Placeway Construction Corp. (Placeway) appeals the United States Claims Court’s order of September 11, 1989, dismissing its complaint for lack of jurisdiction because, inter alia, the court concluded that the contracting officer (CO) had not made a final decision as to a government claim against Placeway.
See Placeway Constr. Corp. v. United States,
BACKGROUND
In 1988 Placeway entered into a contract with the United States Coast Guard (government) to construct residential housing on Governors Island, New York. The construction was completed December 20, 1984, after the completion date specified by the contract. Appendix at 108,
Placeway Constr. Corp. v. United States,
No. 90-5017 (Fed.Cir. filed Feb. 23, 1990) [hereinafter App.]. Placeway asserts that it submitted a voucher to the CO on January 21, 1985, requesting payment of the remaining contract price balance, $297,226.12.
Id.
at 24. The balance was not paid. On May 28, 1986, Placeway submitted to the CO a written demand for payment of: (1) the contract price balance, (2) thirty-one specified adjustments for additional work, and (3) extended overhead expenses based on various delays allegedly caused by, or the responsibility of, the government.
Placeway,
On June 26, 1987, Placeway filed a complaint in the Claims Court containing six counts: Count I seeks a declaratory judgment that the government cannot withhold the contract price balance due Placeway. Count II seeks a money judgment in the amount of the contract price balance, $297,-226.12, plus interest. Count III seeks an equitable adjustment of $50,000.00, plus interest, alleging underpayment of wages due to defective specifications. Count IV seeks an equitable adjustment of $27,-366.00, for increased performance costs because of alleged differing site conditions. Count V seeks twenty-two adjustments, totaling $140,251.95, for additional costs incurred because of alleged change orders, constructive changes, and defective specifi
*906
cations. Count VI seeks extended overhead costs, totaling $119,585.91, plus interest, for several delays allegedly caused by, or the responsibility of, the government.
Placeway,
The government moved to dismiss for lack of certification, and the Claims Court dismissed all the counts for lack of jurisdiction. Placeway timely appealed; we have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3) (1988). We review the question of jurisdiction de novo. See 41 U.S.C. § 609(b) (1988).
OPINION
I. Declaratory Judgment Claim
The United States Claims Court correctly noted that its predecessor court, the United States Court of Claims, did not have jurisdiction over claims seeking relief other than money damages.
See United States v. King,
In the instant case, Placeway filed its Complaint long after the contract with the government had been awarded. Accordingly, the Claims Court lacks jurisdiction over Placeway’s claim for a declaratory judgment. Therefore, we affirm the Claims Court’s dismissal of Count I.
II. Contract Price Claim
The Government Claim
The Claims Court determined that “the Government has asserted a right of set off which is tantamount to seeking ‘the adjustment ... of contract terms_’ ”
1
Placeway,
We agree that the set off asserted is a government claim,' but we conclude that the CO effectively made a final decision on the government claim. It was undisputed that Placeway had completed performance of the contract. Moreover, the contract price for the work completed was undisputed and was due upon completion of work. Although the CO may have implied that the amount of the claimed set off would be redetermined in the future, the CO effectively granted the government’s claim in the amount of $297,057.12 when he declined to pay Placeway the balance due on the contract. That the CO might decide Placeway owed more or less at a later time does not affect the finality of the decision made granting the government a sum certain, $297,057.12.
Generally, exhaustion of administrative remedies should occur before a case is ripe for judicial review. Both issues of liability and of damages should usually be resolved before judicial review is sought.
See Teller Envtl. Sys., Inc. v. United States,
III. Adjustment Claims
There is a potential for contractors to subvert the certification requirement by artificially fragmenting a single claim into separate “claims,” each seeking no more than $50,000.00;
3
any greater amount triggers the requirement for certification. Nonetheless, the CD A recognizes that a single government contract may give rise to more than one claim, and that a contractor may pursue his rights by filing “two or more suits” in either one or more fora. 41 U.S.C. § 609 (1988);
see, e.g., Warwick Constr., Inc. v. United States,
A. Adjustments for Additional Work
The Claims Court determined that Placeway had originally presented its request for compensation for additional work to the CO as a lump sum request, and concluded that Placeway improperly fragmented the single claim into “individual items” when it filed its Complaint with the Claims Court. Because the Claims Court decided it had only a single uncertified claim that exceeded $50,000.00 requiring certification, the court dismissed that claim for lack of jurisdiction.
Placeway,
The Claims Court relied upon
Contract Cleaning Maintenance, Inc. v. United States,
Because the Claims Court focused on the form in which Placeway’s claims were originally submitted to the CO, we must conclude that the court erred. It is not established that only one claim exists merely because Placeway’s letter to the CO listed all of the adjustments with a totaled sum requested at the bottom of the page. The court should have determined whether one or more claims existed, regardless of the form in which they were presented to the CO; the court should have decided this question based on whether all claims presented to the CO arose from a common or related set of operative facts.
