History
  • No items yet
midpage
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323
Fed. Cir.
2010
Check Treatment
Docket

*1 an retained also noted that INSC court invalidity report and secured

expert 10, 2004, and therefore

early as November defenses known its relevant have

should 16(b) This the Rule order. before

long Coleman, situation resembles the ob- experts hired the movants

where year filing before report “over

tained judgment,” and were there- summary their com- leave to amend

fore denied all Considering F.3d at 1295.

plaints. 232 factors, the trial we conclude

these discretion. did not abuse its

Conclusion reasons, foregoing we reverse

For the new Defendants’ motion for denial of and Assadian’s individual

trial on Khatemi infringement, induce-

liability for direct

ment, contributory infringement. We mo- of Defendants’ reverse denial However, trial on

tion new mo- the denial of Defendants’

we affirm amend, and for leave

tions for JMOL proceedings. remand for further

REYERSED-IN-PART, AFFIRMED-

IN-PART, and REMANDED CARPENTRY,

M. MAROPAKIS

INC., Plaintiff-Appellant, STATES, Defendant-Appellee.

UNITED

No. 2009-5024. Appeals,

United States Court of Circuit.

Federal 17, 2010.

June *2 NEWMAN, LOURIE, and

Before LINN, Judges. Circuit *3 LINN, Judge. Circuit action under the Contract This arises (“CDA”), §§ 41 Disputes Act 601- (“Mar- Maropakis Carpentry, Inc. 613. M. opakis”) appeals the decision of the United dismissing of Federal Claims States Court subject for lack of Maropakis’s complaint to matter because failed present to the officer a “claim” meaning within the Maropakis CDA. appeals grant further counterclaim for ment’s dam- ages. Maropakis Because has demonstrat- clearly ed errors of law or no erroneous findings, factual we affirm.

Background 6, April Navy On a 1999 awarded for, among things, replacement of windows building roof at a at warehouse located Inventory Naval Control Point Mechan- M. icsburg, Pennsylvania. Inc. 84 Carpentry, v. United Fed. (2008). 182, specified The Cl. 185 16, 2000, January completion date later exten- though was modified 4, February sions 2000. The contract clause, liquidated damages also included a 52.211-12, of 48 C.F.R. the form provided which would per day liable to the for $650 Divittore, E. & Sinon Stephanie Rhoads day delay beyond for each the contract LLP, PA, Harrisburgh, argued for completion date. plaintiff-appellant. Of counsel on brief H. Kelly was Decker. begin until Maropakis did not work after project specified completion date. Kiffner, Attorney, Kent Trial Com- C. 17, 2001, days 467 completed May Branch, Division, Litigation mercial Civil completion after the modified date. On Justice, Department of United States 20, 2001, August Maropakis sent DC, argued for defendant- Washington, O.I.C., to “Mr. W.L. Robertson addressed him on brief were appellee. With requesting “an General, Navfac Contracts” exten- West, Tony Attorney Assistant January ... Davidson, Director, sion of contract time from and Donald Jeanne E. 2000 total of 447 con- Kinner, April Director. E. Assistant 1326 107-day al- days”

secutive calendar based on five extension the removal (1) days leged delays: due of lead contaminated windows. This letter manufacturer; inability to locate window multiple delays referred to but did not (2) days from start in time lost date days specify total number of of extension due of fabrication windows need stated, requested. letter then “we (3) days plans; to re-submit due dispute will ... (4) discovery paint; days lead-based $303,550.00 amount will indicate Navy’s prohibition due use of responsible that M. was not (5) adhesive; asphalt roofing as a added). delays.” (emphases *4 days searching for lost time while for a follow-up correspon- There was no to this August metal fabricator. Id. On Maropakis dence either not party. did 28, 2001, Nihoff, the contracting James separate file a regarding formal claim Officer”) on (“Contracting Maro- time extension. pakis’s responded August to the 20, Navy On December 2002 the issued by stating 20 letter that to Robertson Final Decision # 03-002F which reiterated Maropakis “present[] sufficient government’s for liquidated demand

