History
  • No items yet
midpage
Tamosaitis v. URS Inc.
781 F.3d 468
9th Cir.
2014
Read the full case

Background

  • Dr. Walter Tamosaitis, a URS Energy & Construction, Inc. (URS E & C) employee assigned to the Hanford Waste Treatment Plant (WTP) project, raised technical safety concerns (the “M3 mixing issue”) and sought more time to resolve them; Bechtel (the prime contractor) pushed to close the issue sooner.
  • After circulating a list of concerns and emailing consultants, Tamosaitis was removed from the WTP project on Bechtel’s urging and reassigned by URS to a non‑supervisory offsite position; he later lost bonuses and supervisory duties.
  • Tamosaitis filed an ERA (42 U.S.C. § 5851) administrative complaint with DOL‑OSHA naming “URS Inc.”; URS entities responded and clarified that URS Energy & Construction, Inc. was the employer on the subcontract.
  • After amendments (adding DOE and later naming URS Corp. and URS E & C) and one year of agency inaction, Tamosaitis filed in federal court under the §5851(b)(4) opt‑out provision and sought a jury trial; the district court dismissed DOE, granted summary judgment for URS Corp. and URS E & C (and struck the jury demand).
  • The Ninth Circuit affirmed dismissal of DOE and URS Corp. for failure to satisfy the one‑year administrative notice requirement, reversed summary judgment for URS E & C (finding triable issues on contributing‑factor causation and adverse action), and held there is a constitutional right to a jury trial for money damages under the ERA opt‑out action.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Does the ERA opt‑out one‑year exhaustion period run separately for each respondent named in the administrative complaint? Tamosaitis argued his overall agency filing satisfied exhaustion for defendants he later sued. URS/DOE argued adding defendants restarts the one‑year clock; must wait one year after naming each respondent. The court held exhaustion is respondent‑specific: a respondent must have had notice and an opportunity to participate in the agency process for one year before suit.
Was URS E & C adequately named in the original OSHA complaint despite using the name “URS Inc.”? Tamosaitis argued the agency and URS entities understood he meant URS E & C and URS E & C participated, so notice was adequate. URS Corp. argued it was not the employer/respondent and that amendment changed the respondent. The court held URS E & C was adequately identified (agency received and addressed URS E & C’s position), so exhaustion was satisfied as to URS E & C; URS Corp. was not adequately named and was dismissed.
Can URS E & C be liable where a contractor (Bechtel) with retaliatory motive pressed for removal? (causation and adverse action) Tamosaitis argued Bechtel’s retaliatory demand, URS E & C’s knowledge/acquiescence, and resulting transfer/ loss of duties/bonuses make protected activity a contributing factor. URS E & C argued Bechtel alone made the decision and contractual obligations compelled removal, so URS E & C did not take adverse action for retaliatory reasons. The court found triable issues: emails show Bechtel’s retaliatory motive and URS E & C’s compliance; protected activity can be a contributing factor when employer ratifies/acquiesces to a customer’s retaliatory request. Summary judgment for URS E & C was reversed.
Is there a right to a jury trial for ERA §5851(b)(4) opt‑out actions seeking money damages? Tamosaitis argued the claim sounds in tort, seeks compensatory damages (legal relief), and thus triggers the Seventh Amendment right to jury. Defendants argued statutory silence and the public‑right/administrative enforcement context allow nonjury adjudication; monetary relief is incidental/equitable. The court held there is a constitutional right to a jury trial for money damages in district court under the ERA opt‑out provision because the claim and damages are legal in nature; the administrative origin does not eliminate the jury right once in federal court.

Key Cases Cited

  • Mackowiak v. Univ. Nuclear Sys., Inc., 735 F.2d 1159 (9th Cir. 1984) (ERA protects workers from retaliation based on safety/quality concerns)
  • DeFord v. Secretary of Labor, 700 F.2d 281 (6th Cir. 1983) (purpose of whistleblower protections to preserve information channels)
  • Weinberger v. Salfi, 422 U.S. 749 (1975) (rationale for exhaustion: allow agency correction and record development)
  • City of Monterey v. Del Monte Dunes at Monterey, Ltd., 526 U.S. 687 (1999) (statutory “action at law” is not alone conclusive for a statutory jury right analysis)
  • Feltner v. Columbia Pictures Television, Inc., 523 U.S. 340 (1998) (analysis of when statutory suits seeking legal relief require jury trial)
  • Lorillard v. Pons, 434 U.S. 575 (1978) (statutory language and incorporated procedures can indicate a jury right)
  • Granfinanciera, S.A. v. Nordberg, 492 U.S. 33 (1989) (distinguishing public‑rights administrative adjudication from Seventh Amendment jury right in federal courts)
  • Tull v. United States, 481 U.S. 412 (1987) (Seventh Amendment analysis requires examining nature of remedy sought)
  • Gerdom v. Continental Airlines, Inc., 692 F.2d 602 (9th Cir. 1982) (an employer cannot justify discriminatory action based on a customer’s discriminatory preference)
Read the full case

Case Details

Case Name: Tamosaitis v. URS Inc.
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Nov 7, 2014
Citation: 781 F.3d 468
Docket Number: No. 12-35924
Court Abbreviation: 9th Cir.