APACHE DEEPWATER, L.L.C., Plaintiff - Appellee v. W&T OFFSHORE, INCORPORATED, Defendant - Appellant
No. 17-20599
United States Court of Appeals for the Fifth Circuit
July 16, 2019
Appeal from the United States District Court for the Southern District of Texas
Before HIGGINBOTHAM, GRAVES, and WILLETT, Circuit Judges.
This dispute arises from a successful plugging and abandonment operation of three offshore oil and gas wells in the Mississippi Canyon area of the Gulf of Mexico. Apache Deepwater, LLC performed the operation and seeks payment from its non-operator partner, W&T Offshore, Inc. A jury awarded $43.2 million to Apache for W&T‘s breach of the Joint Operating Agreement. W&T challenges the district court‘s application of the Louisiana Civil Code and interpretation of the contract. Alternatively, W&T contends that it is entitled to an offset in damages because of Apache‘s bad faith. Finding no error, we affirm.
I.
In May 1999, Apache and W&T‘s predecessors entered into a Joint Operating Agreement (“JOA”) that governed the operation of three offshore deepwater oil and gas wells (the “Wells”) in the Mississippi Canyon area of the Gulf of Mexico. This dispute arises from operator Apache‘s plugging and abandonment (“P&A”) of the Wells.
In 2012, Apache attempted to P&A the Wells with an intervention vessel called Uncle John with the consent of W&T, but that operation was unsuccessful. Following that failure, Apache contracted to use a different intervention vessel, the Helix-534 (“Helix”). An internal figure by Apache estimated that the cost to P&A the Wells with the Helix was approximately $56,350,000. In June 2014, W&T contacted Apache to set up a status conference in July discussing the P&A operation, confirming that W&T knew “that the Helix 534 is contracted for the project.” At that meeting, W&T learned that Apache proposed using two drilling rigs for the project instead of the Helix, the Ocean Onyx (“Onyx”) and Ensco-8505 (“Ensco”).
W&T and Apache offered to the jury competing explanations for the switch from the Helix to the Onyx and Ensco drilling rigs. By W&T‘s telling, Apache‘s decision to use the Onyx and Ensco was a simple matter of cost: W&T contends that Apache entered into a contract for the two drilling rigs for the purpose of drilling new deepwater wells, but abandoned that project in 2014 and was left with exorbitant stacking costs for the idle rigs (approximately $1,000,000 per day). W&T asserts that Apache‘s decision to use the rigs instead of the Helix was an attempt to recoup on the costs of contracting for the
Apache rejects W&T‘s economic explanation and argues that the Helix was not a safe option after the Deepwater Horizon spill and the government regulators would not have approved the Helix for the P&A operations. Apache put on evidence that it had discussed the risks of using the Helix with W&T, and demonstrated that technical difficulties posed by the Wells would make the “open water” operations of the Helix environmentally risky, that the Wells were “high risk,” and that the drilling rigs were able to conduct the P&A operations with safeguards mitigating the risk of oil spills. Apache also claimed that the federal Bureau of Safety and Environmental Enforcement (“BSEE”) advised Apache that it was no longer approving the type of open-water operations that Helix would need to perform to complete the P&A task. In Apache‘s version, W&T began “actively resisting” the P&A plan using the rigs because the Helix operation would be far cheaper for W&T and W&T was disregarding the environmental risk.1 Apache argued to the jury that W&T ignored the fact that Helix would have had operational issues that would have increased the costs of the operation past the initial estimates and that the use of the rigs was “reasonably necessary.”
Amid their dispute over the appropriate intervention vessel, Apache sought W&T‘s approval for use of the rigs through an Authorizations for Expenditure (“AFE”), but W&T decided not to approve the use of the rigs,2 and rejected two other requests for AFEs. Apache decided to use the rigs for the P&A and the work was successfully completed in February 2015 for a total cost of $139,900,000. Apache billed W&T for its contractual 49% share, or $68,570,000. W&T decided to pay $24,860,640, which represented 49% of the estimate for use of the Helix, contending that “Apache‘s insistence on using a drilling rig unnecessarily and unreasonably increased the costs of this work,” and determining that it was not obligated to pay the full billed amount because it had not approved the AFEs.
