bidder to:
Supply air diffusers and return air grilles in all 1' X 1' and 2' X 4' ceiling grids are to be removed and replaced with new diffusers and grilles. Remove and provide new diffusers and grilles in plaster ceilings where work is being performed above ceilings. See mechanical plate M-8 for schedule. Remove and reinstall diffusers and grilles in 2' X 2' ceiling grids where work is being performed above ceilings. Balance new air terminals.
Def.’s App. at 5. The contract clearly and unambiguously indicates that the old diffusers and grilles were to be replaced with new ones and that they were to be reconnected to the HVAC system.
The disclaimer in the omissions clause lends further support to the government’s position. The omissions clause specifically states that “[ojmissions from the drawings or specifications or the misdescription of details or work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work, but shall be performed as if fully and correctly set forth and described in the drawings and specifications.” FAR 252.236-7001(d). The clause cautions bidders that information contained in the contract documents may not accurately depict encountered conditions. See Mega Constr. Co. v. United States,
F. Plaintiffs Changed Condition Argument
Lastly, contrary to plaintiffs argument otherwise, the contract’s changes clause is simply inapplicable. The changes clause is invoked when the contracting officer decides to expand the limits of work. Thermocor,
Furthermore, no constructive change can be found under the facts herein. “A constructive change generally arises where the Government, without more, expressly or impliedly orders the contractor to perform work that is not specified in the contract documents.” Lathan Co. v. United States,
There are two basic components to the constructive change doctrine — the change component and the order/fault component. Id. at 678 (citing Al Johnson Constr. Co. v. United States,
To recover under the changes clause of the contract, based on a constructive change for work beyond that required by the contract, it must be clear that:
[E]ach of the other elements of the standard “Changes” or “Extras” clause has been present — the contracting officer has the contractual authority unilaterally to alter the contractor’s duties under the agreement; the contractor’s performance requirements are enlarged; and the additional work is not volunteered but results from a direction of the Government’s officer.
Len Co.,
In this instance, the contracting officer, the person with authority to modify the contract based on a change in the work, did not order the additional work to be done. Of even greater importance is the fact that, as previously discussed in detail, the disputed work performed by Conner was not “additional” work, but rather was work required under the contract. See discussion, supra. Accordingly, the court cannot find in favor of an equitable adjustment based on the changes clause, and the court must grant defendant’s motion for summary judgment on this issue.
G. Plaintiffs Differing Site Conditions Claim
The parties stipulate that the contract incorporated by reference the differing site conditions clause, as found in FAR 52.236-2(a). This clause provides that when a con
(a) The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer in writing of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.
FAR 52.236-2(a).
Plaintiff argues that the contract affirmatively indicated site conditions that were materially different from unforeseeable conditions actually encountered, and that Conner acted reasonably in interpreting and relying on the contract documents. Plaintiff claims that the conditions encountered were unforeseeable conditions that led to the excess costs accrued in the demolition of the old ductwork and in the design, fabrication and installation of the new ductwork associated with the diffusers and grilles involved in this dispute. Therefore, the conditions above-ceiling constituted a differing site condition for which Conner claims it should be compensated.
Prior to addressing the substantive issue as to whether there existed a differing site condition entitling plaintiff to an equitable adjustment, the court must first address whether plaintiff may raise a differing site condition claim given that it failed to plead such claim in its complaint. Plaintiff asserts a claim for differing site conditions in its Response to Defendant’s Motion for Summary Judgment and Cross-Motion for Summary Judgment. Defendant argues that plaintiff failed to plead differing site conditions as a claim in the complaint, and therefore should be precluded from asserting it in plaintiffs cross-motion for summary judgment.
