SIERRA CLUB and Galveston Baykeeper, Petitioners v. FEDERAL ENERGY REGULATORY COMMISSION, Respondent American Petroleum Institute, et al., Intervenors.
No. 14-1275
United States Court of Appeals, District of Columbia Circuit.
June 28, 2016
Argued November 13, 2015
* * *
For those reasons, the question of administrative exhaustion is moot. We accordingly reverse and remand to the district court for further proceedings consistent with this decision.
So ordered.
Robert H. Solomon, Solicitor, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were David L. Morenoff, General Counsel, and Karin L. Larson, Attorney, Washington, DC.
Jonathan S. Franklin, Washington, DC, argued the cause for respondent-intervenors Freeport LNG Development, L.P., et al. With him on the brief were Lisa M. Tonery, New York, NY, and Charles R. Scott, Shreveport, LA.
Before: ROGERS, GRIFFITH, and MILLETT, Circuit Judges.
MILLETT, Circuit Judge:
The Sierra Club and Galveston Baykeeper (the “Associations“) take issue with the Federal Energy Regulatory Commission‘s decision authorizing Freeport LNG Development, L.P. to redesign its liquefied natural gas terminal in Texas to support export operations. Specifically, the Associations argue that the Commission‘s analysis of the proposal‘s impact on the environment ran afoul of the National Environmental Policy Act of 1969 (“NEPA“),
I
A
Export authorizations for natural gas implicate a tangled web of regulatory processes. The Department of Energy maintains exclusive authority over the export of natural gas as a commodity.
The Department has delegated to the Federal Energy Regulatory Commission the authority to “[a]pprove or disapprove the construction and operation of particular [export] facilities, the site at which such
In addition to those public-interest determinations, authorizations to export natural gas also require an environmental review under NEPA. See
In analyzing the environmental impact of a project, NEPA obligates the agency to consider not just the “direct” environmental effects of the proposed action that “are caused by the action and occur at the same time and place,” but also the action‘s “indirect” environmental effects that “are caused by the action and are later in time or farther removed in distance, but are still reasonably foreseeable.”
Notwithstanding the limited scope of the Commission‘s delegated authority under the Natural Gas Act, that Act designates the Commission to be “the lead agency for the purposes of coordinating all applicable Federal authorizations and for the purposes of complying with the National Environmental Policy Act.”
B
In 2004, the Commission authorized Freeport to site, construct, and operate a liquefied natural gas import terminal on Quintana Island in Brazoria County, Texas. That facility was placed into service in 2008.
As it happens, an increase in the availability of cheap domestic natural gas during the last decade caused the market for importing gas to decline. As a result, Freeport shifted its operations toward exporting and, in 2009, obtained authorization from the Commission to operate its existing terminal facility for both exporting and importing natural gas on a short-term basis. In 2011 and 2012, Freeport sought authorization from the Commission both to modify its facilities to better support gas exports, and to construct additional gas liquefaction facilities to supplement its export operations. (Throughout this opinion, we refer to those two projects collectively as the “Freeport Projects.“).
As required by the Natural Gas Act and NEPA, the Commission undertook an extensive environmental review of the Freeport Projects. Deeming the two projects to be “connected actions,”
Meanwhile, in 2010 and 2011, Freeport separately sought authorization from the Department of Energy to export natural gas. The Department approved Freeport‘s request for free-trade agreement countries in February 2011, and conditionally approved Freeport‘s application with respect to non-free trade agreement countries in May and November 2013. The conditional order explained that the Department of Energy would participate in the Commission‘s ongoing environmental review of the Freeport Projects as a cooperating agency, and that the Department‘s final authorization would be contingent on satisfactory completion of that environmental review process.
The Commission released its Final Environmental Impact Statement in June 2014. That Statement found that the Freeport Projects “would result in some adverse environmental impacts,” but that those impacts would be “mostly temporary and short-term” as long as Freeport implemented mitigation procedures proposed by the Commission. The following month, the Commission conditionally authorized both Freeport Projects. After considering the Final Environmental Impact Statement and all substantive public comments, the Commission determined that, if Freeport complied with specified environmental conditions, the Projects would not be inconsistent with the public interest.