6.2. Authorization for Expenditure: The Operator shall not make any single expenditure or undertake any activity or operation costing Two Hundred Thousand Dollars ($200,000) or more, unless an AFE has either (1) been included in a proposal for an activity or operation and is approved by the Participating Parties through their Election to participate in the activity or operation, or (2) received the approval of the Parties as a General Matter. When executed by a party, an AFE grants the Operator the authority to commit or expend funds on the activity or operation in accordance with this Agreement for the account of the Participating Parties. . . .
18.4. Abandonment Operations Requirement by Governmental Authority: The Operator shall conduct the abandonment and removal of any well, Production System or Facilities required by a governmental authority, and the Costs, risks and net proceeds will be shared by the Participating Parties in such well, Production System or Facilities according to their Participating Interest Share.
The district court denied W&T‘s motion for summary judgment and determined that the interaction of the provisions in the JOA was ambiguous, creating an issue of fact as to the “parties’ intent on the applicability of § 6.2 to a government-mandated plugging and abandonment operation governed by § 18.4.” The case proceeded to trial and the jury made five findings:
- Did W&T fail to comply with the Contract by failing to pay its proportionate share of the costs to plug and abandon the MC 674 wells? Yes.
- What sum of money, if any, would compensate Apache for W&T‘s failure to pay its proportionate share of costs to plug and abandon the MC 674 wells? $43,214,515.83.
- Was Apache required to obtain W&T‘s approval under Section 6.2 of the Contract before Apache plugged and abandoned the MC 674 wells as required under Section 18.4 of the Contract? No.
- Did Apache act in bad faith, thereby causing W&T to not comply with the contract? Yes.
- By what amount, if any, should the amount you found in response to Jury Question No. 2 be offset? $17,000,000.
Following trial, the court entered its order and final judgment, determining that the jury‘s “bad faith” finding in Question 4 did not preclude Apache‘s recovery for breach of contract under Louisiana law and holding that W&T was not entitled to an offset under Louisiana law. The district court also denied W&T‘s motion for a new trial or remittitur and renewed motion for judgment as a matter of law. This appeal followed.
II.
This court reviews the denial of a
“A district court‘s resolution of a motion for new trial is reviewed for abuse of discretion, and ‘[t]he district court abuses its discretion by denying a new trial only when there is an “absolute absence of evidence to support the jury‘s verdict.”’”7 “A motion for a new trial or to amend a judgment cannot be used to raise arguments which could, and should, have been made before the judgment issued.”8 “To the extent that a Rule 59(e) ruling was a reconsideration of a question of law, . . . the standard of review is de novo.”9
III.
W&T contends that the plain language of
An obligee may not recover damages when his own bad faith has caused the obligor‘s failure to perform or when, at the time of the contract, he has concealed from the obligor facts that he knew or should have known would cause a failure.
If the obligee‘s negligence contributes to the obligor‘s failure to perform, the damages are reduced in proportion to that negligence.10
In answering the fourth question on the verdict form, the jury found that “Apache act[ed] in bad faith thereby causing W&T to not comply with the contract.”
The district court denied W&T‘s motion for judgment as a matter of law, concluding that it was bound by the Louisiana Supreme Court‘s decision in Lamar Contractors, Inc. v. Kacco, Inc.11 The district court determined that, under Lamar, Article 2003‘s bad faith damages bar is only implicated where the obligor has established
W&T disputes the district court‘s reading of and reliance on Lamar, arguing that (1) Lamar is not binding on this court because it is not jurisprudence constante and this court must instead follow the plain language of Article 2003, which contains no language limiting Article 2003‘s application to situations where the obligee has breached; (2) Lamar‘s holding is limited to Article 2003‘s negligence clause; and (3) application of Lamar is contrary to public policy.
