BRISTOL ASPHALT CO., INC., & another vs. ROCHESTER BITUMINOUS PRODUCTS, INC., & others.
21-P-1135
Appeals Court
April 28, 2023
Plymouth. November 2, 2022. Present: Rubin, Englander, & Hand, JJ.
NOTICE: All slip opinions and orders are subject to formal revision and are superseded by the advance sheets and bound volumes of the Official Reports. If you find a typographical error or other formal error, please notify the Reporter of Decisions, Supreme Judicial Court, John Adams Courthouse, 1 Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-1030; SJCReporter@sjc.state.ma.us
“Anti-SLAPP” Statute. Practice, Civil, Motion to dismiss. Constitutional Law, Right to petition government. Zoning, Site plan approval, Wetlands. Municipal Corporations, Conservation commission. Massachusetts Environmental Policy Act.
Civil action commenced in the Superior Court Department on August 17, 2020.
A special motion to dismiss was heard by Thomas F. McGuire, Jr., J.
Michael S. Rabieh for the defendants.
Brian M. Hurley for the plaintiffs.
HAND, J. This case stems from a decade-long battle between the plaintiffs and the defendants over the plaintiffs’ efforts to build a bituminous concrete plant on property in the town of Rochester‘s (town or Rochester) industrial zoning district. The proposed plant was to be developed adjacent to an existing concrete plant operated by the defendants in the same district.
As we discuss below, the plaintiffs’ amended complaint is based on three petitioning efforts by the defendants to block the plaintiffs’
Background. We summarize the facts drawn from the pleadings and the affidavits in the record before the judge. Benoit v. Frederickson, 454 Mass. 148, 149 (2009).
1. The parties. The plaintiffs are Bristol Asphalt Co., Inc. (Bristol Asphalt), and Edgewood Development Company, LLC (Edgewood) (collectively, Bristol parties). In 2019 Bristol Asphalt was established to assist Edgewood and other related entities in obtaining the necessary permits for the bituminous concrete plant (proposed plant) on behalf of the proposed plant‘s developer, Lorusso Corporation. Bristol Asphalt was also incorporated to construct the permitted plant at a site located at 99 Kings Highway in Rochester (proposed site).
The defendants are Rochester Bituminous Products, Inc. (Rochester Bituminous), and Albert Todesca and Paul Todesca, individually and as trustees of the Todesca Realty Trust (Todesca Trust) (hereinafter, we refer to the defendants collectively as the RBP parties).5 Rochester Bituminous owns and operates an existing bituminous concrete production facility at 83 Kings Highway, the abutting parcel immediately south of the proposed site. Previously, title to that property was held by the Todesca Trust, of which brothers Albert Todesca and Paul Todesca are the trustees. Additionally, at different times Paul Todesca has served as a manager, officer, and director of Rochester Bituminous, while Albert Todesca has served as a “consultant.” Albert Todesca and
2. The petitioning activity. a. Site plan approval. The first category of petitioning activity addressed in the amended complaint concerns the RBP parties’ challenges to the town planning board‘s approval of the site plan.6
The proposed site was located in the industrial district of the town. Under § IV(D)(1) of the town‘s zoning bylaws, as amended May 18, 2009, activities including “[m]anufacturing, industrial or commercial uses including processing, fabrication, assembly and storage of materials” were permitted by right in that district, provided that “no such use [was] permitted which would be detrimental or offensive or tend to reduce property values in the same or adjoining district.” The bylaws required that all new development of the size and cost contemplated by the proposed plant be subject to site plan review and approval by the planning board. See Rochester Bylaws § XVI(1.1), as amended June 9, 2003, and October 24, 2005. In performing the required review for a use available as of right, the planning board‘s discretion was explicitly limited: the bylaws provided that “[t]he Planning Board shall approve an application” if it found that the proposed development conformed with the bylaw, or if conformity could be achieved by compliance with “conditions, limitations and safeguards” imposed by the planning board. See Rochester Bylaws § XVI(1.9)(3)(a), adopted February 27, 2002. The planning board‘s discretion to deny approval of an as of right use was limited to, as relevant here, circumstances in which the plan “[was] so intrusive on the needs of the public in one regulated aspect or another that rejection by the [b]oard would be tenable because no form of reasonable conditions can be devised to satisfy the problem with the plan.” Rochester Bylaws § XVI(1.3)(3), as amended October 24, 2005.