The Associations intervened in the Commission‘s proceeding and timely sought rehearing. As relevant here, they argued that the Commission failed (i) to consider the indirect environmental effects of a possible increase in domestic natural gas production being induced by the Freeport Projects, and (ii) to analyze the cumulative environmental effects of those Projects with “the many proposed export projects” across the country, including, “at a minimum,” those already authorized and “all other export projects to have received conditional authorization from” the Department of Energy. J.A. 1250, 1273.
The next day, the Department of Energy issued its final order authorizing Freeport to export natural gas to non-free trade agreement countries. The Department reconfirmed its findings from the earlier conditional order, and also addressed “the remaining issue: the potential environmental impacts” from Freeport‘s export proposals. J.A. 1403. The Department concluded that “the proposed exports have not been shown to be inconsistent with the public interest.”
II
We start where we must always start: “with the question of our jurisdiction.” Brotherhood of Locomotive Eng‘rs and Trainmen v. Surface Transp. Bd., 457 F.3d 24, 27 (D.C. Cir. 2006). The Commission argues that we lack jurisdiction because the Associations do not have standing, and because their NEPA claim has been mooted by additional environmental analyses conducted by the Department of Energy as part of its own public-interest review. Neither argument succeeds.
A
An association will have standing if “(1) at least one of its members would have standing to sue in [its] own right, (2) the interests the association seeks to protect are germane to its purpose, and (3) neither the claim asserted nor the relief requested requires that an individual member of the association participate in the lawsuit.” Sierra Club v. EPA, 292 F.3d 895, 898 (D.C. Cir. 2002). There is no dispute that the environmental claims the Associations assert are germane to their institutional purposes, or that the relief sought under the Administrative Procedure Act does not require the participation of individual members. The question of individual-member injury is where the rub is.
It is settled law that “an agency‘s failure to prepare (or adequately prepare) an [Environmental Impact Statement] before taking action with adverse environmental consequences” constitutes the “archetypal procedural injury” redressable under Article III. WildEarth Guardians v. Jewell, 738 F.3d 298, 305 (D.C. Cir. 2013); see Florida Audubon Society v. Bentsen, 94 F.3d 658, 665 (D.C. Cir. 1996) (en banc). The bottom-line standing question in this case, then, is whether one of either Association‘s members faces a concrete injury that is “tethered to” the Commission‘s decision to authorize the Freeport Projects’ construction or operation notwithstanding the Commission‘s allegedly inadequate NEPA review. WildEarth Guardians, 738 F.3d at 305. See also Florida Audubon Society, 94 F.3d at 668.
At least one Sierra Club member has risen to that task, and that is all that Article III requires. See Massachusetts v. EPA, 549 U.S. 497, 518 (2007) (“Only one of the petitioners needs to have standing to permit us to consider the petition for review.“);
The Commission says that is not enough, and that the Associations also must tie their injury to the specific “increase[]” in “natural gas production that was [allegedly] caused by the challenged FERC orders.” Resp. Br. 24. That argument “slice[s] the salami too thin.” WildEarth Guardians, 738 F.3d at 307. As we have held before, we hold again: it is sufficient for standing purposes that the “aesthetic injury follows from an inadequate [Environmental Impact Statement] whether or not the inadequacy concerns the same environmental issue that causes their injury.”
That is to say, regardless of how the Commission allegedly failed to discharge its NEPA obligation, that failure led directly to authorization of the Freeport Projects, which in turn is the source of Cornelison‘s injury. The proof is in the pudding: if we were to vacate the Commission‘s order authorizing the Freeport Projects for violating NEPA, not only would Cornelison‘s injuries be redressed, the remedy would also be ” ‘limited to the inadequacy’ here, a deficient [Environmental Impact Statement]—‘that produced the injury in fact that the [petitioners] ha[ve] established.’ ” WildEarth Guardians, 738 F.3d at 307 (quoting DaimlerChrysler Corp. v. Cuno, 547 U.S. 332, 353 (2006)).
The Commission‘s reliance on National Committee for the New River, Inc. v. FERC, 433 F.3d 830 (D.C. Cir. 2005), fares no better. That case, which did not involve NEPA, held that the environmental and aesthetic harms alleged had to be linked to “the route realignments themselves” because route realignments were what the challenged agency action authorized.