In diversity cases where this court must apply Louisiana substantive law,13 “we look to the final decisions of the Louisiana Supreme Court.”14 In the absence of a final decision by the state‘s supreme court, we make an Erie guess, which requires us to “employ Louisiana‘s civilian methodology, whereby we first examine primary sources of law: the constitution, codes, and statutes.”15 Even caselaw rising to the level of jurisprudence constante is “secondary law in Louisiana”16 and, accordingly, we are not strictly bound by the decisions of Louisiana‘s intermediate appellate courts.17 So, it is only when the Louisiana Supreme Court has not made a determinative decision that this court must make an Erie guess, employing Louisiana‘s civilian methodology.18
The parties dispute whether Lamar speaks definitively on the issue of whether Article 2003 bars recovery of damages only when the obligee has been found in breach. In Lamar, the Louisiana Supreme Court considered a trial court‘s decision to reduce breach of contract damages awarded to a general contractor, Lamar, after finding that Lamar had contributed to the
While W&T urges that the Louisiana Supreme Court‘s reading was limited to the second sentence of Article 2003—the negligence prong—the Lamar court drew no such limitation.25 The reasoning of Lamar did not depend on the relationship between bad faith and negligence. W&T offers no principled reason why the Louisiana Supreme Court would have chosen not to recognize a requirement of breach had the obligee in that case acted in bad faith, rather than negligently. Indeed, we find no distinction in Lamar. Because Lamar is controlling here, the district court correctly concluded that the good-faith inquiry in Article 2003 is limited to situations where the obligee has breached.26 The jury did not find that Apache breached so Article 2003 does not bar Apache‘s entitlement to damages as a matter of law.
IV.
W&T also contends that the case never should have gone before a jury because W&T did not breach the contract as a matter of law. Section 6.2 of the JOA provides that the operator “shall not make
Apache disputes W&T‘s reading of the contract, arguing that under Section 18.4, which covers government-mandated P&A operations, Apache was required to undertake its P&A of the Wells as the operator and was authorized to do so without obtaining an AFE from W&T pursuant to Section 6.2. Section 18.4 provides that
The Operator shall conduct the abandonment and removal of any well, Production System or Facilities required by a governmental authority, and the Costs, risks and net proceeds will be shared by the Participating Parties in such well, Production System or Facilities according to their Participating Interest Share.
Apache asserts that this provision contemplates cost-sharing between the parties and does not incorporate Section 6.2‘s AFE process. Apache stresses that requiring a Section 6.2 AFE for a government-mandated P&A operation would lead to an absurd result because the non-operator could essentially hold-up an operator from completing a P&A required by federal law to avoid sharing the costs.
The district court denied W&T‘s motion for summary judgment, concluding that the interplay between Section 6.2 and Section 18.4 was ambiguous, leaving a material question of fact as to the parties’ intent. In answering Question Three, the jury found that Apache was not required to obtain W&T‘s approval through an AFE before conducting the P&A as required by Section 18.428
Whether contract language is ambiguous under Louisiana law is a question of law.29 Under Louisiana law, “[w]hen the words of a contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties’ intent.”30 “[I]f a court finds the contract to be unambiguous, it may construe the intent from the face of the document—without considering
Applying Section 6.2‘s expenditure provision to a government-mandated P&A undertaken pursuant to Section 18.4 would lead to an absurd consequence: namely a situation where a non-operator is empowered to hold an operator hostage, preventing the operator from completing a legally required P&A, in order to extract a better bargain or avoid cost-sharing altogether. The oddity of that result is compounded by the fact that Section 18.4 has its own cost-sharing provision,34 making the idea that the operator was required to obtain an AFE to complete the P&A less tenable. In light of that absurd consequence, the district court correctly concluded that the jury needed to resolve the question of the parties’ intent.35 We agree therefore that the question of whether Section 6.2‘s expenditure requirement applies to government-mandated P&A undertaken pursuant to Section 18.4—which itself mandates cost-sharing—is ambiguous and was properly put to the jury.