Although plaintiff should have sought to amend its complaint under RCFC 15(a), the court finds that plaintiffs allegations, as pled in the complaint, put defendant on sufficient notice of a potential differing site conditions claim. See, e.g., Intern’l Fid. Ins. Co. v. United States,
Despite having the opportunity to raise its claim, the court finds that plaintiff has not substantively established the elements for asserting a cause of action for differing site conditions. The purpose of the differing site conditions clause is to allow contractors to submit more accurate bids by eliminating the need for contractors to inflate their bids to account for contingencies that may not occur. See H.B. Mac,
In Stuyvesant Dredging Co. v. United States,
To prevail on a claim for differing site conditions, the contractor must prove, by a preponderance of the evidence, “that the conditions ‘indicated’ in the contract differ materially from those it encounters during performance.” P.J. Maffei,732 F.2d at 916 (citing Arundel Corp. v. United States, [207 Ct.Cl. 84 ,]515 F.2d 1116 , 1128 (Ct.C1.1975)). The conditions actually encountered must have been reasonably unforeseeable based on all the information available to the contractor at the time of bidding. United Contractors v. United States, [177 Ct.Cl. 151 ,]368 F.2d 585 , 594 (Ct.C1.1966). The contractor also must show that it reasonably relied upon its interpretation of the contract and contract-related documents and that it was damaged as a result of the material variation between the expected and the encountered conditions. Sanders Constr. Co. v. United States, [220 Ct.Cl. 639 ,]618 F.2d 121 (Ct.Cl.1979).
Id. “A material discrepancy between what is indicated in the contract documents and what is encountered at the site can result in unanticipated costs to the contractor, for which the government would be liable.” Sergent Mech. Sys., Inc. v. United States,
A contractor cannot be eligible for an equitable adjustment for a Type I differing site condition unless the contract indicated what that condition would be through reasonably plain or positive indications. See P.J. Maffei,
As defendant correctly notes, there were no affirmative representations made by the Corps in the bid documents which described the above-ceiling conditions at the Hospital. Plaintiff has pointed to no specification or provision in the bid documents which it contends sets forth any such representations. In fact, in letters written to plaintiff’s president, Connor’s subcontractor, Phenix, observed:
The contract documents do not specify the manner of reinstallation of the new or existing diffusers and grilles, nor the manner of connecting these units to the existing duct system. There are no details to indicate what the existing conditions were above the ceiling, and we were unable to get above the ceilings to see the existing conditions before beginning work.
Def.’s App. at 90.
Phenix’s letters went on to state that “the condition of the ceiling ... was not even mentioned by the A/E in the plans or specifications, nor realized by us during our site visit during bids----” Id. at 91. In view of the fact that the disputed contract did not reflect what conditions a prospective contractor should anticipate encountering in this case, Conner cannot demonstrate that it was damaged as a result of a material variation between above-ceiling conditions indicated in the contract and those it actually encountered. Therefore, plaintiff has failed to establish one of the required elements necessary to prove a Type I differing site condition. See H.B. Mac,
Additionally, the court finds that the conditions ultimately encountered were reasonably foreseeable. For a Type I claim, “the underlying issue ... is whether the contractor reasonably could have anticipated the conditions encountered from a knowledgeable interpretation of the contract documents, its inspection of the site, and its general experience as a contractor.” John Massman Constr. Co. v. United States,
In sum, the court finds it clear that plaintiffs differing site conditions claim is based not on any clear contract indications, but upon plaintiff’s factual assumptions. Furthermore, the court finds that the site conditions of which plaintiff complains were foreseeable. The court grants defendant’s motion for summary judgment with respect to plaintiffs differing site conditions claim.
H. Plaintiffs Defective Drawings Claim
Conner argues that the contract’s plans and specifications were defective because the contract drawings did not inform the bidders
Defendant argues that Conner’s interpretation of the contract — that it was not required to demolish or remove and modify the existing ductwork in order to reconnect the new diffusers and grilles to the HVAC system — renders the requirement that new diffusers and grilles be installed meaningless. Defendant contends that the contract unambiguously required the successful bidder to reconnect the diffusers and grilles to the HVAC system. Defendant further alleges that an evaluation of the contract drawings confirms that those drawings were not defective. “Rather, the drawings informed bidders that the new D & Gs had to be placed in different locations in the ceiling than where the replaced D & Gs, which were scheduled for demolition, had previously been located.” Def.’s Opp. to Pl.’s Mot. for Summ. J. at 5-6 (citing Def.’s App. at 196-280). The government argues that had Conner reviewed the terms of the contract and the drawings prior to submitting its bid, the additional costs incurred in connecting the new diffusers and grilles would have been foreseeable.