Edgewood applied to the planning board for site plan approval for the facility in November 2010. In May 2011, after nine public
The Todesca Trust, through trustee Paul Todesca, and several abutters and other neighbors of the proposed site, including tenants of the Todesca Trust (abutters), appealed the planning board‘s approval of the site plan to the town‘s zoning board of appeal (ZBA). After a public hearing, the ZBA affirmed the planning board‘s decision. Pursuant to
Trial proceeded on the abutters’ remaining claims, including that the proposed plant was a prohibited use under the zoning bylaws because the truck traffic and other harms associated with its operations would be “detrimental or offensive” and would tend to reduce the property values in the same or adjoining district; and alternatively, even if the proposed plant were a permitted use, that the request for approval of the site plan should be denied because “the [claimed] problem[s] [with the site plan] [were] so intractable that [they] could admit of no reasonable solution.” Prudential Ins. Co. of Am. v. Board of Appeals of Westwood, 23 Mass. App. Ct. 278, 283 (1986).
The Land Court judge first rejected the abutters’ challenge to the proposed plant‘s qualification as a permitted use on the grounds that “there is no evidence that [the] harms [on which the
Both sides introduced evidence about whether the proposed plant‘s operation created new safety risks or was likely to result in traffic congestion on the adjacent roadway. The judge noted, however, that the abutters’ evidence -- their expert‘s testimony about the ability of trucks of a certain size to pass or travel abreast on the driveway of the proposed facility and the possibility that the “queuing” of waiting trucks could extend onto Kings Highway -- was based on “assumed facts provided by the Todescas and not on . . . proposed site conditions.”9 Concluding that (1) the risks predicted by that expert were hypothetical and unlikely to be realized, and (2) any actual traffic concerns could be adequately resolved through the imposition of the planning board‘s reasonable conditions,
see note 7, supra, the Land Court judge rejected the abutters’ arguments10 and, after trial, dismissed their appeal.
Three abutters funded by the Todesca Trust appealed the Land Court judgment to this court. On April 24, 2017, we rejected their
the Land Court judge “that there [was] no evidence [that anticipated increased noise and truck traffic near the abutters’ homes] [were] inherent to the [proposed] facility in particular, ‘as opposed to any other industrial use,’ and that the by-laws do not contemplate prohibiting an industrial use in an industrial district solely because a nearby residential property owner would find it offensive or detrimental.” Id. Finally, we agreed with the Land Court judge that the abutters had produced no evidence to show that the proposed facility would cause property values across the industrial district to decrease, and that the abutters’ argument relied on an incorrect interpretation of the bylaws. See id.
b. Conservation commission. The second category of petitioning activity engaged in by the RBP parties arose from Edgewood‘s request for an extension of an order of conditions issued by the town conservation commission (commission).
In December 2010, a month after it submitted its application for site plan approval, Edgewood filed, pursuant to the Wetlands Protection Act,
On June 26, 2018, Rochester Bituminous and three abutters (wetlands abutters) filed a certiorari action in the Superior
upholding the decision of the conservation commission to approve the extension order.14 See Rochester Bituminous Prods., Inc. v. Conservation Comm‘n of Rochester, 98 Mass. App. Ct. 1118 (2020).
c. MEPA petitions. The final category of petitioning activity to which the amended complaint refers was connected to the RBP parties’ efforts to obtain review of the proposed facility under the Massachusetts Environmental Policy Act,
concluding that the petition did not meet the regulatory requirements for MEPA review. Undeterred, in January 2020, the Todesca Trust again recruited signatures and submitted, through its attorney, a second citizen petition in which it reiterated the same concerns on the same basis. The EOEEA denied the Todesca Trust‘s second fail-safe petition on the grounds that it alleged “virtually identical facts” to the 2018 petition.
3. The present action. On September 2, 2020, the Bristol parties filed a three-count amended complaint in the Superior Court alleging (1) unfair and deceptive acts and practices in the conduct of trade or commerce in violation of
nearly $12 million in lost profits and had incurred hundreds of thousands of dollars in legal fees.
4. The special motion to dismiss. In response to the amended complaint, the RBP parties filed an answer and a special motion to dismiss pursuant to
After a hearing, the motion judge denied the RBP parties’ special motion to dismiss. In a concise written decision, the motion judge correctly applied the analytical framework we discuss in detail below, concluding that, while the Bristol parties’ claims were based solely on the RBP parties’ petitioning activity, the Bristol parties had met their burden of demonstrating that the
Discussion. 1. Overview. ”
To prevail on a special motion to dismiss under
activities.‘” Fustolo v. Hollander, 455 Mass. 861, 865 (2010), quoting Duracraft, 427 Mass. at 167-168.
