History
  • No items yet
midpage
Blois Construction, Inc. v. FCI/Fluor/Parsons
245 Cal. App. 4th 1091
| Cal. Ct. App. | 2016
Read the full case

Background

  • Expo (public entity) contracted with FFP as general contractor; FFP subcontracted underground work to Blois. Both contracts allowed 10% retentions from progress payments.
  • The general contract allowed Expo, after 50% completion, to stop withholding future retentions; in December 2009 Expo stopped withholding retentions on future progress payments to FFP (but reserved right to resume).
  • Expo did not release previously withheld retention funds to FFP until May 30, 2014 or later.
  • FFP continued to withhold previously accumulated retentions from Blois; by project completion Blois claimed over $500,000 in withheld retentions.
  • Blois sought penalties under Public Contract Code § 7107 after FFP eventually paid Blois the retention amount in 2013; trial court denied penalties, and the Court of Appeal affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether an owner’s decision to stop withholding future retentions (and make full progress payments) constitutes "retention proceeds" received by the original contractor under Pub. Contract Code § 7107(d) Blois: stopping future withholding meant FFP "received" retention proceeds, triggering a 7‑day pay obligation to subcontractors and penalty exposure FFP: § 7107 applies only when retention proceeds actually withheld are paid out; paying full progress payments (without having previously withheld those amounts) is not payment of retained funds Court: No — § 7107 covers funds actually withheld and later released; full progress payments that do not release previously withheld retentions do not trigger § 7107 penalties

Key Cases Cited

  • Morton Engineering & Construction, Inc. v. Patscheck, 87 Cal.App.4th 712 (court recognizes prompt payment statutes’ purpose to ensure timely payments)
  • S&S Cummins Corp. v. West Bay Builders, Inc., 159 Cal.App.4th 765 (de novo review for statutory interpretation)
  • Yassin v. Solis, 184 Cal.App.4th 524 (final payment not a retention payment when not previously withheld)
  • McAndrew v. Hazegh, 128 Cal.App.4th 1563 (penalties under prompt payment statutes require proof owner actually withheld retention proceeds)
  • Murray’s Iron Works, Inc. v. Boyce, 158 Cal.App.4th 1279 (definition of "progress payment" in prompt payment context)
Read the full case

Case Details

Case Name: Blois Construction, Inc. v. FCI/Fluor/Parsons
Court Name: California Court of Appeal
Date Published: Mar 23, 2016
Citation: 245 Cal. App. 4th 1091
Docket Number: B262310
Court Abbreviation: Cal. Ct. App.