In Robins Maint., Inc. v. United States,
In Comtrol, the Federal Circuit found that because Comtrol had failed to review a report incorporated into the contract, it had failed to review all of the contract documents concerning subsurface conditions, and therefore, it could not show that it reasonably relied on the report’s description of soil and water conditions.
It is undisputed that Comtrol failed to inquire about the relocation of the ... pipeline or the actual location of the utility corridor before bidding. We agree with the Court of Federal Claims that the Pipeline Drawing and the other contract drawings placed Comtrol on notice that a fuel pipeline might exist at or near the construction site, and that Comtrol had a duty to seek clarification of this ambiguity. Therefore, Comtrol cannot establish a differing site conditions claim or defective specifications claim relating to the pipeline because it cannot establish that it acted as a reasonably prudent contractor in interpreting the contract documents.
Id.
In this instance the contract incorporated two sets of drawings — one set of demolition drawings indicating the existing ceiling plan prior to demolition and a second set of drawings that informed bidders of the planned ceiling. The drawings informed bidders that the new diffusers and grilles would be located in new positions in the ceiling and that the successful contractor would be responsible for reconnecting those diffusers and grilles to the existing HVAC system. Defendant argues that based upon a reasonable review of these drawings, bidders should have known that the new diffusers and grilles would be placed in different locations and that they could not simply reconnect the new diffusers and grilles to the HVAC system' in the same exact locations as the diffusers and grilles had been in the replaced ceiling.
During his deposition, the president of Phenix, Charles Turner, testified that the mechanical work for Conner’s bid was based upon the mistaken assumption that the new diffusers and grilles would be placed in exactly the same location as the replaced diffusers and grilles. Mr. Turner further acknowledged that he neglected to review the two sets of contract drawings that indicated the new locations for the diffusers and grilles prior to the submission of Conner’s bid, and that he was alarmed by the crowded nature of the above-ceiling conditions when Phenix inspected the site.
Mr. Turner acknowledged that had he inspected the two aforementioned drawings prior to estimating the mechanical work, he would have known that the new diffusers and grilles had to be placed in different locations in the ceiling than the replaced diffusers and grilles. Id. at 171, pp. 62-63; 172-73, pp. 69-70. Mr. Turner further confirmed that Conner and Phenix understood that they were responsible for making the newly installed diffusers and grilles operational, but had submitted their bid to the Corps under the mistaken assumption that the new diffusers and grilles would simply be placed in the same, exact location as the replaced diffusers and grilles. Id. at 169-73.
Similarly, Conner’s president, Donald Conner stated in deposition testimony that he too failed to compare two drawings showing the locations of the old diffusers and grilles and the new diffusers and grilles at the time of the bid. Id at 192, p. 73. Although he testified that he reviewed some mechanical notes regarding the diffusers and grilles, and that from this, his understanding was that the successful bidder would have to remove the diffusers and grilles, replace them, and reconnect the new ones, id. at 186, pp. 46-47, he did not review the two drawings that would have shown where the new connections could have been made. Id. at 192, pp. 72-73. In light of the fact that neither plaintiff nor
As a further impediment to plaintiffs argument, the court notes that simply because the contract documents did not specify exactly how Conner was to make an operational system, that fact does not render the contract drawings and specifications defective. An omission regarding the methodology of the reconnection of the diffusers and grilles to the ductwork does not invite a claim of defective drawings, as plaintiff would like the court to decree. The general rule with regard to the government’s liability for defective specifications is that, if the specifications are strictly observed, the government implicitly warrants that satisfactory performance will result. See Universal Contracting and Brick Pointing Co. v. United States,
Performance type specifications set forth an objective or standard to be achieved, and the successful bidder is expected to exercise his ingenuity in achieving that objective or standard of performance____ Design specifications are explicit, unquestionable specifications which tell the contractor exactly how the contract is to be performed and no deviation therefrom is possible.