If the special movants (here, the RBP parties) make that “first stage” showing, the burden then shifts to the nonmovants (here, the Bristol parties) at the second stage of the analysis to defeat the special motion by meeting the requirements of one of two analytical paths that the judge must consider sequentially. See Nyberg, 101 Mass. App. Ct. at 646. The first path tracks the statutory language and requires a showing by the nonmovants (the Bristol parties) establishing “by a preponderance of the evidence that the [special movants (here, the RBP parties)] lacked any reasonable factual support or any arguable basis in law for [their] petitioning activity . . . and that the petitioning activity caused the nonmoving part[ies] ‘actual injury’ -- i.e., that [their] petitioning activity is illegitimate” (quotation and citation omitted). 477 Harrison Ave., LLC v. JACE Boston, LLC, 477 Mass. 162, 168 (2017) (Harrison I), S.C., 483 Mass. 514 (2019) ( Harrison II). The judge does not consider the defendant‘s motivation for engaging in the petitioning activities; “[r]ather, the relevant inquiry is whether the plaintiff has demonstrated that the defendant‘s petitioning activity lack[ed] any objectively reasonable basis.” Harrison I, supra at 173. “Proving that the moving party‘s petitioning activity was . . . a sham presents a ‘high bar.‘”
Blanchard II, 483 Mass. at 204, quoting Blanchard I, 477 Mass. at 156 n.20.
If, and only if, the nonmoving party fails to make the showing required under the first path of this second stage, the judge must then consider the nonmovant‘s showing under the second stage‘s second path announced in Blanchard I. If the judge reaches this level of the analysis, the nonmovants (here, the Bristol parties) are required “to establish, such that the motion judge can conclude with fair assurance, that [their] claim is not a ‘meritless’ SLAPP suit ‘brought primarily to chill the special movant‘s . . . legitimate petitioning activities.‘” Harrison II, 483 Mass. at 518-519, quoting Blanchard I, 477 Mass. at 160.
Here, the motion judge determined that the RBP parties met their burden at the first stage, successfully shifting the burden to the Bristol parties. He also concluded that the Bristol parties, as the nonmovants, prevailed at the second stage by proving by a preponderance of the evidence both that the RBP parties’ petitioning lacked “any reasonable factual support or any arguable basis in law,” Baker, 434 Mass. at 553-554, and that the Bristol parties had suffered resulting
injury.17 We consider de novo the RBP parties’ showing at the first stage, see Reichenbach v. Haydock, 92 Mass. App. Ct. 567, 572 (2017), but review for abuse of discretion or error of law the motion judge‘s ruling concerning the Bristol parties’ showing at the second stage. See Blanchard I, 477 Mass. at 160; Nyberg, 101 Mass. App. Ct. at 646, citing Blanchard II, 483 Mass. at 203; Reichenbach, supra at 572 n.14; Gillette Co., 91 Mass. App. Ct. at 137.
2. Judge‘s analysis. a. First stage. The Bristol parties do not dispute that their amended complaint was “‘based on’ [the RBP parties‘] petitioning activities alone and [had] no substantial basis other than or in addition to [their] petitioning activities.”18 Reichenbach, 92 Mass. App. Ct. at
572, quoting Office One, Inc. v. Lopez, 437 Mass. 113, 122 (2002). We agree and conclude that the RBP parties met their threshold burden under the first stage of the augmented Duracraft framework.
b. Second stage. The burden shifted to the Bristol parties at the second stage. The motion judge correctly began with an assessment of the Bristol parties’ showing under the first of the two second-stage paths and, concluding that they had demonstrated by a preponderance of the evidence that the RBP parties’ conduct amounted to sham petitioning,19 allowed the motion.20
i. Site plan approval. A. Claims based on noise levels and decrease in property values. The RBP parties’ noise-based challenge to Edgewood‘s site plan approval was based on evidence predicting that the proposed plant would raise noise levels at adjacent properties to thirty A-weighted decibels above the ambient noise levels despite DEP regulations “limit[ing] allowable increases to 10 [A-weighted decibels] above ambient.” See
We likewise see no error in the motion judge‘s rejection of the RBP parties’ argument that approval of the site plan violated § IV(D)(1) of the bylaws, which excluded from as of right uses in the industrial district a use that “would . . . tend to reduce property values in the same or adjoining district.”