justification to warrant time extension” damages. The characterizes requested. Contracting Id. The Officer this letter as a final decision pertaining rejected requested extensions, each for Navy’s liquidated demand noting that, among problems, some damages. Maropakis contends that this delay of the dates of overlapping. were letter was a final decision applying to each closing, Contracting Officer invited previous requests its extension Maropakis to “submit additional informa- period. the contract in support request tion” of its and stated letter is a Final Decision “[t]his activity There was no further by either Contracting Officer.” Id. at 192. party until Maropakis complaint filed on 17, December 2003 in 28, the Court of Federal 2002, Navy On June sent Maro- (1) letter, alleging Claims breach of pakis contract due pointing another out government delay Maropakis seeking resulting “responded had neither [to the (2) extensions, August 2001 time letter] with additional infor- breach of contract “requested mation” nor a Contracting government’s due to the Offi- assessment of cers final decision for [sic] these matters.” seeking remission The $303,550. letter also indicated that the gov- full Compl., Amended ¶¶ payments ernment had made 50-52, 54-55, M. Maropakis, 84 Fed.Cl. $244,036 $1,053,115, in the amount of less government responded by The as- $1,297,151. than the price total contract $59,514 serting a counterclaim for the bal- Finally, informed ance it was the government contended due it liquidated damages would owe in liquidated damages. On October $303,550 day representing per for the $650 2008, the Court of Federal granted Claims days in completing pro- motion to Maro- dismiss ject. Navy The applied this amount pakis’s claim for time extensions for lack of balance, the remaining contract subject-matter jurisdiction, finding that $244,036, resulting in a total due from had not submitted “claim” for $59,514. Maropakis of required contract modification as under Maropakis responded in a Federal July letter on CDA. Court of Claims 22, 2002 reiterating request granted its earlier motion but mentioning summary extension specifically judgment as its counterclaim Time II. Extensions issue. Maro- on the decisions, arguing that appeals both pakis case parties dispute letter was sufficient July its Maropakis submitted valid whether addi- the CDA. In a claim under constitute contracting to its offi for time extensions tion, argues that give sufficient to the Court Federal cer comply with required to jurisdiction over issue. Under assert prerequisites CDA, of Federal Claims has the Court for a time extension actions filed within twelve jurisdiction over liqui- counterclaim for officer’s decision months dated 609(a). § This claim. jurisdiction under 28 U.S.C. We have has found that thus re 1295(a)(3). both claim and a quires a valid decision on that

officer’s final Discussion M. James Ellett Constr. Co. (Fed.Cir. 1541-42 Standard of Review I. *5 1996). the CDA itself does not de Since novo the decision review de We “claim,” the term we look to the Fed fine dismiss the Court of Federal Claims to (FAR) Acquisition Regulations imple eral Corp. jurisdiction. lack of Radioshack menting for the definition. See the CDA (Fed. States, 1358, 566 1360 v. United F.3d Dalton, 1572, Reflectone, Inc. v. 60 F.3d Cir.2009). bears the burden plaintiff A (en banc). (Fed.Cir.1995) FAR 1575 subject-matter jurisdiction by establishing “a demand or defines “claim” as: written Reyn of the evidence. preponderance a by contracting assertion one of the written Serv., Exch. 846 Army v. & Air Force olds right, as a matter of parties seeking, (Fed.Cir.1988). 746, F.2d 748 certain, money a sum payment grant novo also review de We adjustment interpretation of contract or judgment by the summary Court terms, arising or relief or under Claims, justifiable factu “drawing Federal 48 relating to the contract.” C.F.R. party opposing in favor al inferences a not be 33.201. While CDA need judgment” stan reapplying and any particular form or use submitted applicable proceedings before the dard wording, “a any particular it must contain Island Long of Federal Claims. Court gives unequivocal clear and statement that States, Bank, 503 Savs. FSB United contracting adequate officer notice (Fed.Cir.2007). 1234, In the F.3d 1244 amount of the claim.” the basis and Con Claims, moving of Federal once the Court Maint., Cleaning Inc. v. tract United satisfy forward with evidence party comes (Fed.Cir.1997). States, 586, 811 F.2d 592 burden on a motion for sum ing initial a requires The CDA also that mary opposing judgment, party contracting to the officer claim indicate creating a present motion must evidence is requesting the contractor a final that Id. issue of material fact. genuine (“Besides Ellett, 93 decision. F.3d at particular permitted a Whether claim, meeting FAR of a law, definition question a under CDA also claims requires that all be sub de See Frazer v. which review novo. (Fed. States, contracting officer for a [fi mitted 288 F.3d decision.”). Cir.2002) “This require does reviews (holding nal] that “this court decision, request long a as including explicit final legal novo all determinations” de by its sub- tolling). what the contractor desires equitable the defense (inter final agree Maropak- missions is a decision.Id. Fed.Cl. We omitted). quotation nal marks These re July letter of is’s 2002 was suffi- quirements are of the CDA provide ad- cient to any appeal. England v. prerequisites equate notice the basis and amount of Swanson, (Fed.Cir. 1375, 1379 358 F.3d and therefore does not 2004). Thus, for the Federal satisfy the CDA. As noted the trial jurisdiction to have under court, specifically this letter mentioned CDA, proper must the contractor submit 107-day re- previously extension (1) claim—a written demand that includes quested. did The letter not state the adequate notice basis and amount of days requested total number of in exten- (2) request a claim for a final deci request sion final decision. addition, In sion. the contractor must fact, appears promise have received the officer’s final claim, forthcoming written which never Ellett, decision on that claim. at materialized. A claim cannot be based 1541 — 42. merely on intent to assert claim without