Utility Contractors, Inc. v. United States,
As was the case in Universal Contracting,
In this instance, the aspect of the contract involving the replacement of diffusers and grilles clearly reflects performance specifications and Conner has failed to demonstrate that it lacked discretion in performing the contract in order to warrant a finding of defective specifications. The contract drawings showed the layout of the ductwork and the sites of the old diffusers and grilles and where the new diffusers and grilles were to be placed along with a requirement that the system was to be made operable. This lack of detail indicates a performance specification because the contract drawings were
I. Plaintiff’s Impossibility Claim
Conner asserts a claim for impossibility of performance, contending that it was impossible for Conner to complete the work as contracted. In support of this argument, Conner asserts that the original specified work could not be performed since the specifications and drawings initially required only cosmetic changes with the existing airflow unchanged. “The extensive alterations to the duct[]work changed the airflow, and Conner ... could only complete the work with changes to the duct[]work that were approved by the Army. It was impossible for Conner ... to complete the work as provided for in the Construction Contract Specifications and Drawings without a design modification.” Pl.’s Resp. to Def.’s Mot. to Dismiss at 32.
Pursuant to the doctrine of impossibility, a contractor’s performance may be excused when a condition that is part of the contract becomes impossible to perform. Natus Corp. v. United States,
Based on a reading of the allegations, as pled, and in light of the fact that Conner did, in fact, perform the contract, it appears that Conner’s impossibility claim is actually a claim for commercial impracticability.
A contract is said to be commercially impracticable when, “because of unforeseen events, ‘it can be performed only at an exces
Conner acknowledges that it was able to ultimately perform the reconnection work. “After Conner ... began demolition of the locked-in-place concealed spline ceilings, Conner ... and Phenix observed that there was not so sufficient room between the horizontal run of the existing ductwork and the specified location for the new ceiling to permit the use of the existing ducts without design modifications.” Pl.’s Prop. Findings of Fact ¶ 138. “As a result of such problems, instead of joining the new diffusers and grilles to the existing ductwork ... it was generally necessary to remove the existing duct and reroute it around local interferences.” Id. If 140. Once Conner reported the above-ceiling conditions to the Army in a February 11, 1997 meeting, Phenix suggested a way to modify the design, together with an itemized unit price proposal. The Army and Conner came to an agreement as to a solution to the problem and Conner furnished the Army with a proposal and budget for the additional work. Much of the duct-work was completed by the time the claim was filed.
These facts do not establish a claim for commercial impracticability. Although the reconnection work may have been more expensive for Conner, the cost overrun was not so significantly disparate so as to warrant a finding of impracticability. See Raytheon,
J. Plaintiffs Superior Knowledge Claim
Plaintiff alleges that the Army had superi- or knowledge with respect to the site problem in that, among other things, the Army instructed Conner’s architect not to perform an above-ceiling inspection and failed to disclose this fact to Conner so that it could either account for this risk in its bid or choose not to bid the work at all. “Here, the Army had superior knowledge that, among other things, the Army had ‘instructed’ the architect not to perform an above-ceiling inspection and failed to disclose this to Conner ... so that it could either account for this risk in its bid or chose not to bid on the work at all.” Pl.’s Resp. to Def.’s Mot. to Dismiss at 31.
Defendant counters that Conner cannot maintain a superior knowledge claim because Phenix had prior knowledge of the above-ceiling conditions in the Hospital. “Its general experience, combined with its subcontractor’s particular knowledge of the hospital facilities, provided Conner the basis upon which it should have anticipated the ‘difficulties’ it eventually encountered in performance.” Def.’s Mot. for Summ. J. at 18. Defendant contends that:
Rather than making an adequate site investigation and requesting further clarification from the Corps regarding the placement of the new D & Gs, Conner proceeded upon the mistaken assumption that the conditions above-ceiling would merely require “minor effort involving a small flexible duct,” Def.’s App. at 90-92, to reconnect the new D & Gs. As a matter of law, because the work encountered in reconnecting the D & Gs was readily foreseeable to Conner from a reasonable site inspection and/or from a reasonable review of the contract drawings, Conner cannot establish that ... it was misled regarding the work required.
Def.’s Opp. to Pl.’s Mot. for Summ. J. at 15.
It is well established that when the government possesses material informa
There are four requirements for establishing when the government has failed in its duty to disclose superior knowledge. First, the contractor undertakes to perform without vital knowledge of a fact that affects performance costs or direction. Second, the government was aware that the contractor had no knowledge of and had no reason to obtain such information. Third, the contract specification supplied either misled the contractor, or did not put it on notice to inquire. Fourth, the government failed to provide the relevant information. See Giesler v. United States,
Additionally, a bare withholding of information is not enough to make a case for superior knowledge. See Leal v. United States,
In Sergent Mechanical, there was clear evidence that the government withheld vital and material information about various site restrictions in the work area up until the day before work was to begin.