The RBP parties’ evidence demonstrated, at best, a potential decrease in the value of certain individual properties, not, as the relevant bylaw required, a “tend[ency] to reduce property values in the [industrial] or adjoining districts” more generally. To the extent that the RBP parties argued for a narrower interpretation of the bylaw, the motion judge did not err in implicitly deferring to the planning board‘s reasonable interpretation of its own bylaws, see Shirley Wayside Ltd. Partnership v. Board of Appeals of Shirley, 461 Mass. 469, 475 (2012).22
B. Claims based on traffic. We also discern no abuse of discretion or other error in the motion judge‘s conclusion that the RBP parties “lack[ed] a reasonable basis in fact or law” for their claim that potential traffic issues required the denial of the application for site plan approval. Blanchard I, 477 Mass. at 159. As we concluded in D‘Acci, and as the motion judge noted in his decision on the special motion to dismiss, the RBP parties did not present evidence at any stage to show that the Bristol parties’ proposed bituminous concrete plant was any more detrimental or offensive than any other similar use, or that it was not a permitted use in the industrial district. See D‘Acci, 91 Mass. App. Ct. 1118.
Considering the proposed plant as a permitted use, the planning board was limited by § XVI of the bylaws, adopted February 27,
The RBP parties’ particular traffic arguments required no site-specific conditions.24 The motion judge relied on our decision in D‘Acci to conclude that “there was ‘no evidence’ the proposed plant would increase noise or truck traffic any more than any other use permitted in the industrial zoning district.” See D‘Acci, 91 Mass. App. Ct. 1118. While true as far as it goes, this conclusion was part of our determination that the proposed facility was a permitted use; in D‘Acci, we did not consider the traffic challenges the RBP parties raised, or whether additional conditions were needed to address them. Id. We nonetheless conclude that because the record permitted the judge to reach the conclusion that he did, he was within his discretion in denying the special motion to dismiss. See Gabbidon v. King, 414 Mass. 685, 686 (1993) (appellate court may affirm on “any ground apparent on the record that supports the result reached in the lower court“). This is because it is apparent from the Land Court judge‘s
It is true that in the Land Court trial, the abutters’ traffic expert testified, based on the proposed site plan, that the proposed plant‘s operation would result in traffic backups on the adjacent roadway, and that if more than six trucks were lined up on the driveway to pick up deliveries, any additional truck traffic would spill over onto the adjacent roadway. As the Land Court judge noted, however, the expert‘s testimony depended on essential facts about which he had no personal knowledge, and which were provided to him by the “Todesca Plaintiffs.” Notably, the expert relied on the “Todesca Plaintiffs” for such critical facts as the dimensions of the trucks to be used at the site, the number of trucks that “actually process” through a facility and the time required to load each truck and to move it out of the queue of waiting vehicles, and the ability of the plant operators to regulate the timing of incoming truck traffic. The fact that the Land Court judge engaged in a weighing of the evidence presented does not mean that the motion judge abused his discretion in concluding that, ultimately, the site plan challenge was a sham. As the motion judge correctly recognized, to carry its burden at the second stage, first path, the Bristol parties’ burden was to demonstrate that the RBP parties’ claims lacked reasonable factual or legal support; the Bristol parties were not required to show that the RBP parties’ claims lacked any support. See Baker, 434 Mass. at 553-554. Given the Land Court judge‘s assessment, the motion judge, in ruling on the RBP parties’ special motion to dismiss, acted within his discretion to conclude, as he did, that although the “Todesca Plaintiffs” introduced evidence in support of their position, the evidence in question did not provide them with “a reasonable basis in fact or law” for their traffic claims. Blanchard I, 477 Mass. at 159. The bar at this stage of the analysis is “high,” but the record here supports the judge‘s conclusion that the Bristol parties met it in this case. Blanchard II, 483 Mass. at 204.
ii. Conservation commission. We discern no abuse of discretion or error in the motion judge‘s conclusion that the RBP parties’ opposition to the commission‘s extension of the Bristol parties’
iii. MEPA petition. We similarly determine that there was no abuse of discretion or other error in the motion judge‘s conclusion that the MEPA petitioning was sham litigation. Under
Conclusion. The motion judge properly concluded the RBP parties’ petitioning activity was “devoid of any reasonable factual support or any arguable basis in law.”
