History
  • No items yet
midpage
6 F.4th 1321
D.C. Cir.
2021
Read the full case

Background

  • FERC approved construction and operation of three LNG export terminals on the Brownsville Shipping Channel (Rio Grande, Texas, and Annova) and related pipelines; petitioners (residents, environmental groups, and a nearby city) sought rehearing and then judicial review challenging NEPA, APA, and NGA issues.
  • Annova abandoned its project before argument; that petition was dismissed as moot.
  • Petitioners argued FERC’s EISs inadequately analyzed (1) greenhouse gas (GHG) impacts—claiming FERC should have used the social cost of carbon or another accepted method under 40 C.F.R. § 1502.21(c); and (2) environmental justice impacts—challenging FERC’s choice to limit analysis to census block groups within two miles despite finding air impacts could extend far beyond that radius.
  • The court held FERC’s greenhouse-gas analysis deficient for failing to address the significance of 40 C.F.R. § 1502.21(c) and failing to engage opposing viewpoints about use of the social cost of carbon; it also held the environmental-justice analysis arbitrary for the unexplained two-mile delimitation.
  • Because FERC’s public-interest determinations under Sections 3 and 7 of the NGA depended on those defective NEPA analyses, the court remanded those determinations as well.
  • Remedy: remand without vacatur (court found defects likely remediable and vacatur would be disruptive).

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Adequacy of GHG analysis under NEPA (use of social cost of carbon / 40 C.F.R. § 1502.21(c)) FERC had to use the social cost of carbon or another generally accepted method under § 1502.21(c) because the agency said impacts couldn’t be quantified by other means. FERC said no consensus on discount rate, tool doesn’t show project-level incremental physical impacts, and no monetary threshold for "significant." Court: FERC’s analysis was deficient for failing to address § 1502.21(c) and opposing viewpoints; on remand FERC must explain whether and how to apply the social cost of carbon or another accepted method or explain why not.
Environmental justice scope (geographic delineation) Limiting EJ analysis to census blocks within two miles was arbitrary given FERC found some air impacts could reach ~31 miles. FERC did not adequately justify the two-mile boundary in the rehearing order. Court: Arbitrary—FERC must justify the two-mile boundary or analyze a broader area and reassess findings that affected populations are minority/low-income and that impacts are not disproportionate.
NGA public-interest determinations (Sections 3 & 7) FERC’s public-interest/convenience findings are invalid to the extent based on the deficient NEPA analyses. FERC relied on its EIS conclusions; those EIS conclusions were challenged. Court: Because NGA findings rested on flawed NEPA analyses, those determinations must be reconsidered on remand.
Remedy (vacatur vs. remand) Petitioners sought vacatur; intervenors argued remand without vacatur to avoid project disruption. Intervenors argued vacatur would disrupt financing and project completion; defects likely fixable. Court: Remand without vacatur—deficiencies are remediable and vacatur would cause undue disruption.

Key Cases Cited

  • Sierra Club v. FERC, 827 F.3d 36 (D.C. Cir. 2016) (describing DOE/FERC roles for LNG export and facility approvals)
  • Sierra Club v. FERC, 867 F.3d 1357 (D.C. Cir. 2017) (NEPA EIS must force an agency to take a "hard look" and disclose analysis)
  • Motor Vehicle Mfrs. Ass'n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (arbitrary-and-capricious standard for agency action)
  • TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1 (D.C. Cir. 2015) (agency must address opposing viewpoints in NEPA analysis)
  • EarthReports, Inc. v. FERC, 828 F.3d 949 (D.C. Cir. 2016) (discussing FERC’s past refusals to use the social cost of carbon)
  • Cmtys. Against Runway Expansion, Inc. v. FAA, 355 F.3d 678 (D.C. Cir. 2004) (environmental justice analysis reviewable under NEPA/APA)
  • Williams Gas Processing–Gulf Coast Co. v. FERC, 475 F.3d 319 (D.C. Cir. 2006) (agency decision that rests on an infirm ground is arbitrary and capricious)
  • Black Oak Energy, LLC v. FERC, 725 F.3d 230 (D.C. Cir. 2013) (vacatur/remand balancing test: remediability and disruptive consequences)
  • Nevada v. Dep’t of Energy, 457 F.3d 78 (D.C. Cir. 2006) (NEPA review standard; scope of appellate review)
Read the full case

Case Details

Case Name: Vecinos para el Bienestar de la Comunidad Costera v. FERC
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Aug 3, 2021
Citations: 6 F.4th 1321; 20-1045
Docket Number: 20-1045
Court Abbreviation: D.C. Cir.
Log In