Alan Custom Homes, Inc v. KrolAlan Custom Homes, Inc v. Krol
In this case involving breach of contract and a construction lien, defendants Kenneth and Karen Krol appeal as of right the judgment entered in favor of plaintiff Alan Custom Homes, Inc., following a bench trial. Plaintiff was awarded $42,763 plus interest, fees, and costs, for a total judgment of $57,512.62 against defendants. We affirm.
On October 24, 1998, defendants and plaintiff entered into a cost-plus contract
1
for plaintiff to build a custom home for defendants, at a cost of $262,466. Construction was delayed by waiting for permits, inclement weather, problems with draws, and changes in design. On January 4, 2000, defendants locked plaintiffs
On appeal, defendants claim that the trial court erred by denying their motion for summary disposition regarding plaintiff’s claim for foreclosure of the construction lien. We disagree. This Court reviews a trial court’s grant or denial of summary disposition de novo.
Spiek v Dep’t of Transportation,
The trial court apparently considered both MCR 2.116(C)(8) and (C)(10) as grounds for its summary-disposition decision. A motion for summary disposition under MCR 2.116(C)(8) tests the legal sufficiency of the claim on the pleadings alone to determine whether the plaintiff has stated a claim on which
relief may be granted.
Spiek, supra
at 337. A court must accept all factual allegations in the pleadings in support of the claim as true, as well as any reasonable inferences or conclusions that can be drawn from the facts, and construe those facts in the light most favorable to the nonmoving party.
Maiden v Rozwood,
Resolution of this issue requires us to interpret § 110 of the Construction Lien Act (cla),
If a contractor fails to provide a sworn statement to the owner or lessee before recording the contractor’s claim of hen, the contractor’s construction hen is not invalid. However, the contractor is not entitled to any payment, and a complaint, cross-claim, or counterclaim may not be filed to enforce the construction hen, until the sworn statement has been provided.
Defendants contend that this provision bars plaintiff’s foreclosure claim.
While a strict reading of
[t]he scope of a statutory “substantial compliance” provision requires an analysis, on a case-by-case basis, of the following logically relevant factors among others: the overall purpose of the statute; the potential for prejudice or unfairness when the apparent clarity of a statutory provision is replaced by the uncertainty of a “substantial compliance” clause; the interests of future litigants and the public; the extent to which a court can reasonably determine what constitutes “substantial compliance” within a particular context; and, of course, the specific language of the “sub stantial compliance” and other provisions of the statute. [Id. at 321-322.]
While
Northern Concrete Pipe
dealt with the applicability of the “substantial compliance” provision to the filing requirement of
In this case, application of the CIA’s “substantial compliance” provision supports plaintiff’s contention that its provision of unverified statements to the title company during construction and of a verified sworn statement to defendants before the summary-disposition hearing satisfied the notice requirement of
Therefore, we find that the unverified statements plaintiff gave to the title company to obtain draws
substantially complied with the statutory notice requirement of
In addition, plaintiff was entitled to maintain a cause of action against defendants for breach of contract, independent of any claim for foreclosure of the hen.
Defendants next contend that the trial court erred by dismissing their counterclaim for breach of contract without evaluating whether plaintiffs failure to provide accountings to them was a material breach. Again, we disagree. This Court reviews a trial court’s findings of fact in a bench trial for clear error and its conclusions of law de novo. MCR 2.613(C);
Chapdelaine v Sochocki,
A careful reading of the trial court’s findings indicates that the court did not find it necessary to decide whether plaintiff materially breached the contract before defendants locked plaintiff out, because defendants did not prove any damages from plaintiff’s alleged breach. The party asserting a breach of contract has the burden of proving its damages with reasonable certainty, and may recover only those damages that are the direct, natural, and proximate result of the breach.
In re F Yeager Bridge & Culvert Co,
Defendants also argue that the trial court clearly erred in upholding plaintiff’s claim of lien where the claim was excessive and made in bad faith. However,
this issue was not addressed by the trial court and is not properly before this Court.
Fast Air, Inc v Knight,
Defendants rely on
(1) Each contractor, subcontractor, supplier, or laborer who provides an improvement to real property shall have a construction hen upon the interest of the owner or lessee who contracted for the improvement to the real property, as described in the notice of commencement provided for by section 108 or 108a, the interest of an owner who has subordinated his or her interest to the mortgage for the improvement of the real property, and the interest of an owner who has required the improvement. A construction lien acquired pursuant to this act shall not exceed the amount of the lien claimant’s contract less payments made on the contract. [Emphasis added.]
A contractor shall not have a right to a construction lien upon the interest of any owner or lessee in a residential structure unless the contractor has provided an improvement to the residential structure pursuant to a written contract between the owner or lessee and the contractor and any amendments or additions to the contract also shall be in writing. [Emphasis added.]
The reference in
Furthermore, as plaintiff points out, the requirement of a written contract, and written amendments thereto, in
It is farther agreed that this agreement and any written amendments or addenda attached hereto contain all the representations and obligations of the respective parties and any modifications or changes herein shall be made in writing and executed by all the parties to this agreement otherwise the same shall not be binding upon the other party hereto.
But the addendum to the contract, executed at the same time as the contract, stated, “[i]f the actual cost of any individual line item(s) shall exceed the estimate provided on this list by Seller, these additional costs shall be the sole responsibility of the purchaser.” Defendants do not dispute that many of the cost overruns were due to their choice of fixtures and changes in design. Therefore, the written addendum, executed by both parties at the same time as the original contract, obligated defendants to pay for the expenses over the allowances estimated by plaintiff. Accordingly, plaintiffs claim of lien was supported by a written contract, as required by
In addition, we hold that the award of $17,000 for “extras” was not clearly erroneous inasmuch as the trial court indicated that it had “considered all the evidence relating to those ‘extras’ ” and “determined that the preponderance of the evidence supports the balance of $17,000 worth of ‘extras’ after credits to defendants.” It appears that the trial court “was aware of the issues in the case and correctly applied the law.”
Triple E Produce Corp v Mastronardi Produce, Ltd,
Affirmed.
Notes
A cost-plus construction contract is “[o]ne which fixes the amount to be paid the contractor on a basis, generally, of the cost of the material and labor, plus an agreed percentage thereof as profits. Such contracts are used when costs of production or construction are unknown or difficult to ascertain in advance.” Black’s Law Dictionary (6th ed).
The “substantial compliance” provision of the cla,
This act is declared to be a remedial statute, and shall be liberally construed to secure the beneficial results, intents, and purposes of this act. Substantial compliance with the provisions of this act shall be sufficient for the validity of the construction liens provided for in this act, and to give jurisdiction to the court to enforce them.
We note that defendants’ motion for summary disposition was filed one month before plaintiff delivered the sworn statement to defendants, but that the motion hearing was held three months after the sworn statement was delivered.
“Contract” means a contract, of whatever nature, for the providing of improvements to real property, including any and all additions to, deletions from, and amendments to the contract.