So ordered.
RUBIN, J. (concurring). I agree with and join the majority‘s opinion in its entirety. Although I therefore do not believe we need reach the question to resolve this case, I write separately to express my disagreement with my learned dissenting colleague‘s assertion that, even in the absence of a statute like the anti-SLAPP statute, the Federal Constitution requires immunity from suit (what he calls “not be[ing] subject to suit“), post at , for redress against all abusive litigation that is not within the definition of “sham” as it has been articulated in the United States Court of Appeals for the Ninth and Tenth Circuit cases he cites construing the Noerr-Pennington doctrine of antitrust immunity for nonsham litigation1 (which, I note, is in any event an immunity from liability, not suit). See United States v. Koziol, 993 F.3d 1160, 1171 (9th Cir. 2021), cert. denied, 142 S. Ct. 1372 (2022); CSMN Invs., LLC v. Cordillera Metro. Dist., 956 F.3d 1276, 1286 (10th Cir. 2020); Scott v. Hern, 216 F.3d 897, 915 (10th Cir. 2000). For example, suits alleging the tort of abuse of process, themselves facially protected by the petition clause of the First Amendment to the United States Constitution, have long been held to have merit even in some cases where the defendant‘s abusive suit led to some recovery. See, e.g., Puerto Rico Tel. Co. v. San Juan Cable LLC, 874 F.3d 767, 774 (1st Cir. 2018), cert. denied, 138 S. Ct. 1597 (2019) (Barron, J., concurring, with whom Torruella, J., joined) (“[T]he tort of abuse of process is itself sensitive to circumstance, but, presumably, the First Amendment is not infringed just because the tort imposes liability on some suits that have some merit“). See also Poduska v. Ward, 895 F.2d 854, 857 (1st Cir. 1990) (Aldrich, J.) (even fact that jury made small award to defendant as plaintiff in lawsuit does not preclude finding that suit was abuse of process); Restatement (Second) of Torts § 682 comment a (1977).2 This aspect of the tort obviously was not outlawed at the Federal level by the adoption in 1791 of the First Amendment, nor in Massachusetts by the adoption in 1868 of the Fourteenth Amendment to the United States Constitution. Likewise, the relatively recent enactment of the anti-SLAPP statute in 1994, was not, as the dissent‘s analysis implies, unnecessary because, since 1868, one could get every suit to which it applies, and more, dismissed directly under the First and Fourteenth Amendments.
I also therefore disagree with my dissenting colleague‘s conclusion that the Supreme Judicial Court‘s second path of the second stage holding in Blanchard v. Steward Carney Hosp., Inc., 477 Mass. 141, 160 (2017), S.C., 483 Mass. 200 (2019), by which we are bound, that a plaintiff can defeat a special motion to dismiss and proceed with suit if that plaintiff can “demonstrat[e] that [the challenged] claim was not primarily brought to chill the special movant‘s legitimate petitioning activities,” violates the petition clause of the First Amendment.
ENGLANDER, J. (dissenting in part). Application of the anti-SLAPP
To be clear, I agree with the majority that many of the claims that the RBP parties previously asserted to government bodies -- including all claims that the RBP parties asserted based upon actions of the town of Rochester (town) conservation commission and the Executive Office of Energy and Environmental Affairs -- were entirely without basis and thus a “sham.” But not all of the RBP parties’ prior claims met that test. In particular, the RBP parties’ Land Court challenge to the planning board‘s site plan approval raised material concerns about how truck traffic would infringe on the public way abutting the site, which concerns were backed by reasonable, fact-based expert testimony. In bringing suit to present such legitimate concerns, the RBP parties were exercising their constitutional right to petition the government for redress.1 See Real Estate Bar Ass‘n for Mass., Inc. v. National Real Estate Info. Servs., 608 F.3d 110, 124 (1st Cir. 2010). The RBP parties cannot be subject to government sanction for that exercise,
My quarrel with the majority is narrow, but important. While I agree that most of the claims and arguments that the RBP parties advanced in opposing the proposed development were without basis in fact or law, the majority also would allow the Bristol parties to pursue damages from the RBP parties for their assertion of a claim that was not “without basis.” There are several points to be made about why such a result cannot be allowed.
