Lead Opinion
Oрinion concurring in part and dissenting in part filed by Circuit Judge BROWN. ■
Environmental groups and landowners have challenged the decision of the Federal Energy Regulatory Commission to approve the construction and operation of three new interstate natural-gas pipelines in the southeastern United States. Their primary argument is that the agency’s assessment of the environmental impact of the pipelines was inadequate. We agree that FERC’s environmental impact statement did not contain enough information on the greenhouse-gas emissions that will result from burning the gas that the pipelines will carry. In all other respects, we conclude that FERC acted properly. We thus grant Sierra Club’s petition ‘for review and remand for preparation of a conforming environmental impact statement.
I
The Southeast Market Pipelines Project comprises three natural-gas pipelines now under construction in Alabama, Georgia, and Florida. The linchpin of the project is the Sabal Trail pipeline, which will wend its way from Tallapoosa County in eastern Alabama, across southwestern Georgia, and down to Osceola County, Florida, just south of Orlando:' a journey of nearly five hundred miles. Sabal Trail will connect the other two portions of the project. The first—the: Hillabee Expansion—will boost the capacity of an existing pipeline in Alabama, which will feed gas to Sabal Trail’s upstream end for transport to Florida. At the downstream end of Sabal Trail will be the Florida Southeast Connection, which will link to a powér plant in Martin County, Florida, 120 miles away. Shorter spurs will join Sabal Trail to other proposed and existing power plants and pipeline networks. By its scheduled completion in 2021, the project will be able to carry over one billion cubic feet of natural gas per day.
The three segments of the project have different owners,
Despite these optimistic predictions, the project has drawn opposition from several quarters. Environmental groups fear that increased burning of natural gas will hasten climate change and its potentially catastrophic consequеnces. Landowners in the pipelines’ path object to the seizure of their property by eminent domain. And communities on the project’s route are concerned that pipeline facilities will be built in low-income and predominantly minority areas already overburdened by industrial polluters.
Section 7 of the Natural Gas Act places these disputes into the bailiwick of the Federal Energy Regulatory Commission (FERC), which has jurisdiction to approve or. deny the construction of interstate natural-gas pipelines. See 15 U.S.C. § 717f. Before any such pipeline can be built, FERC must grant the developer a “certificate of public convenience and necessity,” id. § 717f(c)(l)(A), also called a Section 7 certificate, upon a finding that the project will serve the public interest, see id. § 717f(e). FERC is also empowered to attach “reasonable terms and conditions” to the certificate, as necessary to protect the public. Id. A certificate holder has the ability to acquire necessary rights-of-way from unwilling landowners by eminent domain proceedings. See id. § 717f(h).
FERC launched an environmental review of the proposed project in the fall of 2013. The agency understood that it would need to prepare an environmental impact statement (EIS) before approving the project, as the National Environmental Policy Act of 1969 (NEPA) requires for each “majоr Federal action[] significantly affecting the quality of the human environment.” See 42 U.S.C. § 4332(2)(C). FERC solicited public comment and held thirteen public meetings on the project’s environmental effects, and made limited modifications to the project plan in response to public concerns, before releasing a draft impact statement in September 2015 and a final impact statement in December 2015. In the meantime, the pipeline developers formally applied for their Section 7 certificates in September and November 2014.
In the Certificate Order, issued on February 2, 2016, FERC granted the requested Section 7 certificates and approved construction of all three project segments, subject to compliance with various conditions not at issue here. Order Issuing Certificates and Approving Abandonment, Fla. Se. Connection, LLC,
Both the environmental groups (collectively, “Sierra Club”) and the landowners timely petitioned our court for review of the Certificate Order and the Rehearing Order. Sierra Club argues that FERC’s environmental impact statement failed to adequately consider the project’s contribution to greenhouse-gas emissions and its impact on low-income and minority communities. Sierra Club also contends that Sabal Trail’s service rates were based on an invalid methodology. The landowners allege further oversights in the EIS, dispute the public need for the project, and assert that FERC used an insufficiently transparent process to approve the pipeline certificates. Their petitions were consolidated before us.