In its complaint, Maropakis alleged it any communication contractor of was entitled to because of various for a contracting desire officer decision. “delays, impacts disruptions” by Corp., See Transamerica Ins. Inc. v. Unit- government. Maropakis, M. 84 Fed.Cl. at (Fed.Cir. ed 184. The Court of Federal Claims found 1992), part by Reflectone, overruled in subject it lacked matter (holding F.3d 1572 quali- submissions *6 over this claim for time extension because fied as CDA claims when the contractor Maropakis require- had not the satisfied writing “asserted in and with sufficient ments of the CDA. The trial court thor- specificity right compensa- additional oughly analyzed each communication be- tion” and “the contractor communicated tween the government and his desire for a officer deci- them, found that none of either alone or in sion”); Mingus Constructors Inc. v. Unit- combination, contained a clear and un- (Fed.Cir. 1387, ed 812 F.2d 1394 equivocal qualify statement sufficient to as 1987) (finding that indicating letters a claim. Id. at 196-203. intent to file a claim in the future for an appeal, Maropakis

On argues that unspecified amount not were claims as de- July 22, of sufficient 2002 was by the fined contract where the contractu- Specifi constitute a claim under the CDA. al definition of claim substantially the cally, Maropakis argues that because the same as the FAR definition: “a written July 2002 product letter “was the of demand or parties assertion one of the continuing parties discussions between the seeking, a legal right, as the payment of concerning the assessment of liquidated money, adjustment or interpretation of damages Project delay, cause terms, relief, or other arising un- give letter was sufficient to contract”). relating or der to this adequate notice of Mar the basis of argues if even opakis’s Maropakis’s Principal claim.” Br. it compliance was not in technical with the at found, however, 20-21. trial CDA, best, the United States had actual knowl a generous “[a]t reading 22, 2002, edge of the amount July Maropak and basis of correspondence can inter preted Maropakis’s is’s claim and request for final therefore the Court Fed jurisdiction. However, decision on the liquidated eral Claims had damages assessment.” M. Maropakis, Maropakis provides 84 no evidence that

