History
  • No items yet
midpage
Van Buren Charter Township v. Visteon Corporation
319 Mich App 538
Mich. Ct. App.
2017
Read the full case

Background

  • Van Buren Charter Township (plaintiff) and Visteon Corporation (defendant) entered a 2010 Settlement Agreement concerning defendant’s obligations to cover any bond-payment shortfall for bonds issued by the township to finance Visteon Village.
  • In 2013 plaintiff’s consultant (PFM) produced projections showing an inevitable cash shortfall between 2017–2019 ranging roughly $23.7M–$36.4M unless new revenues were introduced.
  • Plaintiff sent the PFM report to Visteon and demanded immediate negotiations to determine Visteon’s payment obligation under Paragraph 3 of the Agreement; Visteon asserted it had no duty to negotiate until an actual shortfall occurred.
  • Plaintiff sued for declaratory judgment and breach of contract (failure to negotiate in good faith; anticipatory repudiation). The trial court granted summary disposition for defendant under MCR 2.116(C)(4) and (C)(8)/(C)(10).
  • The Court of Appeals affirmed, holding Paragraph 3 unambiguous (performance triggered by an actual shortfall), damages speculative at this time, and breach claims unripe.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Paragraph 3 is ambiguous and requires pre-shortfall negotiations Paragraph 3 is ambiguous and reasonably read to require timely/pre-shortfall negotiations Paragraph 3 is unambiguous: obligations (negotiate and make a PILOT) are triggered only after an actual shortfall Court: Paragraph 3 is unambiguous; shortfall is a condition precedent, no duty to negotiate before shortfall
Whether declaratory relief is warranted now An actual controversy exists—resolution needed to preserve rights and avoid catastrophic harm No justiciable controversy because contractual duty arises only after shortfall; declaratory relief discretionary Court: No actual controversy; refusal to grant declaratory relief was permissible
Whether plaintiff’s projected damages are sufficiently certain to support breach claim now PFM report shows shortfall is inevitable, so damages are certain Projections are speculative/contingent; amount and timing uncertain Court: Damages are speculative/hypothetical now; plaintiff cannot prove damages with required certainty
Whether Visteon anticipatorily repudiated or already breached by refusing to negotiate Visteon refused to negotiate and said it would not pay, constituting anticipatory repudiation and breach Visteon merely asserted it need not negotiate until performance is due and did not unequivocally refuse future performance Court: No unequivocal repudiation or present breach; claims are not ripe

Key Cases Cited

  • Lansing Schools Educ Ass’n v. Lansing Bd. of Educ., 293 Mich. App. 506 (procedural standard for declaratory-judgment review)
  • McDonald v. Farm Bureau Ins. Co., 480 Mich. 191 (contract interpretation is question of law)
  • Maiden v. Rozwood, 461 Mich. 109 (summary-disposition evidentiary standard)
  • PT Today, Inc. v. Comm’r of Fin. & Ins. Servs., 270 Mich. App. 110 (discretionary nature of declaratory relief)
  • Shavers v. Kelley, 402 Mich. 554 (when declaratory relief is necessary to guide future conduct)
  • Meagher v. Wayne State Univ., 222 Mich. App. 700 (ambiguity standard for contract interpretation)
  • Rory v. Continental Ins. Co., 473 Mich. 457 (courts may not rewrite unambiguous contracts)
  • Alan Custom Homes, Inc. v. Krol, 256 Mich. App. 505 (elements and damages standard for breach of contract)
  • Doe v. Henry Ford Health Sys., 308 Mich. App. 592 (damages cannot be speculative or contingent)
  • Stoddard v. Manufacturers Nat’l Bank, 234 Mich. App. 140 (anticipatory repudiation doctrine)
Read the full case

Case Details

Case Name: Van Buren Charter Township v. Visteon Corporation
Court Name: Michigan Court of Appeals
Date Published: May 16, 2017
Citation: 319 Mich App 538
Docket Number: 331789
Court Abbreviation: Mich. Ct. App.