II
We have jurisdiction to hear these petitions under the Natural Gas Act. See 15 U.S.C. § 717r(b). Any party to a proceeding under the Act who is “aggrieved” by a FERC order may petition for review of that order in our court, provided that they first seek rehearing before FERC. Id. § 717r(a)-(b). Sierra Club was an interve-nor in the proceedings on all three pipeline applications, see Certificate Order App. A, and the landowner petitioners were inter-venors in the Sabal Trail proceedings, see id.
A party is “aggrieved” by a FERC order if it challenges the order under NEPA and asserts an environmental harm. See Gunpowder Riverkeeper v. FERC,
We also have an independent duty to ensure that at least, one petitioner has standing under Article III of the Constitution. See Ams. for Safe Access v. DEA,
Several individual Sierra Club members submitted such affidavits, explaining how the pipeline project would harm their “concrete aesthetic and recreational interests.” WildEarth,
Because they allege concrete injury from FERC’s order certifying the pipeline project, and because that certification was based on an allegedly inadequate environmental impact statement, these Sierra. Club members, and therefore Sierra Club itself, have standing to object to any deficiency in the environmental impact statement.
Transco, owner of the Hillabee Expansion, argues that no Sierra Club member has alleged an injury caused by Tran-sco’s section of the overall project, which would suggest ■ that Sierra Club lacks standing to seek the vacatur of Hillabee’s certificate. Transco thus implicitly argues that the Certificate Order is- severable. Under this view, if Sierra Club succeeds on the merits, but has standing to challenge only Sabal Trail’s certificate, we could vacate only the portion of the Certificate Order pertaining to Sabal Trail, and leave the rest intact.
The question whether an agency order is severable turns on the agency’s intent. See Epsilon Elecs., Inc. v. U.S. Dep’t of Treasury,
We substantially doubt that FERC would have approved the Southeast Market Pipelines Project only in part, and we especially doubt that. the agency would have certified either of the other two segments if Sabal Trail were not part of the project. Because Sierra Club and the landowners have alleged injury-in-fact caused by Sabal Trail, and because the Certificate Order is not severable, both sets of petitioners have standing to challenge the Certificate Order as a whole.
Having concluded that we have jurisdiction to entertain all of petitioners’ claims, we turn to the merits of those claims.
Ill .
Both sets of petitioners rely heavily on the National Environmental . Policy Act of 1969, Pub. L. No. 91-190, 83 Stat. 852 (1970). NEPA “declares a broad national commitment to protecting and promoting environmental quality,” and brings that commitment to bear on the operations of the federal government. Robertson v. Methow Valley Citizens Council,
This environmental impact statement, as it has come to be called, has two purposes. It forces the agency to take a “hard look” at the environmental consequences of its actions, including alternatives to its proposed course. See id. § 4332(2) (C) (iii); Balt. Gas & Elec. Co. v. Nat. Res. Def. Council, Inc.,
The role of the courts in reviewing agency compliance with NEPA is accordingly limited. Furthermore, because NEPA does not create a private right of action, we can entertain NEPA-based challenges only under the Administrative Procedure Act and its deferential standard of review. See Theodore Roosevelt Conservation P’ship v. Salazar,
But at the same time, we are responsible for holding agencies to the standard the statute establishes. An EIS is deficient, and the agency action it un-dergirds is arbitrary and capricious, if the EIS does not contain “sufficient discussion of the relevant issues and opposing viewpoints,” Nevada,
With those principles in mind, we direct our attention to the specific deficiencies the petitioners have alleged in the EIS for the Southeast Market Pipelines Project. As noted above, FERC prepared a single unified EIS for the project’s three pipelines, and no party has challenged that approach. Thus, for purposes of our NEPA analysis, we will consider the project as a whole.
A
The principle of environmental justice encourages agencies to consider whether the projects they sanction will have a “disproportionately high and adverse” impact on low-income and predominantly minority communities.