1329 provide Contracting not on actual no- did Officer placed was ever days of the total adequate of ex- notice number specific number tice extension, actually requested in it did ultimately days would tension certain, it Instead, state Maropakis points to sum request. request dam- a final decision. The demand for absence request to notice and the failure to a final and asserts that since refers ages letter, jurisdictional impairments July gov- decision were 2002 Ellett, fully aware that least the for a under CDA. ernment was Moreover, 107- at 1541-42. while assessed F.3d techni- amount compliance in cal with certification not a day dispute. extension was jurisdictional prerequisite litigation of a assuming govern Even CDA, contractor’s claim under the it is a knowledge Maropakis’s conten ment’s requirement to the maintenance such an in along way, nothing there is tions 605(c)(6); § see action. U.S.C. Shar- compliance that excuses contractor man, Here, addition to requirements. CDA claim explicit with above, noted defects (requiring that “[a]ll See Maropakis’s letter was not certified. govern claims a contractor Because did meet relating to a contract shall be ment jurisdictional prerequisites of a claim writing,” be submitted the con “shall against the government for contract modi- decision,” tracting officer for and “[f]or CDA, fication under the the Court Fed- $100,000, the of more than contrac claims correctly Maropak- eral Claims dismissed claim”). Indeed, certify [ ] tor shall breach of contract is’s lack of recognized have that the CDA a statute jurisdiction. waiving sovereign immunity. Winter FloorPro, (Fed. Inc., Liquidated Damages III. Cir.2009). sovereign immuni A “waiver of Maropakis also claimed that strictly favor of ty must be construed *7 government’s damages assessment of was States, 545 sovereign.” v. United Orff in full. improper sought its remission 596, 601-02, 2606, 162 125 S.Ct. U.S. made a motion for sum (2005). “must L.Ed.2d 544 Such waiver mary judgment on this claim and on its expressed statutory unequivocally be for corresponding counterclaim the as v. implied.” text and will not Lane liquidated damages. The sessed Court Pena, 187, 192, 116 U.S. S.Ct. Federal Claims found that omitted). (1996) (citations 135 L.Ed.2d 486 “failed to a material issue as to establish Thus, we limits of have enforced the “strict liquidated government’s whether the dam ‘jurisdictional prerequisites to the CDA as ” an ages provision penal was unenforceable any appeal.’ England, 353 F.3d at 1379 granted It States, ty.” govern therefore (quoting Sharman Co. v. United motion, summary judgment finding (Fed.Cir.1993), ment’s F.3d 1568-69 n. 6 for Maropakis liable the retained balance grounds by Reflectone, overruled on other $59,514 1572). an of the contract and additional Maropakis’s argument that Maropakis, 84 liquidated damages. M. may ignore this court at 208. requirements based on Maro Fed.Cl. CDA knowledge by the pakis’s allegations of appeal, Maropakis argues that “the On without government is merit. Maropakis’s did not consider factual Court Maropakis’s Principal Br. at Maropakis’s July was defenses.” Maropakis argues right its a valid under the CDA because However, against government’s require assert a defense certification. claim for means Claims Court nevertheless concluded requirements jurisdiction that would other- that it did not have over the apply Maropakis’s wise dispute affirmative the government because had not claim for entitlement to time extensions no made a final decision on its claim and thus longer apply and can raise had itself not made a valid CDA claim. On appeal, these issues to defend determined that the disagree. claim. We effectively ment’s officer had made a final decision on claim notwithstanding Placeway relies on Construc the fact that the contracting officer re- Corp. tion the authority served redetermine (Fed.Cir.1990), authority the propo for amount the setoff upon claimed based sition that a valid CDA claim is not re receipt of additional information on the quired prior raising excusable as a actual costs incurred government. government’s liquidated defense to the Therefore, Id. at 906-07. we concluded However, damages Placeway claim.1 jurisdiction that the Claims Court did have support decision does not such a In rule. over the liquidated Placeway, the contractor had submitted a However, Id. we did not ad- payment unpaid written demand dress whether the juris- Claims Court had $297,226 contract balance of con any diction over Placeway’s defenses. tracting officer along with other demands for payment. case, Placeway’s de In this there is no dispute that the mands, like Maropakis’s requests, were Court of Federal Claims had not valid claims under the CDA. Id. over relating liqui- demands, response Placeway’s con dated and the cor- tracting officer refused to con responding release the counterclaim. parties tract balance Placeway agree because had failed dam- to complete the “in timely ages man a government claim that did not Placeway ner.” Id. a complaint require filed in the certification and that the contract- seeking, among ing officer properly made a final decision amounts, the contract price balance. The on issue. The Court of Federal Claims United States Claims Court determined correctly Placeway found that no had that the to keep bearing decision requirements CDA’s contract balance awas claim contractor claims. M. Maropakis, 84 Fed. *8 as opposed to a contractor claim and thus Cl. at 204. Several other Court of Federal agrees 1. argu- The dissent with der Navy’s the contract" and "whether the Co., citing inspection directives under the ment contract’s Garrett v. General Electric Garrett, appealable clause are CDA claims.” (Fed.Cir.1993) authority as 987 F.2d at 749. The Court found that this for the assertion that claims and are defenses government was a claim over which the However, Op. distinct. at 1326. is Garrett correctly Board determined it