Conversely, in this instance, there was no glaring withholding of information by the government as was the case in Sergent Mechanical. With respect to the first and second prongs of the superior knowledge test, at best, Conner and the government had the same knowledge of the above-ceiling conditions, but the government did not have superior knowledge. As plaintiff has asserted throughout its submissions to the court, there were no details in the contract documents that suggested how the new diffusers and grilles were to be attached or installed. Both parties were made aware of a site investigation conducted by Southeastern Architects Engineers Planners, Inc. (hereinafter A/E), which was hired by Stevens and Wilkinson of Georgia, Inc.
Furthermore, despite whatever knowledge the Corps may have possessed, Conner, as explained in Section II.D, supra, was on notice to inquire as to the above-ceiling conditions. Prospective bidders on the project were urged to make a site visit to investigate the conditions of the existing hospital that would affect the work required to be performed. The site visit clause stated that “offerors and quoters are urged and expected to inspect the site where work will be performed.” FAR 52.236-27. Similarly, the site investigation clause required Conner to acknowledge that it took “steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost____” FAR 52.236-3. Conner was also required to acknowledge “that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site____” Id. There is no indication that the government withheld facts from Conner given that both Conner and Phenix had every opportunity to inspect the premises and review the contract documents for themselves. Conner did not seek clarification from the Corps with respect to the above-ceiling conditions prior to submitting the bid. Without utilizing the available means to discern the actual conditions within which the work was to be performed, the court finds that plaintiff was not misled by the government. Rather, plaintiff simply exercised misjudgment on its part when it relied on its own and its subcontractor’s less-than-thorough review of the contract materials and did not inquire with the Corps about the above-ceiling conditions.
As previously stated, Conner engaged in three site visits prior to submitting its bid. Conner’s president stated in deposition testimony that he was able to view parts of the area above the ceiling via some access panels,
K. Plaintiffs Mistake Claim
Plaintiff claims that there exists either a unilateral or mutual mistake as to the degree of effort required in removing and replacing the air system diffusers and grilles. In particular, Conner claims that the Corps “failed to call to its attention a potential mistake in its bid related to the diffuser/grille work.” Compl. If 68. Defendant asserts that Conner has failed to identify any mistake in Conner’s bid.
Parties to a contract are generally bound by its terms. See Giesler,
In the case of mutual mistakes, courts have resorted to reformation to conform the words of a contract to those the parties actually intended. Bromley Contracting Co. v. United States,
Generally, if the government suspects that a mistake in the contractor’s bid has been made, it will request a verification of the bid under the federal procurement regulations. Carrier Corp. v. United States,
Where a mistake in bid is not alleged until after the contract is awarded, such as in this case, plaintiff may recover only if defendant’s responsible officials knew or should have known of the mistake at the time the bid was accepted. Wender Presses,
The Aydin court noted that the test for constructive notice in cases dealing with mistaken bids is whether under all the facts and circumstances of the case “ ‘there were any factors which reasonably should have raised the presumption of error in the mind of the contracting officer.’ ” Id. (citing Chernick v. United States,
In this instance, the government did not request verification of Conner’s bid since plaintiff first raised the mistake in bid issue after the contract had been awarded and work had commenced. Accordingly, the court must inquire as to whether Conner “misread” the specification when it submitted its bid since there is no allegation that Conner committed a clerical or arithmetical error when it submitted its bid. Giesler,
Conner has also failed to offer evidence that the government knew or should have known of the purported mistake. It is true that the government has a general duty to examine bids for mistakes. Giesler,
Nothing in Conner’s bid materials gave rise to a suspicion of a mistake in its bid. Conner did not adequately inquire as to the above-ceiling conditions and did not avail itself of the full information available to it. Conner’s mistake-in-bid claim must be rejected as a mistake in its own business judgment. Liebherr Crane,
L. Plaintiff’s Estoppel Claim
Plaintiff claims that the government should be estopped from withdrawing its approval of the changed work since it would be unfair to permit the government to enforce its rights after Conner relied upon the government’s approval to conduct the additional ductwork. Allegedly, because the Army previously agreed that the ductwork was additional, extra work, Conner claims that it should be estopped from now asserting that the original work to be done was not changed.