Sierra Club argues that the EIS failed to adequately take this principle into account. Like the other components of an EIS, an environmental justice analysis is measured against the arbitrary-and-capricious standard. See Cmtys. Against Runway Expansion, Inc. v. FAA,
The EIS explained that 83.7% of the pipelines’ proposed route would cross
FERC concluded that the various feasible alternatives “would affect a relatively similar percentage of environmental justice populations,” and that the preferred route thus would not have a disproportionate impact on those populations. See J.A. 836. The agency also independently concluded that the project would not have a “high and adverse” impact on any population,- meaning, in the agency’s view, that it could not have a “disproportionately high and adverse” impact on any population, marginalized or otherwise.
Sierra Club contends that FERC misread “disproportionately high and adverse,” the standard for when a particular environmental effect raises an environmental-justice concern. By Sierra Club’s lights, any effect can -fulfill the test, regardless of its intensity, extent, or duration, if it is not beneficial and falls disproportionately on environmental-justice communities. But even if we assume that understanding to be correct, we cannot see how this EIS was deficient. It discussed the intensity, extent, and duration of the pipelines’ environmental effects, and also separately discussed the fact that those effects will disproportionately fall on environmental-justice communities. Recall that the EIS informed readers and the agency’s ultimate decisionmakers that 83.7% of the pipelines’ length would be in or near environmental-justice communities. The EIS also evaluated route alternatives in part by looking at the number of environmental-justice communities each would cross,' and the mileage of pipeline each would place in low-income and minority areas. FERC thus grappled with the disparate impacts of the various possible pipeline routes. Perhaps Sierra Club would have a stronger claim if the agency had refused entirely to discuss the demographics of the populations thát will feel the pipelines’ effects, and had justified this refusal by pointing to the limited intensity, extent, and duration of those effects. However, as the EIS stands, we see no deficiencies serious enough to defeat the statute’s goals of fostering well-informed decisionmaking and public comment. See Nevada,
The same goes for Sierra Club’s other arguments. The agency’s methodology was reasonable, even where it deviated from what Sierra Club would have preferred. See Runway Expansion,
Sierra Club is particularly concerned about Sabal Trail’s plan to build a compressor .station (a facility that helps “pump” gas along the pipeline, and gives off ah- and noise pollution while doing so) in an African American neighborhood of Albany, Dougherty County, Georgia. The agency identified environmental-justice communities by looking at the demographics of census tracts, which are county subdivisions created to organize census data. The neighborhood in question is a 100% African American census block, an even smaller census subdivision, but because it sits in the midst .of a majority-white census tract, FERC did not designate it an environmental-justice community. Sierra Club’s objection to this omission elevates form over substance. The goal of an environmental-justice analysis is satisfied if an agency recognizes and discusses a project’s impacts on predominantly-minority communities, even if it does not formally label each such community an “environmental justice community.” FERC did recognize the existence and demographics of the neighborhood in question, and discussed the neighborhood extensively. The EIS listed community features, including subdivisions, schools, and churches, along with their distances from the proposed compressor station, and explained that the station’s noise and air-quality effects on these locations were expected to remain within acceptable limits.
More persuasive is Sierra Club’s argument that FERC disregarded the extent to which Dougherty County is already overburdenеd with pollution sources. A letter to FERC from four members of Georgia’s congressional delegation cites the grim statistics: southern Dougherty County has 259 hazardous-waste facilities, 78 air-polluting facilities, 20 toxic-polluting facilities, and- 16 water-polluting facilities. The EIS did not mention these existing polluters in its discussion of Dougherty County. Sierra Club thus argues that FERC inadequately considered the project’s “cumulative impacts,” that is, its effects taken in combination with existing environmental hazards in the same area. See 40 C.F.R. § 1508.7; Del Riverkeeper,
Perhaps FERC could have said, more, but the discussion it undertook of the cumulative impacts of the proposed route fulfilled NEPA’s goal of guiding informed decisionmaking. The EIS acknowledged that the Sabal Trail project will generate ah* pollution and noise pollution in Albany, and it projected cumulative levels of both of these types of pollution from all sources in the vicinity of the compressor station, finding that both would remain below harmful thresholds.