had inapposite. The issue in Garrett was whether despite Navy’s nonmonetary the choice of a Appeals jurisdic- the Board of Contract had remedy. Gairett did discuss de- GE’s contracting tion a over officer’s decision that government fenses to the at claim issue or problem GE must correct a under a contract whether those defenses themselves involved at Navy though no additional cost the to even contractor claims that must adhere to the GE submitted no claims itself to the contract- Therefore, requirements of the CDA. Ganett Thus, ing by officer. the issue addressed Placeway support like does not rule the advo- this Court in Garrett was whether the Board by agreed by cated and to "jurisdiction Navy’s had over the un- claims dissent. language statutory The directly addressed this cases have in a explicit requiring CDA is contractor to that even and have all concluded issue make valid claim to the offi a government used as a defense to when prior to that claim. The litigating cer claim, a contractor’s requirement is to purpose of this encour jurisdic must adhere to modification age disagreements of at the the resolution Sun Ea requirements of the CDA. tional thereby saving level States, 23 Cl.Ct. Corp. v. gle United expense litigation. parties the See both (1991) (“This court holds 33.204; Reflectone, at 48 C.F.R. challenging government is plaintiff point any does not to making its damages and own liquidated to provides exception an authority amounts with claim to recover contractor when a requirements CDA claim contrac The latter held tor’s claim for contract modification is certified.”)2 added); (emphasis must government made in defense Builders, Elgin Inc. And no create we see reason to such an (1986) that “where (stating Cl.Ct. Thus, exception. that a hold contractor contest the ... the contractor seeks to adjustment seeking an of contract terms liquidated damages by assessment jurisdictional requirements must meet claiming extensions or entitlement time CDA, procedural prerequisites relief, is with a presented the court asserting against whether the claim govern against contractor government an affirmative claim as or as presented and that must first be ment to a action. the contractor’s defenses the CO” and of, Here, “limited to the nature such case are Federal Claims cor- in, the assessment present rectly required comply and the issues with is, example, to contest that requirements notwithstanding itself—that comple Maropakis’s styling its claim any there was as a de- tion”). fense to a counterclaim for 605(c). portions quotes this need 2. The dissent same tion not address issue, language Eagle describing in Sun when as the case is in settlement. However, proposition adversely are that claims and defenses dis- the issue were resolved if However, dissent, Op. tinct. plaintiff, would result call for ignores claims, respect, all the actual with due hold- all contractor dismissal itsof ing Eagle, Sun which states follows: jurisdiction only the court would retain over practical claim. As a conse- bar, plaintiff seeking In the case agree quence, plaintiff likely would adjustment monetary contract terms or stay government claim while it recer- relief because it defends the assess- claims, tified its contractor obtained a con- on the ment basis thereon, tracting officer and refiled decision Army delay. The that the caused the Claims Court. That action would be claim the contractor. contrac- joined proceed- with the action instant and, tor made the claim in claim letter if ings expedited *9 scheduled basis. recovers, the CDA award the con- would added) (emphases Eagle, Sun 23 Cl.Ct. at 482 its s tractor interest on claim. con- Plaintiff (internal Thus, omitted). Eagle citations Sun required certified, tractor claim must be as dissent, not, 605(c). by support does the as stated the plaintiff by 41 this case proposition prerequi- that the absence CDA certify did its claim. Defendant asserts that government Maropakis’s sites on claims the certification is insufficient because the delay right bar to does not its raise them certify that the data contractor failed government's liquidated the dam- supporting defense of its claim were "accurate and Instead, ages Eagle complete Sun stands for the to the best the contractor’s belief,” by required opposite. knowledge sec- exact inquiry granted permitting the as to liquidated damages. Because Court of without correctly held that it did its merits and defenses. Federal Claims jurisdiction not have over contract, During performance of the extensions, and claim time because for requested exten- Maropakis had various claim was the Maropakis’s extension time, in light perform- sions various against the defense asserted government does not delays. ance liquidated damages, for counterclaim delay.1 deny My that it had role in grant summary judgment affirm the colleagues’ ruling that the court does not on its counterclaim for government the jurisdiction” “subject have matter of the government that contractor’s defense the delay, the on the contributed to is based Conclusion theory Maropakis that “had not submitted of Federal determi- The Court Claims’s a ‘claim’ for contract as re- modification jurisdiction nation it lacked over Mar- that quired Maj. Op. under the CDA.” opakis’s claim for breach contract is My hold colleagues that the courts are We affirm the affirmed. Court of deprived no sepa- because grant summary judg- Federal Claims’s modify rate claim to the contract was government the on its ment to counter- However, Maropakis seeking made. not is liquidated damages. claim for Maropakis contract reformation. Nor is AFFIRMED seeking damages compensa- or additional Maropakis simply raising tion. is an ob- Dissenting by opinion Circuit filed jection to the merits of the Judge NEWMAN. delay damages, defending claim for on the NEWMAN, ground Judge, dissenting. government Circuit that the had contribut- ed to the delay. The court holds that the contractor M. barred,

