AFFILIATED CONSTRUCTION GROUP, INC., Plaintiff, v. The UNITED STATES, Defendant.
No. 10-444C
United States Court of Federal Claims.
April 16, 2014
115 Fed. Cl. 607
VICTOR J. WOLSKI, Judge
IV. Conclusion
In sum, even though KCR lacks privity with the Government under its current Complaint, amendment would prove futile as KCR was not an operator at the time that the Wells were plugged. Thus, it has no standing to bring either Count in its Complaint before this Court: it owned no property rights in the Wells (operator or otherwise) at the time the Wells were plugged, such that it possessed no property rights subject to taking. Likewise, KCR‘s abandonment of its operator status effectively revoked any rights under the Lease, which required that the Wells produce in paying quantities.
In practical effect, everything that happened in this case is the result of KCR‘s lackadaisical treatment of BLM‘s numerous letters and notices. Rather than informing BLM that it believed that the Wells were producing in paying quantities as instructed in the several iterations of the letters, KCR opted to pretend like nothing was happening and hope that if it ignored BLM‘s letters, all of KCR‘s problems would go away.2 Further exacerbating the situation, KCR opted to abandon its status as operator—and all rights appurtenant thereto—prior to the alleged taking.
For the foregoing reasons, the Court concludes that KCR lacks standing to bring its taking claim because it abandoned its rights in the Wells before the alleged taking occurred. Likewise, as currently pled, KCR also lacks privity of contract with the Government. Even if KCR amended its Complaint, however, such amendment would prove futile as once again, KCR had abandoned its status as operator of the Wells. For these reasons, the Government‘s motion to dismiss is GRANTED and KCR‘s Complaint is dismissed. The Clerk is directed to enter judgment accordingly.
Kenneth D. Woodrow and Michael S. Macko, Commercial Litigation Branch, Civil Division, Department of Justice, with whom were Tony West, Assistant Attorney General, Jeanne E. Davidson, Director, and Kirk T. Manhardt, Assistant Director, all of Washington, D.C., for defendant.
MEMORANDUM OPINION AND ORDER
VICTOR J. WOLSKI, Judge
Plaintiff Affiliated Construction Group, Inc. (ACG or Affiliated) alleges that the government breached a construction contract and that it is entitled to an equitable adjustment for increased costs and delays due to changes ordered by defendant. Compl. ¶ 12. The government has moved to dismiss two of Affiliated‘s claims under Rule 12(b)(6) of the Rules of the United States Court of Federal Claims (RCFC), arguing that plaintiff has failed to state claims upon which relief can be granted. Affiliated concedes that one claim should be dismissed, but defends the other. As discussed below, in opposing the motion for partial dismissal the plaintiff has advanced a version of a claim that departs from that presented to the contracting officer and would thus be outside our subject-matter jurisdiction under the Contract Disputes Act (CDA),
I. BACKGROUND1
Affiliated contracted to perform construction work for the Department of Defense at
The government initially filed a motion for partial dismissal of Affiliated‘s complaint for failure to state claims upon which relief can be granted. The claim that remains at issue concerns the cost of additional fire-mitigation items.2 See Def.‘s Mot. for Partial Dismissal (Def.‘s Mot.) at 1, 4. Plaintiff seeks reimbursement for costs of $50,199 and a seven-day extension of contract time for having to install increased quantities of smoke dampers, access doors, registers, grills, and diffusers beyond what it had estimated when pricing its bid. Compl. ¶¶ 36-38. In its bid, plaintiff had estimated that it would need to install six smoke dampers; twenty-three registers, grills, and diffusers; seventeen access doors; and eleven fire dampers. Id. ¶ 36. After ACG began the renovations, the required quantities increased to thirty-four smoke dampers; thirty-one registers, grills, and diffusers; and thirty-eight access doors, while the quantity of fire dampers decreased to four. Id. The government contended that this claim should be dismissed for failure to state a claim upon which relief can be granted because ACG entered into a firm-fixed-price contract for design/build services, and thus under
Regarding the fire-mitigation equipment, the complaint alleges:
These quantities represent a substantial increase in costs. ACG could not have anticipated the final quantities of the equipment and materials required for this project without the drawings during the bidding phase. The final quantities were based on code requirements and as such were not the design team‘s requirements. The quantities that were included in the original pricing allowed for a reasonable number of each item for this type of room. It was impossible to determine the amount of existing ducts and equipment that traversed and transversed this space prior to a complete and thorough site survey. The additional quantities represent a large difference in costs to the Project.