It is unclear from plaintiffs allegations whether Conner is asserting a claim for promissory estoppel or equitable estoppel. Promissory estoppel involves a “promise which the promisor should reasonably expect to induce action or forbearance on the part of the promisee.” LaMirage, Inc. v. United States,
Equitable estoppel is used to bar a party from raising a defense or objection it otherwise would have, or from instituting an action which it is entitled to institute. La-Mirage,
Although the Supreme Court has not adopted a per se rule prohibiting the application of equitable estoppel against the government under any circumstances, it has made it clear that “the government may not be estopped on the same terms as any other litigant.” Heckler,467 U.S. at 60 [,104 S.Ct. 2218 ]. In particular, the [Supreme] Court has suggested that if equitable estoppel is available at all against*691 the government some form of affirmative misconduct must be shown in addition to the traditional requirements of estop-pel____While the Supreme Court has not squarely held that affirmative misconduct is a prerequisite for invoking equitable es-toppel against the government, [the Federal Circuit] has done so ..., as has every other court of appeals.
Id. (emphasis added); see also Rumsfeld v. United Techs. Corp.,
The doctrine of equitable estoppel bars a party from raising a defense or an objection it otherwise would have. Biagioli,
Conner’s equitable estoppel claim fails because the government person who purportedly agreed to Conner’s proposed price modification for the additional duct-work, Ken Bright, did not possess the requisite authority to bind the government. See Emeco Industries,
Despite Conner’s urgings to the contrary, the Army clearly stated in July 1997 that there would be no modification and that Conner needed to submit its request for a contracting officer’s final decision. Although Conner believed that an “understanding” had been reached between Conner and the government that Conner would be paid extra for the modifications needed, as a result of meetings and negotiations that occurred in February and March 1997, no modification was actually issued and the proposed agreement was never reduced to a writing. At best, there was merely a verbal agreement that Conner would be paid an extra sum for making the additional connections. After Conner began demolition of the lock-in-place concealed spline ceilings, both Conner and Phe-nix observed that design modifications had to be made in order to connect the diffusers and grilles to the existing ductwork. Conner first reported these conditions to the Army on February 11, 1997. On February 14, 1997, Conner forwarded to the Army a letter written by Phenix which included a sketch and unit price proposal to undergo the work Conner insisted was necessary to complete the Contract. On February 18, 1997, the Army received this additional information from Conner and Conner’s proposal to modify the existing ductwork. On March 4, 1997, the Army advised Conner that the “connection between the new diffuser and the existing duet are considered to be part of the subject contract and a modification shall not be forthcoming for this portion of the work.” Pl.’s Findings of Fact H152 (citing PL’s App. 74 at 1110). It was at this point, less than a month after the D & G issue was first raised by Conner to the government, that the government expressed to Conner that there would be no change to the contract based on the alleged additional work. The Army stated that:
[A] pre-change agreement on unit prices for various types of unusual work was sought by the [government. However, this was for future application in the event some anticipated or unusual circumstance occurred that was not part of the contract requirements. In this case, rather than just complaining about just a few rare instances, Conner sought recovery for over 1400 instances. In other words, for almost every diffuser and grille replacement. The [gjovemment never agreed with Conner that the installation of the replacement diffusers and grills, or duct modification in the manner Conner proposed, was outside the scope the contract requirements.
Def.’s App. at 148.
Based on these circumstances, the court does not agree that Conner was misled by the government. The facts do not show that the contracting officer intentionally deceived Conner. See DeMarco Durzo Dev. Co. v. United States,
CONCLUSION
For the following reasons, it is hereby ORDERED that:
(1) Defendant’s Motion for Summary Judgment, filed September 10, 2002, is GRANTED;
(2) Plaintiffs Cross-Motion for Summary Judgment, filed October 11, 2002, is DENIED;
(3) The Clerk’s office is DIRECTED to ENTER judgment for defendant, dismissing plaintiffs complaint with prejudice; and
(4) Each party shall bear its own costs.