To sum up, the EIS acknowledged and considered the substance of all the concerns Sierra Club now raises: the fact that the Southeast Market Pipelines Project will travel primarily through low-income and minority communities, and the impact of the pipeline on the city of Albany and Dougherty County in particular. The EIS also laid out a variety of alternative approaches with potential to address those concerns, including those proposed by, petitioners, and explained why, in FERC’s view, they would do more harm than good. The EIS also gave the public and agency decisionmakers the qualitative and quantitative tools they needed to make an informed choice for themselves. NEPA requires nothing more.
'S
It’s not just the journey, though, it’s also the destination. All the natural' gas that will travel through these pipelines will be going somewhere: specifically, to power рlants in Florida, some of which already exist, others of which are in the planning stages. Those power plants will burn the gas, generating both electricity and carbon dioxide. And once in the atmosphere, that carbon dioxide will add to the greenhouse effect, which the EIS describes as “the primary contributing factor” in global climate change. J.A. 915. The next question before us is whether, and to what extent, the EIS for this pipeline project needed to discuss these “downstream” effects of the pipelines and their cargo. We conclude that at a minimum, FERC should have estimated the amount of power-plant carbon emissions that the pipelines will make possible.
An agency conducting a NEPA review must consider not only the direct effects, but also the indirect environmental effects, of the project under consideration. See 40 C.F.R. § 1502.16(b). “Indirect effects” are those that “are caused by the [project] and are later in time or farther removed in distance, but are still reasonably foreseeable.” Id, § 1508.8(b). The phrase “reasonably foreseeable” is the key here. Effects are reasonably foreseeable if they are “sufficiently likely to occur that a person of ordinary prudence would take [them] into account in reaching a decision,” EarthReports, Inc. v. FERC,
What are the “reasonably foreseeable” effects of authorising a pipeline that will
The pipeline developers deny that FERC would be the legally relevant cause of any power plant carbon emissions, and thus contend that FERC had no obligation to consider those emissions in its NEPA analysis. They rely on Department of Transportation v. Public Citizen,
The Supreme Court sided with the agency. The Court noted that the agency would have no statutory authority to exclude Mexican trucks from the United States once the President lifted the moratorium; it would only have power to set safety rules for those trucks. See id. at 766-67,
We recently applied the Public Citizen rule in three challenges to FERC decisions licensing liquefied natural gas (LNG) terminals. See Sierra Club v. FERC (Freeport),
An agency has no obligation to gather or consider environmental information if it has no statutory authority to act on that information. That rule was the touchstone of Public Citizen, see
This raises the question: what did the Freeport court mean by its statement that FERC could not prevent the effects of exports? After all, FERC did have legal authority to deny an upgrade license for a natural gas export terminal. See Freeport,
The answer must be that FERC was forbidden to rely on the effects of gas exports as a justification for denying an upgrade license. Cf. Motor Vehicle Mfrs. Ass’n of U.S. v. State Farm Mut. Auto. Ins. Co.,
Here, FERC is not so limited. Congress broadly instructed the agency to consider “the public convenience and necessity” when evaluating applications to construct and operate interstate pipelines. See 15 U.S.C. § 717f(e). FERC will balance “the public benefits against the adverse effects of the project,” see Minisink Residents for Envtl. Pres. & Safety v. FERC,
FERC next raises a practical objection, arguing that it is impossible to
We conclude that the EIS for the Southeast Market Pipelines Project should have either given a quantitative estimate of the downstream .greenhouse emissions that will result from burning the natural gas that the pipelines will transport or explained more specifically why it could not have done so. As we have noted, greenhouse-gas emissions are an indirect effect of authorizing this project, which FERC could reasonably foresee, and which the agency has legal authority to mitigate. See 15 U.S.C. § 717f(e). The EIS accordingly needed to include a discussion of the “significance” of this indirect effect, see 40 C.F.R. § 1502.16(b), as well as “the incremental impact of the action when added to other past, present, and reasonably foreseeable future, actions,” see WildEarth Guardians,