B
Next is mootness. In 2014, the Department of Energy, “in response to chal-
That argument woefully misunderstands the Associations’ claim. They do not seek some quantum of additional environmental information for its own sake, nor are they, in this case, challenging the Department of Energy‘s analysis of environmental consequences. Their argument is that the Commission bungled its NEPA review by failing to consider the specific indirect and cumulative effects that the Associations identified. The Department of Energy‘s additional reports do not remedy that problem. See Pet. Reply Br. 9 (“The Department of Energy‘s reports played no part in the Commission‘s decision-making, and did not include the procedures and substance required under NEPA to ensure that environmental considerations inform such decision-making.“). The Associations’ hope is that, if the Commission were to consider those factors, perhaps it would reach a different conclusion on whether the Freeport Projects are consistent with the public interest. After all, “[t]he idea behind NEPA is that if the agency‘s eyes are open to the environmental consequences of its actions and if it considers options that entail less environmental damage, it may be persuaded to alter what it proposed.” Lemon v. Geren, 514 F.3d 1312, 1315 (D.C. Cir. 2008).
In short, because the Commission‘s NEPA analysis was an integral component of authorizing the export construction projects—without which the Department of Energy‘s separate export authorization would be pointless—and because, if error occurred, the Commission might come to a different result on remand, the lawfulness of the Commission‘s action remains very much a live legal issue.
III
Before addressing the merits of the Associations’ NEPA claim, we pause to underscore what we are not deciding in this case. Because the Associations do not challenge the propriety or scope of the Commission‘s delegated authority under the Natural Gas Act, or the interplay between the Commission and the Department of Energy when the former is acting as the “lead agency” in reviewing the environmental effects of a natural gas export operation under NEPA, we take those agency roles as we find them. See
We also express no opinion on whether (i) the Commission‘s environmental analysis would have been adequate to satisfy the Department of Energy‘s own independent NEPA obligation in authorizing Freeport to export natural gas; or (ii) the Commis-
Accordingly, we limit our analysis in this case solely to whether the Commission discharged its NEPA duty to adequately consider the indirect and cumulative environmental effects of authorizing the “siting, construction, expansion, [and] operation” of the Freeport Projects.
the Commission understated the full extent of the Projects’ emissions. Pet. Br. 38.
In reviewing the Associations’ challenges, our task is not to “flyspeck” the Commission‘s environmental analysis for “any deficiency no matter how minor.” Theodore Roosevelt Conservation P‘ship v. Salazar, 661 F.3d 66, 75 (D.C. Cir. 2011). Our job is “simply to ensure that the agency has adequately considered and disclosed the environmental impact of its actions and that its decision is not arbitrary or capricious.” Baltimore Gas & Elec. Co. v. Natural Res. Def. Council, Inc., 462 U.S. 87, 97-98 (1983); see also Natural Res. Def. Council, Inc. v. Hodel, 865 F.2d 288, 294 (D.C. Cir. 1988) (If an agency‘s NEPA analysis is “fully informed and well considered, it is entitled to judicial deference and a reviewing court should not substitute its own policy judgment.“). None of the Associations’ challenges can survive that deferential standard of review.
A
NEPA obligated the Commission to factor into its environmental analysis not just the direct, but also the indirect, environmental effects of the Freeport Projects’ construction and operation—that is, those effects that are “later in time or farther removed in distance,” yet “reasonably foreseeable.” Department of Transp. v. Public Citizen, 541 U.S. 752, 764 (2004); see
Additionally, the Commission‘s NEPA analysis did not have to address the indirect effects of the anticipated export of natural gas. That is because the Department of Energy, not the Commission, has sole authority to license the export of any natural gas going through the Freeport facilities. In the specific circumstances where, as here, an agency “has no ability to prevent a certain effect due to” that agency‘s “limited statutory authority over the relevant action[ ],” then that action “cannot be considered a legally relevant ‘cause’ of the effect” for NEPA purposes. Public Citizen, 541 U.S. at 771.
The Associations argue that the Commission should have factored in the increase in domestic natural gas production that, in their view, the Freeport Projects would induce. But that challenge again focused on the impact of natural gas exports from the Freeport Projects on domestic production, and export effects do not fall within the Commission‘s bandwidth. To the extent that the Associations’ argument focuses on induced production from domestic operations, we disagree. The Commission reasonably explained that the asserted linkage was too attenuated to be weighed in its particular NEPA analysis.
