16 F. Supp. 3d 944
N.D. Ind.2014Background
- In 1990 U.S. Steel performed a full "reline" (major modification) of its No. 4 furnace at Gary Works without obtaining NSR/PSD preconstruction permits; EPA alleges this violated the Clean Air Act.
- EPA (with state co-plaintiffs) sued seeking civil penalties and injunctive relief for permitting violations tied to the 1990 work; damages claims were previously dismissed as time-barred under 28 U.S.C. § 2462.
- The court originally permitted the EPA’s request for injunctive relief but granted U.S. Steel’s motion to reconsider that portion after reviewing Seventh Circuit precedent.
- The central legal question is whether the government can still obtain injunctive relief more than five years after an alleged preconstruction permitting violation that was completed decades earlier.
- The court accepts EPA’s allegation that the 1990 work was a "major modification" for purposes of the motion-to-dismiss analysis and treats both PSD (42 U.S.C. § 7475) and nonattainment NSR (42 U.S.C. § 7503) preconstruction claims as functionally the same for this issue.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether injunctive relief is available for preconstruction permitting violations that were completed >5 years ago | Injunction still available; violation is continuing because the facility operates without required permits/BACT | Time-bar applies; violation was completed when construction commenced, so relief is untimely | Dismissed injunction claims as time-barred under the Seventh Circuit's Midwest Generation approach |
| Whether § 2462's five-year limit applies to equitable relief in government enforcement actions | Ongoing operation renders violation current; no limitations problem | § 2462 bars enforcement that accrued >5 years ago; concurrent-remedy and laches defenses don't bar government suits but Midwest Generation applies a five-year limit to these injunctions | Court follows Midwest Generation and treats the claim as untimely for injunctions |
| Whether failure to install BACT creates a continuing violation tied to the original construction-permit violation | EPA: ongoing failure to use BACT makes the violation current | U.S. Steel: operating without BACT is not a continuing § 7475 violation; any current operations-based violation would arise under other statutes/regulations | Court adopts Seventh Circuit view: § 7475 addresses construction, not continued operations; failure to install BACT during past construction is not a current § 7475 violation |
| Whether analogous § 7503 nonattainment claims survive because § 7475 limitation reasoning is inapplicable | EPA: § 7503 may reach ongoing operation and thus be actionable now | U.S. Steel: EPA pleaded § 7503 as a preconstruction claim mirroring § 7475, so same limit applies | Court treats § 7503 allegations as preconstruction claims and applies Midwest Generation logic to dismiss injunctive relief |
Key Cases Cited
- United States v. Midwest Generation, LLC, 720 F.3d 644 (7th Cir. 2013) (preconstruction PSD claim accrues at construction; injunctions for long-completed construction claims are untimely)
- United States v. EME Homer City Generation, L.P., 727 F.3d 274 (3d Cir. 2013) (construction-permit injunctions limited to ongoing violations; post-construction claims are not enjoinable under § 7475)
- Ashcroft v. Iqbal, 556 U.S. 662 (2009) (plausibility pleading standard under Rule 12(b)(6))
- Bell Atlantic v. Twombly, 550 U.S. 544 (2007) (pleading must state a plausible claim for relief)
- Cope v. Anderson, 331 U.S. 461 (1947) (concurrent-remedy doctrine: equity may withhold relief when a statute-of-limitations bars the legal remedy)
- Hollander v. Brown, 457 F.3d 688 (7th Cir. 2006) (plaintiff may plead facts that establish an affirmative defense such as untimeliness)
- Bogie v. Rosenberg, 705 F.3d 603 (7th Cir. 2013) (appellate court may affirm on any ground supported by the record and not waived)