Quantification would permit the agency to compare the emissions from this project to emissions from other projects, to total emissions from the state or the region, or to regional or national emissions-control goals. Without such сomparisons, it is difficult to see how FERC could engage in “informed decision making” with respect to the greenhouse-gas effects of this project, or how “informed public comment” could be possible. See Nevada,
We do - not hold that quantification of greenhouse-gas emissions is required every time 'those emissions are an indirect effect of an agency action. We understand that in some cases quantification may not be feasible, See, e.g., Sierra Club v. U.S. Dep’t of Energy,
Nor is FERC excused from making emissions estimates just because the
We also recognize that the power plants in- question will be subject to “state and federal air permitting processes.” J.A. 917. But even if we assume that power plants’ greenhouse-gas emissions will be .subject to regulation in the future, see Exec. Order. No. 13,783, § 4(a), 82, Fed. Reg. 16,093, 16,095 (Mar. 28, 2017) (instructing the EPA administrator to consider “whether to revise or withdraw” federal regulation of these emissions), the existence of permit requirements overseen by another federal agency or state permitting authority cannot substitute for a proper NEPA analysis. See Calvert Cliffs’ Coordinating Comm. v. Atomic Energy Comm’n,
Our discussion so far has explained that FERC must either quantify and consider the project’s downstream carbon emissions or explain in more detail why it cannot do so. Sierra Club proposes a further analytical step. The EIS might have tried to link those downstream carbon emissions to particular climate impacts, like a rise in the sea level or an increased risk of severe storms. The EIS explained that there is no standard methodology for making this sort of prediction. Cf. WildEarth Guardians,
C
GBA Associates alleges two further flaws in the EIS, but we find neither charge persuasive.
First, the landowners contend that “FERC has erroneously limited the scope
GBA also accuses FERC of giving too little consideration to the safety risks involved in the construction of the pipeline, and specifically to the fact that in some places, new pipeline will cross, or run alongside, existing pipeline. As GBA’s own brief recognizes, though, the EIS recognized and discussed the risk of pipeline crossings, ultimately concluding that some crossings were necessary to minimize impacts on natural resources and homes. GBA’s only response is that commenters, including the owner of one of the existing pipelines, submitted letters to FERC expressing safety concerns. But the EIS responded to those comments, and GBA does not explain why the responses were insufficient. Again, NEPA does not require a particular substantive result, like the elimination of all pipeline crossings; it only requires the agency to take a “hard look” at the problem. This FERC has done.
IV
All of these pipelines, of course, are being built for a reason: to make a profit for their shareholders, and their shareholders’ shareholders. But the profits they can make are constrained by the Natural Gas Act, the “fundamental purpose” of which “is to protect natural gas consumers from the monopoly power of natural gas pipelines.” Nat’l Fuel Gas Supply Corp. v. FERC,
Drilling down further, we can see that the rate of return itself has two ntain components. Like most businesses, a pipe-' line company is funded by both equity (ie., investments made by shareholders) and debt. See NCUC,
In its original application for a Section 7 certificate, Sabal Trail sought to design its rates based on a capital structure with 60% equity and 40% debt. It anticipated that the interest rate on its debt would be 6.2%, аnd proposed to pay a 14% return to its equity investors. The weighted average of those two rates would yield an overall rate of return of 10.88%.
FERC, however, felt that a 14% rate of return on equity was too high for a pipeline with only 40% debt. (Recall that a high rate of return must be justified by a high investment risk, and that pipelines with less debt are less risky for equity investors.) The agency explained that Sabal Trail could design its rates around a 14% return on equity if it wanted to, but only'if it also changed the proposed capital structure. With a 50% equity/50% debt capital structure, FERC explained, a 14% rate of return on equity would be reasonable.