Compl. ¶ 37.
In its motion to dismiss, the government argued that plaintiff‘s contention amounted to a claim that plaintiff had underestimated the costs of performance, and in a firm-fixed-price contract the risk of such error was borne by the contractor. Def.‘s Mot. at 4-8. In its initial response, and at oral argument, plaintiff‘s position was that the increase in the quantity of fire-mitigation devices was caused by the changes the government ordered in the UPS system from the 35 percent submission to the 75 percent submission, and thus the government was responsible for the increase in the costs. Pl.‘s Br. in Opp‘n to Mot. (Pl.‘s Br.) at 4-9; Tr. 13-17.
During the hearing, the Court instructed plaintiff to file a supplemental brief addressing how the code requirements linked
II. DISCUSSION
A. Legal Standards—Jurisdiction and the CDA
Whether a federal court has jurisdiction to decide the merits of a case is a threshold matter. Steel Co. v. Citizens for a Better Env‘t, 523 U.S. 83, 94, 118 S.Ct. 1003, 140 L.Ed.2d 210 (1998). Subject-matter jurisdiction may be raised at any time by a party, by the court on its own initiative, or on appeal. Capron v. Van Noorden, 6 U.S. (2 Cranch) 126, 127, 2 L.Ed. 229 (1804); Folden v. United States, 379 F.3d 1344, 1354 (Fed. Cir. 2004); James v. United States, 86 Fed. Cl. 391, 394 (2009). When considering whether to dismiss a complaint, in whole or in part, for lack of jurisdiction, the court must presume the truth of all undisputed factual allegations and construe all reasonable inferences in favor of the non-movant. Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 40 L.Ed.2d 90 (1974); Pixton v. B & B Plastics, Inc., 291 F.3d 1324, 1326 (Fed. Cir. 2002); Forest Glen Properties, LLC v. United States, 79 Fed.Cl. 669, 676 (2007).
Under the CDA, “[e]ach claim by a contractor against the Federal Government relating to a contract shall be submitted to the contracting officer for a decision.”
In assessing the operative facts of the claim, the critical test for jurisdiction is “whether the scheme of adjudication prescribed by the CDA is undermined ... by circumventing the statutory role of the contracting officer to receive and pass judgment on the contractor‘s entire claim.” Cerberonics, 13 Cl. Ct. at 418; see also Croman Corp. v. United States, 44 Fed. Cl. 796, 801 (1999); ThermoCor, Inc. v. United States, 35 Fed. Cl. 480, 489 (1996). In other words, the claim before the court cannot be said to arise from the same operative facts unless it is clear that the claim presented to the contracting officer was specific enough to give the officer notice of the basis of the claim and allow him to make an informed judgment about it. Dodson Livestock Co. v. United States, 42 Fed. Cl. 455, 462 (1998); see also Laidlaw Envtl. Servs. (GS) Inc. v. United States, 43 Fed. Cl. 44, 51 (1999) (finding the contracting officer did not have adequate notice because the claim before the court was “at substantial variance to the issues presented to the contracting officer“).
Two claims are the same if they “arise from the same operative facts, [and] claim essentially the same relief,” even if they “assert differing legal theories for that recovery.” Scott Timber, 333 F.3d at 1365. Thus, in Scott Timber, even though plaintiff “posed slightly different legal theories” in support of its CDA claim than had been offered in the submission to the contracting officer, the Federal Circuit nevertheless determined that the Court of Federal Claims had “correctly found that it had jurisdiction” over a claim which arose from the same set of operative facts as the claim presented below. Id. at 1365-66.
B. Is Plaintiff Presenting a New Claim for an Equitable Adjustment?
The claim submitted to the contracting officer concerning the additional fire-mitigation devices is almost identical to that contained in the complaint filed in our court. The contracting officer was told:
ACG could not have anticipated the final quantities of the equipment and materials required for this project without the drawings during the bidding phase. The final quantities were based on code requirements and as such were not the design team‘s requirements. The quantities that were included in the original pricing allowed for a reasonable number of each item for this type of room. It was impossible to determine the amount of existing ducts and equipment that traversed and transversed this space prior to a complete and thorough site survey. The additional quantities represent a large difference in costs to the Project.
