BLOIS CONSTRUCTION, INC., Plaintiff and Appellant, v. FCI/FLUOR/PARSONS, Defendant and Respondent.
No. B262310
Court of Appeal, Second District, Division One, California
March 23, 2016
245 Cal.App.4th 1091
Counsel
Lax & Stevens and Paul A. Lax for Plaintiff and Appellant.
Musick, Peeler & Garrett, Jack W. Fleming and Peter J. Diedrich for Defendant and Respondent.
Opinion
ROTHSCHILD, P. J.—This case involves the interpretation of prompt payment statutes intended to guarantee timely payments to contractors and subcontractors in construction projects. As is typical in the construction industry, here the contract between the owner of the project and the contractor allowed the owner to withhold as “retentions” a percentage of the payments due pending successful completion of the project. Similarly, the contract between the contractor and the subcontractor allowed the contractor to withhold retentions from the payments due the subcontractor.
Pursuant to
FACTS AND PROCEEDINGS BELOW
In 2006, the Exposition Metro Line Construction Authority (Expo)1 contracted with defendant FCI/Fluor/Parsons (FFP) to serve as the general contractor for the Exposition light-rail line, connecting downtown Los Angeles with Culver City and ultimately with Santa Monica. FFP is a joint venture of Flatiron West, Inc.; Fluor Enterprises, Inc.; and Parsons Transportation Group, Inc. Plaintiff Blois Construction, Inc. (Blois), agreed to serve as a subcontractor on the project, responsible for underground work. Both the primary contract and subcontract contained a provision allowing for portions of the progress payments due under the contract to be retained pending successful completion of the work. Expo was permitted to withhold 10 percent of the payments owed to FFP, and FFP was entitled to withhold 10 percent of the payments owed to Blois.
The retention provision in the general contract provided that “after fifty percent (50%) of the Work has been completed, [Expo] may elect to not make further retentions from the remaining Progress Payments if it determines, in its sole discretion, that progress on the Work is satisfactory.” Accordingly, in December 2009, FFP requested that Expo cease withholding retentions. Expo acceded to FFP‘s request, and although Expo reserved the right to resume withholding at a later date, it never withheld retention funds from a payment to FFP after December 7, 2009. It did not, however, release the previously withheld retention funds until May 30, 2014, or later.
By the time Blois finished its work on the project in 2011, FFP had withheld over $500,000 in retentions from Blois. In 2012, Blois filed suit against FFP and its sureties, alleging that FFP had failed to pay Blois for (1) the extra work that Blois performed on the project and (2) the retentions it had withheld. Pursuant to FFP‘s motion, the court referred the case to a dispute review board (Board) for arbitration. In the fall of 2013, while the case was still pending before the Board, FFP paid Blois $534,909.89, the full amount that Blois claimed it was owed in retentions. The Board ruled in favor of Blois, finding among other things that under the terms of the subcontract, FFP had been required to pay the retentions it had withheld by September 2011. But the Board left for the trial court to decide whether Blois was entitled to penalties from FFP for late payment of retained amounts.
After a court trial, the court ruled Blois was not entitled to penalties because Expo had not released the retained funds to FFP until 2014 and FFP had paid Blois the full amount of its retention by the end of 2013.
DISCUSSION
California has a series of laws known as “prompt payment” statutes, which govern the timing of payments from project owners to general contractors and from general contractors to subcontractors.2 The purpose of these statutes is to ensure that contractors and subcontractors, who may have less leverage than project owners and contractors, respectively, are paid for their work on a timely basis. (Morton Engineering & Construction, Inc. v. Patscheck (2001) 87 Cal.App.4th 712, 720.)
The primary prompt payment statute at issue here is section 7107. This section requires public entities to release retention proceeds to contractors within 60 days of the completion of a project. (
The only dispute in this case is whether Expo‘s practice, beginning in February 2010, of paying FFP the full amount of progress payments and not withholding any retentions triggered an obligation by FFP under section 7107 to pay Blois retentions that it had previously withheld. Blois contends that the answer is yes. It argues that, after December 2009, when Expo made its regular progress payments to FFP without withholding any amount in retention, “retention proceeds [were] received by the original contractor” (
Blois‘s argument fails because when Expo ceased withholding retention funds in 2010, it was not paying funds previously withheld. Rather, in its progress payments, it paid FFP the total amount then due without withholding a retention. Because no funds were withheld or paid as retentions, section 7107 did not apply to these payments.
Blois contends that our conclusion is inconsistent with the remedial purpose of the prompt payment statutes, “to encourage general contractors to pay timely their subcontractors.” (Morton Engineering & Construction, Inc. v. Patscheck, supra, 87 Cal.App.4th at p. 720.) According to Blois, by restricting the definition of “retention proceeds,” we will allow contractors in FFP‘s position to continue withholding retentions from their payments to subcontractors even after the project owner ceases withholding retention proceeds from the contractor. This result would be contrary to the spirit and arguably the letter of
In a complicated public works project, a contractor may wait years before being paid retentions from the owner. The prompt payment statutes guarantee only that subcontractors do not wait significantly longer for payment than direct contractors do. By adopting a limited definition of “retention proceeds” in accordance with statutory language and case law, we support that guarantee. Under the prompt payment statutes, contractors are required to pay subcontractors the retentions owed them upon their receipt from the owner but not earlier.
Because FFP did not receive any retention proceeds from Expo until at least May 30, 2014, its obligation to pay Blois pursuant to section 7107, subdivision (d), did not arise until at least that date. FFP satisfied that obligation by paying Blois the full amount it was due by November 2013. Thus, Blois is not entitled to late payment penalties under section 7107, subdivision (f).
DISPOSITION
The judgment of the trial court is affirmed. Respondent to recover its costs on appeal.
Johnson, J., and Lui, J., concurred.
On April 12, 2016, the opinion was modified to read as printed above. Appellant‘s petition for review by the Supreme Court was denied June 29, 2016, S234254. Corrigan, J., did not participate therein.