First, we should pause for a moment to recognize that it should be the unusual case where a court concludes, as the judge did here, that a party‘s prior efforts to petition the government were without reasonable basis. Labeling petitioning activity a “sham” cannot be undertaken lightly. As the majority notes, proving that particular petitioning activity is “a sham presents a ‘high bar‘” (citation omitted). Blanchard v. Steward Carney Hospital, Inc., 483 Mass. 200, 204 (2019) (Blanchard II). And for good reason, because if petitioning activity can be too easily subjected to suit, we will end up chilling the very activity that the anti-SLAPP statute (and the petition clause) were designed to protect.
Second, the standard for establishing “sham” petitioning was not met here with respect to the RBP parties’ previous claim that the Bristol parties’ proposed use might result in “detrimental or offensive” traffic impacts on an abutting highway. As indicated, the sham petitioning standard requires the Bristol parties to show that the petitioning activity they seek to sanction was “devoid of
The petitioning activity I wish to focus on here was the RBP parties’ challenge to the planning board‘s site plan approval. The RBP parties filed suit in the Land Court, as provided by statute. See
For their part, the Bristol parties did not take issue with their obligation to meet the not “detrimental or offensive” legal standard under the town bylaws. Nor did the Bristol parties challenge the RBP parties’ expert‘s calculations or observations as to how many trucks could be queued on site at one time. Rather, the Bristol parties argued that the scenario painted by the RBP parties’ expert was unlikely to occur. For one thing, the Bristol parties pointed out that one of the conditions of site plan approval required “no parking” signs to be placed on Kings Highway. But the Bristol parties’ principal contention was a practical one: they contended that most of the trucks bringing raw material would be from their own or related companies, and those trucks could be
“On balance, I am not persuaded that [the] site plan . . . will result in the vehicular safety issues hypothesized by [the RBP parties’ expert], except in unusual circumstances. Even if such unusual circumstances were to arise, I credit [the Bristol parties’ expert‘s] testimony that [the Bristol parties] ha[ve] the capacity to control the majority of the trucks visiting the [proposed site] and therefore could direct trucks away from the site if the hypothetical events posited by [the RBP parties’ expert] were to occur.”
It was incorrect to conclude, on the above record, that this aspect of the RBP parties’ claims was a “sham.” The RBP parties’ claim was based in fact (the idiosyncrasies of the proposed site plan, including the proximity to Kings Highway and the narrowness of the interior roads), and supported by reasonable expert testimony. The RBP parties brought an appropriate legal claim, based upon the standard of a town bylaw. Notably, the trial judge did not suggest the claim was without basis, ruling against it only after considering the arguments “on balance.” A losing claim is not automatically a “sham.” See Wenger v. Aceto, 451 Mass. 1, 7 (2008) (“The critical determination is not whether the petitioning activity in question will be successful, but whether it contains any reasonable factual or legal merit at all“); Donovan v. Gardner, 50 Mass. App. Ct. 595, 601 (2000) (“That [defendants] were unsuccessful does not, in and of itself, mean that their [petitioning activity] did not have some basis in law or foundation in fact“).
In short, this particular aspect of the RBP parties’ arguments raised reasonable concerns to a government body, which the RBP parties were entitled to raise. The majority attempts to paint these concerns as “hypothetical,” ante at , but that is a mere label, which does not meet the substance of the RBP parties’ contentions. True, the RBP parties’ expert testimony necessarily was hypothetical, in that the expert was addressing what would happen in the future, when the plant was completed and operating. His analysis was not rooted in fantasy, however, but in a facially reasonable assumption that from time to time, more than six trucks would be queued to pick up finished product. Notably, there was no planning board condition that would prevent this; there was no condition, for example, requiring the Bristol parties
Third, I disagree with the majority that we review the motion judge‘s denial of the special motion to dismiss only for “abuse of discretion.” The question whether particular petitioning activity was without reasonable basis must be treated as a question of law, subject to de novo review. The reason for this, most importantly, is that fundamental First Amendment rights are at stake; the RBP parties had a right to bring their Land Court suit, and they cannot be subject to State sanction (e.g., in damages) for bringing it, unless it was without basis in fact or law. See Scott v. Hern, 216 F.3d at 914-915 (collecting cases; “petitioning activities” are protected “from liability under the First Amendment” unless, among other things, plaintiff shows “the defendant‘s [prior] claims were devoid of reasonable factual support” or “lacked any cognizable basis in law” [citation omitted]).5