W&T‘s response to the absurdity concern is unavailing. It suggests that if the parties fail to agree on costs through the AFE process, the government can simply conduct the P&A operation itself and charge the operator and non-operator later.36 W&T does not dispute that federal law required the P&A operation of the Wells—rather it reads the Section 6.2 AFE requirement to apply to government-mandated P&A operations and urges that Apache, having failed to obtain an AFE from W&T, could have decided not to comply with federal regulations and allow the government to P&A the Wells itself. Allowing Apache to evade its obligations under federal law to P&A the Wells is contrary to its duty to conduct all operations as would a prudent operator.37 W&T‘s proposed answer to the troubling consequences of its reading is no solution at all.
V.
Finally, W&T claims that even if Apache was not barred from recovering damages, W&T is entitled to an offset based on Jury Question No. 5 and that the damages award of $43,214,515.83 should be reduced by $17 million. As to the legal basis for the offset, W&T points to “the basic law of damages” in Louisiana set out in
Article 1995 provides that “[d]amages are measured by the loss sustained by the obligee and the profit of which he has been deprived.”38 “The measure of damages for a breach of contract is the sum that will place plaintiff in the same position as if the obligation had been fulfilled.”39 On Question 2, the jury was instructed in accordance with Article 1995 to calculate “an amount that is fair compensation for those damages.” The court then explained to the jury:
Damages are measured by the loss sustained by the non-breaching party. These are called compensatory damages. The damages amount is the amount that will place Apache in the position it would have been in if the parties’ contract had been properly performed. The damages include the amount a party owed under the contract.
The jury was instructed to determine the actual loss sustained without reference to Question 5. W&T‘s own closing argument emphasized this understanding, encouraging the jury in calculating an amount for Question 2 to subtract the amount of savings W&T attributed to Apache‘s avoiding the stacking costs by using the rigs.40 W&T‘s offset argument on appeal ignores the fact that the jury instructions with respect to Question 2 tracked the language of Article 1995. The two cases W&T relies on do not offer a theory entitling W&T to offset. In Evangeline Parish School Bd. v. Energy Contracting Servs., Inc., the Louisiana appellate court considered a damages award in favor of an obligee to an energy-savings services contract.41 The court reaffirmed the general principle of Article 1995 that “[d]amages for obligor‘s failure to perform are measured by the loss sustained by the obligee and the profit of which he has been deprived” and remanded, noting that the experts failed to calculate the amount overcharged and the
W&T posits two additional legal bases to support an offset in Apache‘s damages award. First, W&T suggests that Article 2323, governing comparative fault, provides an independent legal basis for a reduction. Article 2323 applies in tort cases; the Civil Code provides its own rule governing comparative fault in contract cases—Article 2003—that we have already determined does not aid W&T here.45 W&T also claims the doctrine of compensation under Article 1893 gives independent grounds for an offset.46 As the district court correctly noted, W&T “previously admitted neither [compensation or unjust enrichment] could be the basis of the jury‘s finding, as that was not the nature of the evidence presented to the jury.” In its post-verdict briefing, W&T conceded that Article 1893 did not apply, because “the jury was not instructed on the specific requirements of the traditional doctrine of offset or setoff, which requires debts owed by both parties being offset against each other.” Neither comparative fault nor compensation provide a basis for a reduction in the damages award here.
Finally, W&T offers a last-ditch argument that the jury award was clearly excessive because of Apache‘s savings on the stacking costs. The district court did not abuse its discretion in denying W&T‘s motion for a new trial or remittitur. We agree with the district court the damages award was supported by substantial evidence. The jury logically awarded the precise amount that W&T shorted by making a partial payment after the P&A operation. Such an award was not excessive or “contrary to right reason”—rather, it reflects that the jury‘s consideration of the evidence led it to reject W&T‘s assertion that Apache enjoyed a windfall by avoiding the stacking costs.47
VI.
For the foregoing reasons, the judgment of the district court is affirmed.
PATRICK E. HIGGINBOTHAM
UNITED STATES CIRCUIT JUDGE