Sierra Club objects to FERC’s decision to allow Sabal Trail to base its rates on a “hypothetical capital structure.” It argues that, having concluded that Sabal Trail’s proposed return on equity was too high, FERC should have either cut the rate of return or denied the pipeline a certificate altogether. We review FERC’s capital-structure decision under the deferential standard of the Administrative Procedure Act, and may disturb that decision only if it is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” See NCUC,
We think that FERC adequately explained its decision to allow Sabal Trail to employ a hypothetical capital structure. FERC’s job, when evaluating a proposed rate for a new pipeline, is to see that the pipeline’s investors receive a reasonable, but not excessive, return on their investment. See id. at 661. The returns must be proportionate to the business and financial risk the investors take on: more risk, more reward. See id.; MarkWest,
Sierra Club’s objection stems, in part, from a misunderstanding of FERC’s role in the rate-setting process. FERC does not directly control either the pipeline’s return on equity or its capital structure. FERC merely approves the initial rates the pipeline will charge, a price that is based in part on an anticipated return on equity and an anticipated debt level. See NCUC,
Nothing in our precedent is to the contrary, Sierra Club claims that in NCUC we disapproved FERC’s use of a hypothetical capital structure. That’s true, but our reasoning- there is inapposite here. In that case FERC had used a hypothetical capital structure to increase, rather than decrease, the rates the pipeline could charge, and to. “mask an otherwise anomalous [ly high] return as something more appealing.” See
FERC also acted consistently with its own precedent. Its approach in this case was identical to its order in MarkWest. See
Though we see nothing arbitrary or capricious in FERC’s choice to use a hypothetical capital structure in rate-setting, substantial evidence must support the capital structure FERC ultimately uses, in the rate calculation, hypothetical or not. See NCUC,
However, Sierra Club does not make this argument in its opening briеf, confining itself to attacking .the use of a hypothetical capital structure more generally. See Sierra Club Opening Br. 43 (“FERC has not stated an adequate explanation for allowing a high rate of return based upon a hypothetical capital structure.”); see also, e.g., Fox v. Gov’t of Dist. of Columbia,
V
We turn to GBA’s two remaining arguments, both of which we find unavailing.
The landowners challenge PERC’s conclusion that the Southeast Market Pipelines Project will serve the public convenience, and necessity. As mentioned previously, a finding that a proposed natural-gas pipeline “is or will be required by the present or future public convenience and necessity” is a prerequisite for FERC certification, See 15 U.S.C. § 717f(e). The “public convenience and necessity” analysis has two components. First, the applicant must show that the project will “stand on its own financially” because it meets a “market need.” See Myersville,
The landowner petitioners take issue with FERC’s market-need analysis, alleging that this project serves only the profit motive of the pipeline developers, rather than any public need. See GBA Opening Br. 28. That argument misunderstands our test. The criterion is “market need”—whether the pipelines will be self-supporting—which the applicants here satisfied by showing that 93% of their capacity has already been contracted for. The landowners also assert that the pipeline will be “redundant as it largely parallels existing pipelines,” see GBA Opening Br. 29, but as FERC found, and the petitioners do not refute, the “expansion of existing pipelines will not satisfy the identified need,” see J.A. 1101.
The landowner petitioners also assert that FERC violated the Government in the Sunshine Act, 5 U.S.C. § 552b, by approving the pipelines’ certificates via notational voting, a procedure where the members of a multimember agency cast their votes individually and separately, rather than at a public meeting. But we have expressly approved of notational voting, and held it to be consistent with the Sunshine Act, on multiple occasions. See R.R. Comm’n of Tex. v. United States,
VI
The petition for review in No. 16-1329 is granted. The orders under review are vacated and remanded to FERC for the preparation of an environmental impact statement that is consistent with this opinion. The petition for review in No. 16-1387 is denied.
So ordered.
