History
  • No items yet
midpage
Southwinds Express Construction, LLC v. D.H. Griffin of Texas, Inc.
513 S.W.3d 66
Tex. App.
2016
Read the full case

Background

  • Griffin contracted as demolition subcontractor; Southwinds was hired to haul concrete, brick, and later C&D (construction & demolition) debris after an oral modification setting C&D at $9/yd and a revised (unexecuted) written subcontract.
  • The original written Subcontractor Agreement (signed) contained a broad arbitration clause and a dispute-resolution paragraph requiring mediation unless Griffin in its sole discretion deemed mediation useless and escalated to binding arbitration.
  • A dispute arose alleging Southwinds ceased work and failed to pay landfill fees, leaving Griffin to pay $67,000 in landfill arrearages and hire third parties; Griffin sought arbitration in March 2014.
  • Arbitrator held the oral agreement modified the subcontract, brought C&D claims within the arbitration clause, found Southwinds breached, and awarded damages, fees, and costs to Griffin.
  • Trial court confirmed the award; Southwinds moved to vacate arguing (1) arbitration clause did not cover C&D claims, (2) mediation was a condition precedent that did not occur, and (3) the award reflected manifest disregard/gross mistake. The court affirmed the confirmation on appeal.

Issues

Issue Griffin's Argument Southwinds' Argument Held
Arbitrability of C&D claims Oral agreement modified the subcontract so C&D claims fall within the written arbitration clause Oral agreement was a separate contract; claims arising from it are not covered by the subcontract arbitration clause Court (de novo) held C&D claims were factually intertwined with and within the scope of the broad arbitration clause, so arbitrable
Who decides arbitrability AAA rules and the parties’ agreement delegate arbitrability to the arbitrator Threshold challenge to existence/scope of arbitration (separate oral agreement) means court must decide arbitrability Court held that when existence of an agreement is challenged (claims arise from separate agreement), the trial court decides arbitrability; here court independently determined arbitrability and affirmed arbitrability of C&D claims
Mediation as condition precedent Arbitration provision allowed Griffin to skip mediation; thus mediation was not a condition precedent Griffin’s unilateral opt-out rendered clause illusory or mediation must be performed before arbitration; no mediation occurred Court held Griffin’s unilateral right to bypass mediation did not make the arbitration clause illusory; mediation was not a condition precedent to Griffin’s ability to arbitrate
Manifest disregard / gross mistake Award should be vacated for manifest disregard and gross legal error in covering non-arbitrable claims Manifest disregard and gross mistake are not statutory grounds for vacatur; arbitration award should be confirmed absent statutory grounds Court held neither manifest disregard nor gross mistake are grounds under the Texas Arbitration Act or FAA; because statutory vacatur grounds were not met, confirmation was proper

Key Cases Cited

  • Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79 (2002) (distinguishes procedural vs. substantive arbitrability; procedural matters presumptively for arbitrator)
  • First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938 (1995) (parties must clearly and unmistakably delegate arbitrability to arbitrator)
  • In re Morgan Stanley & Co., 293 S.W.3d 182 (Tex. 2009) (where existence of agreement is challenged, courts decide threshold issue)
  • Hoskins v. Hoskins, 497 S.W.3d 490 (Tex. 2016) (Texas Arbitration Act requires confirmation unless statutory vacatur grounds are shown)
  • Valero Energy Corp. v. Teco Pipeline Co., 2 S.W.3d 576 (Tex. App.-Houston [14th Dist.] 1999) (court determines if claims arise out of separate agreement and thus outside prior arbitration clause)
  • John Wiley & Sons, Inc. v. Livingston, 376 U.S. 543 (1964) (arbitrator generally decides grievance-procedure completion; historical precedent on procedural matters)
  • In re Bath Junkie Franchise, Inc., 246 S.W.3d 356 (Tex. App.-Beaumont 2008) (claims arising from subsequent agreement may fall within original arbitration clause if factually intertwined)
Read the full case

Case Details

Case Name: Southwinds Express Construction, LLC v. D.H. Griffin of Texas, Inc.
Court Name: Court of Appeals of Texas
Date Published: Nov 15, 2016
Citation: 513 S.W.3d 66
Docket Number: NO. 14-15-00610-CV
Court Abbreviation: Tex. App.