Notes
. The specific language of Amendment 0002 is as follows:
Remove all T X 1' and 2' X 4' ceiling tiles and replace with new 2' X 2' ceiling tiles. Remove and replace 2' X 2' ceiling tiles as necessary for sprinkler, medical gas and duct installations and/or renovation.
Supply air diffusers and return air grilles in all 1' X 1' and 2' X 4' ceiling grids are to be removed and replaced with new diffusers and grilles. Remove and provide new diffusers and grilles in plaster ceilings where work is being performed above ceilings. See mechanical plate M-8 for schedule. Remove and reinstall diffusers and grilles in 2' X 2' ceiling grids where work is being performed above ceilings. Balance new air terminals.
Def.’s App. at 5.
. The pertinent contract drawings are as follows: (1) Drawings A-8 through A-25 of the "Partial Reflected Ceiling Plans” depicting the T x T ceiling that was required to be removed and the approximate location of the old diffusers, see Def.'s App. at 29-50; (2) Drawings A-27 through A-45 of the "Partial Reflected Ceiling Plans” showing the new work requirement in the same part of the Hospital as shown on drawings A-8 through A-25, see id.; (3) Drawings X-8 and X-9, the contract "Phasing Plan,” setting forth the phasing required to complete the contract, including the requirement that the “[h]ospital will be in operation during construction,” Def.’s App. 51 at n. 2, the requirement to "[c]ap airtight half of supply air diffusers in work area, and all of return air or exhaust grilles”, Def.’s App. 52 at n. 11, the requirement to ”[r]emove individual supply diffusers and return air registers and cap duct branch connections when ceiling is removed,” id. at n. 12, and the requirement to "[¡Install new diffusers and grilles," id. at n. 13; and (4) Drawing plate M-8, "Details & Schedules — Mechanical,” sheet 77, containing a diffuser and register schedule, Def.’s App. at 53.
. See Specification section 15895, Air Supply and Distribution System for Air-Conditioning System, Part 2, Productions, para. 2.8.7.I.
. See Specification section 15895, Air Supply and Distribution System for Air-Conditioning System, Part 2, Productions, para. 2.8.1.2.
. In preparing to bid upon the mechanical subcontract for the project, Mr. Charles Turner, the owner of Phenix Mechanical Contractors, Inc. (Phenix), Conner's subcontractor, sent Mr. Clyde Ashmore, a Phenix project superintendent, to “check out the area.” Def.’s App. at 159. The extent of the superintendent’s site visit is unclear. Mr. Turner stated that Mr. Ashmore visited the work area, but could not see how the grilles were connected in the ceiling. Def.’s Supp.App. at 161, pp. 25-26; 166, pp. 45-46.
. Pursuant to court order dated December 4, 2004, the parties filed Joint Stipulations of Fact on March 15, 2005.
. The court observes that Mr. Turner’s own statements contradict this contention. Although Mr. Turner made that statement concerning his prior knowledge of the Hospital ceiling conditions in a letter to plaintiff dated November 10, 1997, four years later, during his deposition, Mr. Turner disavowed that either he or anyone in his company would have examined the space above the ceiling at the Hospital on any occasion or for any other contract prior to the contract at issue here. Def.'s Supp.App. at 161, p. 24; 167, pp. 46-47.
. Likewise, Conner's president states that he did not study the pertinent drawings so as to discern that the new grilles were in different locations than the old in the new ceiling: "At the time of
. The court observes that in another statement, however, Mr. Turner asserted that the crowded nature of the above-ceiling conditions did not give him reason for concern because he "figured that A & E had already solved those problems.” Def.'s Supp.App. at 161-62, pp. 25-26.
. It is clear that neither Phenix nor Conner deemed it impossible to perform the additional ductwork necessary to complete the contract. It was simply more expensive. The demolition and redesign of the ductwork was not objectively impossible to perform, rather, the work was merely more extensive than originally planned. This does not constitute a legal impossibility requiring compensation.
. Stevens and Wilkinson was awarded a separate contract regarding the design of the Hospital life safety upgrade. Pl.’s Findings of Fact ¶ 17.