Maropakis Carpentry, question Inc. is not whether appeal Court of Federal Claims of could have or should have submitted grant gov- officer’s sort of some contract modifica- tion; delay damages, question ernment’s from is whether against by permitted that defending showing against to defend government caused and contribut- ment’s claim for ma- damages. The delay. my colleagues grant jority ed to the Thus cites the FAR’s inclusion of “the summary judgment government adjustment on ... contract terms” in the $303,550 delay damages, However, its claim for definition of “claim.” this defini- theory subject requires the court tion does not mean that FAR “lack[s] jurisdiction” government presented matter consider de- contract be fense that had raised with the before a modification contractor can Contracting government Officer. I do not share defend arising Indeed, “jurisdiction” performance. view that there is no from con- sider the defense to the did require Maro- claim, whereby pakis claim was summarily request to file a modifi- exist, disputed specified 1. It that the change specifica- ordered cessation of all work and did not refused to tions, proceed authorize to remove the time the windows were removed, paint days discovery lead until paint after custom and the lead made *10 paint Maropakis. by disputed performance It not the was entire time set in contract elapsed. when found that had windows to on GE submitted no claims the CO in for the order cation requests engine at the Maropakis’ various defects time of to consider however, time. performance Act, provides extensions for decision. simply denied requests were These may appeal that a contractor Govern- substance, to relating various reasons to appropriate ment claim board procedure. submitting without a claim its own to Thus, only jurisdiction the CO. over the juris- is within tribunal’s