In particular, the Commission found no evidence that the Projects by themselves would lead to increased gas production because “no specific shale-play [had] been identified as a source of natural gas for” the Projects. J.A. 1209. More importantly, there was no evidence suggesting that the gas to be processed in the Freeport facility, independent of the export authorization, would “come from future, induced natural gas production, as opposed to from existing production, particularly in light of the longtime, extensive natural gas development that has already occurred in Texas, including in its shale areas.”
The Associations level two objections to the Commission‘s reasoning, but neither surmounts the high hurdle of demonstrating arbitrary and capricious decision-making.
First, the Associations says it is “self-evident” under “[b]asic economic principles” that authorizing the Freeport Projects will lead to the Department of Energy granting an export license, which in turn will increase domestic gas production and the price of domestic natural gas, which next will drive consumers toward cheaper energy sources, including more environmentally harmful products like coal. That increase in both gas production and coal use will, according to the Associations, cause domestic greenhouse gas and ozone emissions to rise. Pet. Br. 23; see
Perhaps. But critical to triggering that chain of events is the intervening action of the Department of Energy in granting an
The Associations rely on the Eighth Circuit‘s decision in Mid States Coalition for Progress v. Surface Transp. Bd., 345 F.3d 520 (8th Cir. 2003). In that case, the court found inadequate the Surface Transportation Board‘s Environmental Impact Statement analyzing the construction and rehabilitation of hundreds of miles of railroad lines for the transportation of coal.
Even assuming the correctness of a decision that does not bind this circuit, this case looks nothing like Mid States. Here, the Associations have not identified any specific and causally linear indirect consequences that could reasonably be foreseen and factored into the Commission‘s environmental analysis that exist apart from the intervening Department of Energy decision to authorize exports.
Second, the Associations say the Commission acted arbitrarily and capriciously by not taking sufficient account of the Energy Information Administration‘s 2012 report on the “Effect of Increased Natural Gas Exports on Domestic Energy Markets,” which (according to the Associations) “specifically predicted the extent to which LNG exports from the Gulf Coast would increase gas production and coal use.” Pet. Br. 23; see generally U.S. ENERGY INFORMATION ADMIN., EFFECT OF INCREASED NATURAL GAS EXPORTS ON DOMESTIC ENERGY MARKETS 1, 3 (Jan. 2012) (“2012 Report“). Again, that argument treads on environmental consequences tied to the Department of Energy‘s export authorization that, under Public Citizen, fall outside the Commission‘s NEPA wheelhouse.
In rejecting the Associations’ challenges, we are mindful that “[t]he grounds upon which an administrative order must be judged are those upon which the record discloses that its action was based,” SEC v. Chenery Corp., 318 U.S. 80, 87 (1943), and that the Commission did not explicitly consider the extent to which Public Citizen placed the Associations’ asserted export-intertwined effects outside of the Commission‘s NEPA duties. But Chenery‘s restriction on our review of an agency‘s order “is to be understood with a qualification; the order must be judged upon the grounds upon which the action was based, unless the appellate court concludes that the decision “already made * * * should properly be based on another ground within the power of the appellate court to formulate” “—that is, one that “does not depend upon a factual determination or a policy judgment that [the agency] alone is authorized to make.” Shea v. Director, Office of Workers’ Comp. Programs, 929 F.2d 736, 739 n. 4 (D.C. Cir. 1991) (quoting Chae-Sik Lee v. Kennedy, 294 F.2d 231, 234 (D.C. Cir.),
Our decision here follows not from de novo factual findings or independent policy judgments, but from our interpretation of NEPA and binding Supreme Court precedent—neither of which trenches upon a “determination specifically entrusted to [the Commission‘s] expertise.” Canonsburg Gen. Hosp., 807 F.3d at 304; see New York New York, LLC v. NLRB, 313 F.3d 585, 590 (D.C. Cir. 2002) (“We are not obligated to defer to an agency‘s interpretation of Supreme Court precedent under Chevron or any other principle.“) (internal quotation marks omitted); Grand Canyon Trust v. FAA, 290 F.3d 339, 342 (D.C. Cir. 2002) (“[T]he court owes no deference to [an agency‘s] interpretation of NEPA * * * because NEPA is addressed to all federal agencies and Congress did not entrust administration of NEPA to [any one agency] alone.“).