Notes
. Sabal Trail is owned by Spectra Energy Partners, NextEra Energy, and Duke Energy: the Hillabee Expansion is owned by the Williams Companies; and Florida Southeast Connection is owned by NextEra, Duke Energy, and NextEra’s subsidiary Florida Power &
. Though GBA Associates and Isaacs raise different arguments as to why the Certificate and Rehearing Orders are unlawful, the standing analysis does not differ for them, as they seek the same remedy and allege similar injuries to their property interests.
. The same reasoning goes for Sierra Club’s argument that FERC used an arbitrary and capricious methodology in determining Sabal Trail's initial rates. A finding that FERC failed to justify its approach to this issue would lead us to "hold unlawful and set aside” Sabal Trail’s certificate, see 5 U.S.C. § 706(2), which would in turn redress the Sierra Club members' environmentally based injuries in fact. See Ctr. for Biological Diversity v. U.S. Dep't of Interior,
. Like petitioners, we refer to these two typеs of community collectively as “environmental-justice communities.’'
. Because FERC voluntarily performed an environmental-justice review, we need not decide whether Executive Order 12,898 is binding on FERC. See Runway Expansion,
. Sierra Club argues that the project will in fact have “high and adverse” impacts, but does so only in a brief and cursory fashion. See CTS Corp. v. EPA,
. FERC appropriately relied on EPA’s national ambient air quality stánd'ards (NAAQS) as a standard of comparison for air-quality impacts. By' presenting the project’s expected
. We aiso note that Florida Power & Light, which expects to be oiiv.„ of the pipelines’ two primary customers, represented to FERC that “its commitments on Sabtl Trad’s and Florida Southeast’s systems are to provide gas to existing natural gas-fired plants.” Certificate Order 1185, J.A. 1100. So even if the dissent were correct that Florida regulаtors' authority over power-plant construction excuses FERC from considering emissions from new or expanded power plants, that argument would not apply to the significant portion of these pipelines’ capacity that is earmarked for existing plants.
. The dissent contends that if FERC refused to approve these pipelines, Florida utilities would find a way to deliver an equivalent amount of natural gas to the state regardless. See Dissenting Op. 1383. This argument, however, does not bear on the question whether FERC is legally authorized to consider downstream environmental effects when evaluating a Section 7 certificate application. In any case, the record suggests that there is no other viable means of delivering the amount
. For a highly simplified illustration, suppose that the rate base is $1 billion and the rate of return allowed is 10%. In that case, the pipeline can earn a total annual return of $100 million. Thus, if the pipeline’s annual costs are $150 million, then the pipeline can collect total annual revenues of $250 million, and can set its rates accordingly.
Concurrence Opinion
concurring in part and dissenting in part:
I join today’s opinion on all issues save the Court’s decision to vacate and remand the pipeline certificates on the issue of downstream greenhouse emissions. Case law is clear:, When an agency “‘has no
When examining a NEPA claim, our role is limited to ensuring the relevant agency took a “hard look at the environmental consequences” of its dеcisions and “adequately considered and disclosed the environmental impact of its actions.” Balt. Gas & Elec. Co. v. Nat. Res. Def. Council,
Regarding causation, the Court is correct that NEPA requires an environmental analysis to include indirect effects that are “reasonably foreseeable,” Freeport,
In several recent cases, petitioners sought review of a downstream environmental effect that fell within the oversight of another agency. We held the occurrence of a downstream environmental effect, contingent upon the issuance of a license from another agency with the sole authority to authorize the source of those downstream effects, cannot be attributed to the Commission; its actions “cannot be considered a legally relevant cause of the effect for NEPA purposes.” See Freeport,
This case presents virtually identical circumstances. Under the Florida Electrical Power Plant Siting Act, “a power plant cannot be built unless a site certification is obtained” from the Florida Power Plant Siting Board (“the Board”). Ecodyne Cooling Div. of Ecodyne Corp. v. City of Lakeland,