The contracting officer rejected this claim due to the firm-fixed-price nature of the contract, also noting “that fire damper quantities were not formally established or set by the Government” and that he “found no evidence that the requirement had changed.” Pl.‘s Supp‘l Br. Ex. A, at 11. After ACG brought this same claim in our court, see Compl. ¶ 37, defendant understandably moved for its dismissal, as the claim seemed to be based on actions of the plaintiff and not the government—namely, ACG‘s underestimation of the number of items it needed to furnish to meet code requirements. See Def.‘s Mot. at 5-7. As explained above, ACG initially (and mistakenly) tried to link the increase in these items to the alleged change in UPS requirements, and belatedly changed course to argue that the increased amounts of smoke dampers, registers, grill diffusers, and access doors were due to the existing duct work not already meeting code standards. See Pl.‘s Supp‘l Br. at 1-2, 5-7.
The question for the Court is whether this articulation of the claim differs sufficiently from that presented to the contracting officer such that it must be considered a new claim for CDA purposes. Although it is a very close question, the Court concludes that it does. Affiliated contends that the reason an equitable adjustment is warranted is that it reasonably assumed that an information technology equipment area it was to renovate already met code standards concerning the required automatic fire and smoke dampers in the air ducts.5 The key operative facts relating to this claim—other than whether ACG was on notice that the existing area was not code compliant—are whether the existing duct work contained an inadequate number of dampers and related equipment to meet the applicable code, and whether the increased numbers of these items that ACG installed were due to these preexisting deficiencies.
The problem facing ACG is that the claim as presented to the contracting officer and repeated in the complaint does not state that the room was unexpectedly found to violate code requirements. See Pl.‘s Supp‘l Br. Ex. B, at 16-17; Compl. ¶ 37. While plaintiff alleged that “final quantities were based on code requirements and as such were not the design team‘s requirements,” Pl.‘s Supp‘l Br. Ex. B, at 16, this was not placed in the context of the site‘s failure to comply with code requirements. Instead, ACG was complaining that “without the drawings” and “prior to a complete and thorough site survey” it was not in a position to know “the amount of existing ducts and equipment.” Id. at 16-17. Affiliated explained that its bid was based on “a reasonable number of each item for this type of room,” id., but failed to elaborate that this number was based on an assumption that an area that was already used to house information technology equipment would have already contained a certain amount of these items to comply with the National Fire Protection Association code. The claim as presented instead concerned the reasonableness of ACG‘s estimate of the amount of items needed compared to what was actually needed. Thus, the reference to code requirements appeared to mean that ACG had underestimated the volume of ducts and thus miscalculated the amount of fire-mitigation devices it needed to install to meet code standards for the renovation work—there is no language to indicate that the existing ducts and equipment were insufficient to comply with the code.
One may, of course, infer from the language of the claim that ACG was really contending that the conditions of the site differed from those assumed in the contract. Perhaps the strongest motivation for drawing such an inference is that the claim, as written, does not seem to have anything to do with changes in the work ordered by the
In sum, ACG‘s new articulation of its claim concerning the fire-mitigation devices is not just a change in legal theories, but is based on different operative facts from those associated with the claim as presented to the contracting officer. This articulation would thus be a new claim that has not yet been considered by the contracting officer, and accordingly cannot come within our subject-matter jurisdiction.8 The claim presented to the contracting officer, and contained in the complaint, concerns a risk that must be borne by the contractor in a firm-fixed-price contract, see
III. CONCLUSION
For the reasons stated above, the defendant‘s Motion for Partial Dismissal is GRANTED. The claims concerning lost production time due to snow days, Compl. ¶¶ 44-45, and the increased amount of fire-prevention equipment, id. ¶¶ 36-38, are not claims upon which relief can be granted and are accordingly DISMISSED under RCFC 12(b)(6). The parties shall file a Joint Status Report within fourteen days of the date of this order, proposing a schedule for further proceedings.
IT IS SO ORDERED.
VICTOR J. WOLSKI
Judge