The cases the majority cites for applying an abuse of discretion standard -- in particular, Blanchard v. Steward Carney Hosp., Inc., 477 Mass. 141 (2017) (Blanchard I), S.C., 483 Mass. 200 (2019) (Blanchard II) -- do not require a contrary result. In Blanchard I, the Supreme Judicial Court announced an alternative means by which plaintiffs can defeat special motions to dismiss -- the complexly labelled “second path” of the “second stage” of the anti-SLAPP analysis. Blanchard II, 483 Mass. at 204-205. In Blanchard I, the Supreme Judicial Court explained
Fourth, the decision below, which denied the motion to dismiss in its entirety, cannot be justified on a theory that most of the defendants’ petitioning activity was, in fact, a sham. The anti-SLAPP case law requires a more careful and discerning analysis. The Supreme Judicial Court‘s decision in Blanchard I made this clear, where the court separately addressed two components of the plaintiffs’ libel claim, holding that one survived the anti-SLAPP statute, while one might not. See Blanchard I, 477 Mass. at 150-153. As we noted in Haverhill Stem LLC v. Jennings, 99 Mass. App. Ct. 626, 634 (2021), when applying the anti-SLAPP statute, “the allegations need to be carefully parsed even within a single count.” Accordingly, while the anti-SLAPP motion was properly denied as to many of the bases of the Bristol parties’ claims, the motion had to be granted as to claimed damages arising out of the traffic contentions highlighted above.8 The First Amendment precludes the Bristol parties from recovering for that
Fifth and finally, I need to go on to address the “second path of the second stage” of the anti-SLAPP analysis. Why this is necessary is not simple to describe, but I will give it a try: (1) if (as here) the plaintiffs’ (Bristol parties‘) claim is based solely on the defendants’ (RBP parties‘) prior petitioning activity, then the first stage is satisfied, and the anti-SLAPP statute applies to bar the claim, unless (2) the petitioning activity sued upon is a sham (under the second stage, first path), in which case the anti-SLAPP statute does not apply to bar the claim and the case can go forward.
So far, so good. But as noted, in Blanchard I the Supreme Judicial Court set forth the alternative “second path.” See Blanchard I, 477 Mass. at 160. Under that alternative, even if a lawsuit seeks to sanction petitioning activity and the petitioning activity had a reasonable basis (i.e., was not a sham), dismissal under the anti-SLAPP statute can still be avoided on the plaintiffs’ showing that its lawsuit was not “primarily brought to chill” the defendants’ prior assertions of their petitioning rights. See id. In Blanchard I, the Supreme Judicial Court reasoned that this second path was required to further mitigate “the possibility” that defendants “may . . . use the [anti-SLAPP] special motion [to dismiss] to eradicate [plaintiffs‘] . . . claim[s],” even where the plaintiffs’ claims are not “primarily geared toward chilling [legitimate] petitioning” -- thus (arguably) chilling the plaintiffs’ own petitioning rights in the process. Id. at 157.
Because I have concluded that a portion of the RBP parties’ prior petitioning activities was not a sham, under Blanchard I and its progeny I would need to analyze this second path. But in my view, such an analysis is unnecessary, and indeed, constitutionally
To the extent described above, I dissent from the majority‘s opinion affirming the denial of the motion to dismiss.
Notes
The RBP parties’ traffic arguments can be contrasted with their contentions, also made to the planning board on site plan review, that the proposed plant would violate the Department of Environmental Protection (DEP) noise regulations. The RBP parties pursued this noise argument, even though the planning board expressly conditioned its site plan approval on the plant‘s compliance with DEP noise regulations. And the RBP parties thereafter pursued this noise argument to the town zoning board of appeals, to the Land Court, and to this court, at which point we noted that the planning board‘s conditions were reasonable, because “[i]n order to begin operations, [the plant operator] would have to apply for an air permit from DEP, which would only approve the permit if it found the [proposed] facility to be in conformance with State noise regulations.” The RBP parties’ pursuit of the noise argument in connection with the planning board‘s site plan approval thus had no reasonable basis in law.
Indeed, I am aware of no context in which conduct objectively protected by the First Amendment nevertheless can be sanctioned, because the government (i.e., the courts) concludes that it does not like the subjective motivation behind the petitioning/speech. Accordingly, while I acknowledge a tension between some abuse of process authority and the above petition clause case law, that tension is resolved by requiring abuse of process plaintiffs to show that the action they are challenging was objectively without basis. See Protect Our Mountain Env‘t, Inc. v. District Court, 677 P.2d 1361, 1369 (Colo. 1984).