We cannot conclude that the Claims Court’s analysis was harmless error. Far from having no legal consequence, the analysis was dispositive of the lawsuit. Placeway demanded payment from the CO based on various grounds: (1) Placeway alleged that the wage schedules in the contract were defective and as a consequence Piaceway has been unlawfully deprived of $50,000.00 in contract payments; (2) Place-way sought a $27,366.00 adjustment for a differing site condition; and (3) Placeway sought various adjustments, totaling $140,-251.95, for additional costs incurred because of change orders, constructive changes, and defective specifications. See App. at 24-28. We cannot discern from the record any common or related operative facts that would require considering any of these three claims as merely parts of a unitary claim. Nor is it apparent from the record why any of the various adjustments demanded based on change orders and defective specifications, each not more than $50,000.00, should be aggregated as a single claim. For example, there is nothing in the record to show, nor does the government argue, how a $36,566.00 adjustment requested for additional washing-machine piping that had to be installed because of defective specifications and a $20,657.28 adjustment requested for a constructive change order for additional partitions at the second floor stairwells are based on a common or related set of operative facts.
Because the Claims Court did not base its analysis on whether the claims presented to the CO arose from a common or related set of operative facts, and the government has not cited support in the record that only a unitary claim exists, we remand for the Claims Court to conduct fact finding consistent with this opinion. Accordingly, we vacate the Claims Court’s dismissal of Counts III, IV, and V for lack of certification and remand for further proceedings. 4
B. Adjustments for Extended Overhead
The Claims Court also concluded that Placeway’s Count VI, which seeks various adjustments for extended overhead, is a unitary claim requiring certification because the total adjustment sought is $119,-585.91, a sum exceeding $50,000.00. The Claims Court concluded that there was only a single claim because it considered “delays in performance of the contract” to be “a
*909
common factual threat contributing to the creation of [Placeway’s] claim.”
Placeway,
CONCLUSION
The dismissal order is affirmed as to Count I but vacated as to the remaining five counts. The Complaint, accordingly, is to be reinstated and further proceeding held thereon. The case is remanded.
COSTS
Because it has offered no persuasive authority that the CO’s action withholding payment of the contract price balance did not constitute a final decision or that certification was required, the government shall bear costs.
AFFIRMED-IN-PART, VACATED-IN-PART, AND REMANDED.
ORDER ON GRANT OF REHEARING IN PART
On September 26, 1990, the United States filed a Petition for Rehearing concerning the judgment and opinion of the court dated August 7, 1990. At the request of the court, Placeway Construction Corporation filed a response, on October 23, 1990.
Upon review of the pleadings, rehearing is granted in part. Among other contentions, the government argued that the thrust of Section II.B. of the opinion,
Because this section of the opinion merely provided an alternate ground to that set forth in earlier paragraphs of II., the court, acting through the original panel, has chosen to delete Section II.B. in its entirety as unnecessary.
Therefore,
IT IS ORDERED THAT:
1. The United States’ Petition is granted in part.
2. Section II.B. of the opinion,
3. Certain conforming changes in other parts of the opinion shall be made as follows:
(a) In heading II.,
(b) Delete the subheading “A. The Government Claim, ” Id.; and
(c) In lines 14 and 15 (col. 1),
Notes
. We believe that the government claim is better characterized as a claim seeking incidental and consequential damages for Placeway's alleged breach of the contract, in particular, failure to complete performance on the date set in the contract. The government does not appear to be trying to adjust any terms of the contract.
. Even if the CO’s letter is construed as merely a statement that he is investigating the government’s claim to decide liability, we find no authority for him effectively to award fixed damages prematurely and speculatively, i.e., prior to liability being established and a quantum being ascertained. Moreover, implicit to a CO decision to award specified damages is a decision imposing liability, whether or not liability is explicitly discussed.
.
See, e.g., Walsky Constr. Co. v. United States,
. For the reasons set forth supra, in section II, we also reject the Claims Court’s alternative basis for dismissal of these counts: that the CO has not made a final decision.
. We note that Placeway has not aided the Claims Court by how it structured its complaint. By lumping its various delay-based type claims into one count without delineating at least briefly how each claim arose and what relief is sought as to each separate claim, it gave the Claims Court grounds to question whether the claims were separate and thus whether jurisdiction existed. Although we recognize that the United States Claims Court Rules permit notice pleading, plaintiffs would be well advised to include sufficient precision in their pleading to enable the court to ascertain its jurisdiction. See RUSCC 8.
The opinion published at