The Supreme Court‘s decision in Public Citizen is explicit that the Commission was not obligated to consider those effects of the Freeport Projects that could only occur after intervening action by the Department of Energy or Congress and that only those actors—and not the Commission—had the authority to prevent. Based on the record before us and the Associations’ arguments, we cannot conclude that the Commission‘s analysis of the Projects’ indirect effects, separate and apart from exporting, was arbitrary or capricious.
B
In addition to addressing reasonably foreseeable indirect effects, NEPA
obligated the Commission to consider the “cumulative impact[s]” on the environment—that is, “the incremental impact of the [Freeport Projects] when added to other past, present, and reasonably foreseeable future actions[.]”
The Commission identified the relevant geographic area for its cumulative-impact analysis as Brazoria County, Texas, the 1,600-square-mile county in which the Freeport Projects would be located and in which “the predominance of environmental impacts” associated with the Projects’ construction and operation would occur. J.A. 978. Such a determination of the size and location of the relevant geographic area “requires a high level of technical expertise,” and thus “is a task assigned to the special competency of” the Commission. Kleppe v. Sierra Club, 427 U.S. 390, 412, 414 (1976). The Commission then catalogued and analyzed the cumulative environmental effects of the Freeport Projects with “[m]ajor current and proposed developments” in the County, including industrial, port and harbor channel, pipeline, oil and gas field, land and air transportation, commercial, residential, and other miscellaneous developments. J.A. 980.
That draws the NEPA circle too wide for the Commission. A NEPA cumulative-impact analysis need only consider the “effect of the current project along with any other past, present or likely future actions in the same geographic area” as the project under review. TOMAC, 433 F.3d at 864 (emphasis added); Grand Canyon Trust, 290 F.3d at 345 (NEPA “cumulative impacts” applies to “impacts in the same area“).
The Associations point to the Supreme Court‘s direction in Kleppe that, “when several proposals for * * * related actions that will have cumulative or synergistic environmental impact upon a region are pending concurrently before an agency, their environmental consequences must be considered together,” 427 U.S. at 410. But the key language there is “upon a region.”
That is not to say that the nature of a particular agency action would never warrant a nationwide cumulative-impact analysis. See Grand Canyon Trust, 290 F.3d at 345 (cumulative impact analyses must identify “the area in which the effects of the proposed project will be felt“). But given the scant record evidence identifying any reasonably foreseeable and proximate effects of the Freeport Projects themselves (separate from their exports) on national energy markets or emission levels, we hold that the Associations have not shown that the Commission acted arbitrarily or capriciously in analyzing the cumulative effects of the Freeport Projects. See Minisink Residents for Environmental Preservation and Safety v. FERC, 762 F.3d 97, 113 (D.C. Cir. 2014) (upholding cumulative-impact analysis finding “no significant cumulative impacts were expected” where the “[p]roject itself was expected to have minimal impacts“).
C
Lastly, the Associations fault the Commission for quantifying emissions from the Projects’ electricity use in pounds per megawatt-hour instead of in tons per year. We lack jurisdiction to entertain that argument.
The Natural Gas Act is explicit that “[n]o objection to the order of the Commission shall be considered by the court unless such objection shall have been urged before the Commission in the application for rehearing unless there is reasonable ground for failure so to do.”
That obligation to raise objections before the Commission first is redoubled under NEPA because “[p]ersons challenging an agency‘s compliance with NEPA
At no point in the proceedings below, including the rehearing stage, did the Associations contend that the Commission should use the tons-per-year metric. In fact, in its comments to the Commission‘s draft statement, Sierra Club specifically directed the Commission to a database that “conveniently” quantified emission rates using the same pounds-per-megawatt-hour metric that it now faults the Commission for employing. J.A. 432. Because the “tons per year vs. pounds per megawatt-hour” argument was not raised before the Commission, it cannot be considered here.
IV
In sum, we hold that at least one of the Associations’ members has standing, and that the case is not moot. On the merits, we reject the Associations’ challenges to the Commission‘s NEPA review of the Freeport Projects, separate and apart from any environmental effects associated with the Department of Energy‘s independent decision to authorize exports.
It is so ordered.