Despite this clearly-controlling cаse law and the exclusive authority of the state Board to license the construction and expansion of power plants in Florida, the Court concludes FERC’s approval of .the pipeline is a “legally relevant cause” of the greenhouse gas emissions from the Florida power plants. See Maj. Op. at 1372. But its attempt to explain why NEPA operates more expansively when applied to pipelines compared to export terminals, ás well as its arguments as to why the Florida Board should be treated differently than DOE under NEPA, are both ultimately unpersuasive.. Both projects qualify as “major [fjederal actions significantly affecting .the quality of the human environment,” 42 U.S.C. § 4332(C), so there is no reason why NEPA’s requirement to consider indirect environmental effects would not apply equally to both. Moreover, nothing in the statutory language empowering the Commission to regulate export terminals and pipelines suggests the Commission’s authority is more limited in one circumstance than another. Congress has granted -the Commission “the exclusive authority to,approve or deny an application for the siting, construction, expansion, or operation of an [export] terminal,” 15 U.S.C. § 717b(e)(l), and to impose any conditions on those terminals the Commission finds to be “necessary or appropriate,” id. § 717b(e)(3)(A). Thus, the Commission has the power to approve or deny the cоnstruction and operation of export terminals subject to any conditions it wishes to impose. Likewise, Congress requires any applicant seeking to construct or extend natural gas transportation facilities to obtain a “certificate of public convenience and necessity” from the Commission. Id, § 717f(c)(l)(A). The Commission “shall” issue a certificate if “the applicant is able and willing properly to-do the acts and to perform the service proposed” and if the proposed service or construction “is or will- be required by the present or future public convenience and necessity.” Id. § 717f(e); FERC also has the “power to attach to the issuance of the certificate . -., such reasonable terms and conditions as the public convenience and necessity may require.” Id. Accordingly, nothing in the text of either statute empowers the Commission to entirely deny the 'construction of an export terminal or the issuance of a certificate based solely on an adverse indirect environmental effect regulated by another agency. See id, §§ 717b(e), 717f(e).
'The actual distinction between this case and the DOE cases discussed above is doctrinally invisible. We stated in Freeport that “[i]n the specific circumstances where ... an agency has no ability to prevent a certain effect due to that agency’s limited statutory authority over the relevant action, then that action cannot be considered a legally relevant ‘cause’, of the effect for NEPA purposes.”
Even if the Court is correct that the Commission has the power to deny pipeline certificates based on indirect environmental concerns, such a denial represents the limit of the Commission’s statutory power. Nothing would prevent the Florida Board from independently approving the construction or expansion of the power plants at issue. In fact, the record shows the Board has already approved some of these projects prior to the Commission reaching a decision on the proposed pipelines. JA 910-11. Moreover, there is also nothing preventing the Intervenors from pursuing an alternative method of delivery to account for the same amount of natural gas. Practical considerations point in the opposite direction. Both the Board and the Commission have concluded Florida has a need for additional natural gas, and nothing in today’s оpinion takes issue with those holdings. Additionally, the Commis-sion has concluded that the failure to take action to address this natural-gas shortage “could result in ... fuel shortages” and “could lead to insufficient energy production to meet expected demands.” JA 920. Given the dire consequences of failing to act, it is inconceivable that the Intervenor utility companies would stand idly by and allow a power crisis to develop. The much more likely result is that they would simply choose another alternative—albeit a much more inconvenient, expensive, and possibly environmentally-harmful alternative—in response to a denial of a certificate by FERC. See Oral Arg. Rec. at 59:45-59:50 (stating the Intervenors are “going to keep the lights on” regardless of whether FERC approves the pipelines).
Thus, just as FERC in the DOE cases and the Federal Motor Carrier Safety Administration in Public Citizen did not have the legal power to prevent certain environmental effects, the Commission here has no authority to prevent the emission of greenhouse gases through newly-constructed or expanded power plants approved by the Board. To be sure, the Commission could make it extremely inconvenient to deliver the same amount of natural gas to the plants, but this is an issue of practicality, which, as conceded by the majority, is irrelevant under NEPA. See Maj. Op. at 1373. Accordingly, the Commission was not obligated under NEPA to discuss downstream greenhouse gas emissions, and I would deny the entire petition for review.