When claim Navy’s claims at under contract are diction, government’s like the appeal. in this issue routinely tribunal has delay damages, the to the consider defenses to (citation omitted). at 749 This hold- any by This is not negated claim. rule ing by is contravened the court’s decision Act. Disputes provision the Contract today, although jurisdiction govern- my colleagues Yet sustain the delay government’s damages monetary and its sizable ment’s CDA claim requires sep- now undisputed, court award, imposing permitting no and arate basis for the contrac- have been stat- negated obstacles that objection government’s to the claim. tor’s my col- precedent. example, For ute and Placeway Corp. v. Construction United required hold that leagues was (Fed.Cir.1990) States, 920 F.2d 903 arose defense, “certify” as if it were a its to analogous facts those of Maropakis. on contrary. monetary Precedent claim. Placeway, appeal In was from the colleagues hold that was My contracting officer’s decision not to release that it is required state a “sum certain” balance, government the contract as however, claiming; Maropakis is not claim- serting Maropakis, Like sum; objecting ing a it is the defense that the the contractor raised raising the government, claimed delay. had caused some government contributed defense that Placeway Corp. v. Constr. See delay. my colleagues And hold to the (1989), 159, 162 in 18 Cl.Ct. aff'd seek required somehow was remanded, part, part, vacated before and obtain “contract modification” (Fed.Cir.1990). court F.2d 903 This defense; this this curious it could raise with agreed support. theory is devoid of withholding Co., Electric Garrett v. General as a its claim for balance setoff (Fed.Cir.1993), the court consid- delay damages was whether the directive ered Placeway, 920 F.2d at 906. Because certain work the contractor to do remedial gov on the officer’s decision expense was a contractor’s final, jurisdiction was ernment was was, “claim”; court that it ment held despite of a proper, the absence contractor appeal and that the contractor could complying procedures in with CDA objections filing sepa- its without raise is, the cluding That contrac certification. “claim” own. was rate of its Jurisdiction recovery complaint seeking tor’s claim, not the based not a balance was contractor This objection contractor’s that claim. claim, require and did not certification. holding that the con- explicit today court’s conflicts with ruling This own did not have submit its tractor holding Placeway.2 claim: Maj. precisely Placeway Op. That is majority posits that dealt defenses. 2. The claims, contractor with *11 Indeed, explored Maropakis’ decisions have various whether re- Other several a claim time aspects quests difference between extensions met the CDA’s defense, particular requirements facts and cir- “claim” and a is irrelevant —al- boundary. though cumstances have tested the these letters stated that con- Eagle Corp. dispute any 23 Cl. Sun United tractor would assessment (1991), explained delay damages. the Claims is not Ct. Court The issue here required that while certification is of a Maropakis perfected monetary whether a own, claim payment contractor’s under the claim of its but whether is contract, for it constitutes a “contractor permitted against gov- to be to defend claim,” government a defense to a claim claim. precedent ernment’s No rule or Eagle not be need certified. The Sun right holds that contractor forfeits summarized: if it does not file its own claim. Placeway held that a chal- contractor’s court is misguided ruling And the in its government to a lenge claim need not be government’s that damages plaintiff This court certified. holds against cannot defended the con- unless challenging government claim to tractor first proce- undertakes the formal making its own dures of modification. In Ganxtt contractor to recover amounts explained “pro- this court the CDA liquidated damages. withheld for The may vides that contractor appeal Gov- latter must be certified. ernment to the appropriate board submitting a without claim of its own to 987 F.2d at CO.” 749. See also 41 respects Precedent the distinction be- 609(a)(1) (“[I]n lieu appealing a claim My tween and a col- defense. agency board, ... may to an a contractor leagues’ quotation opin- selective from the bring directly an action on the claim the Eagle, Maj. ion in Sun n. Op. at 1331 Claims, States of Federal implements holding Eagle Sun notwithstanding any provision, the contractor’s indeed a or regulation, rule of the con- law to “claim,” letter,” made “in a claim 23 Cl.Ct. trary.”). No statute or rule withholds sub- The Eagle Sun court then held ject matter from actions such that since the contractor had made such a when the contractor challenges a claim, it needed be certified. The court ment claim. explicitly did not hold that a contractor raising defense to a government that it dispute jurisdictional meet the requirements “must owed the unpaid balance of the CDA,” procedural prerequisites contract, and the contracting rec- officer’s Maj. Op. at 1331. The routine defense ognition obligation appealed. of that is not that the delay contributed to grant issue is the summary defense, is a not a judgment contract modification. for the Failure to meet requirements claim, the CDA in the while certification, naming certain, “jurisdictional” a sum re- denying, on Mar- grounds, questing decision, final modifying or opakis’ right right of defense. The contract, preclude does not defending against defend adverse claim is not a “jurisdiction,” matter of nor grace; point: Placeway juris- this court based have a does not dimension. claim; diction on the a defense *12 right, of that right. The denial matter of theory on a by the argued by the supported that was

“jurisdiction” sup- and is now Federal Claims court, contrary this

ported CDA, contrary prece-

purposes upon

dent, principles affront to the and an I re- were founded.3 courts

which these

spectfully dissent. INC., DESIGN, Tru

MICHAEL SIMON Arriviste), (Doing Business as Inc. Stores, Tar Target a Division of Plaintiffs-Appel Corporation,

get

lants, Defendant-Appellee. STATES,

UNITED

No. 2009-1571. Appeals, Court of

United States

Federal Circuit. 18, 2010.

June (Dec. 1861), Message en- duty First Annual of Government "It is as much itself, courthouse, prompt justice graved in favor render at the entrance to same, citizens, NW, it is to administer Washington, DC. Place Madison Lincoln, private A. individuals.” between

Case Details

Case Name: M. Maropakis Carpentry, Inc. v. United States
Court Name: Court of Appeals for the Federal Circuit
Date Published: Jun 17, 2010
Citation: 609 F.3d 1323
Docket Number: 2009-5024
Court Abbreviation: Fed. Cir.
AI-generated responses must be verified and are not legal advice.