SOUTHWINDS EXPRESS CONSTRUCTION, LLC, Appellant v. D.H. GRIFFIN OF TEXAS, INC., Appellee
NO. 14-15-00610-CV
Court of Appeals of Texas, Houston (14th Dist.).
Opinion filed November 15, 2016
Robert Joseph Killeen Jr., Houston, TX, for Appellant.
Panel consists of Chief Justice Frost and Justices Boyce and Wise.
OPINION
William J. Boyce, Justice
Southwinds Express Construction, LLC challenges the trial court‘s judgment confirming an arbitration award in favor of D.H. Griffin of Texas, Inc. Southwinds contends that the trial court erred in confirming the arbitrator‘s award because (1) the arbitration agreement between the parties did not cover the claims asserted
BACKGROUND
The Lemoine Company contracted with Griffin in 2013 to serve as the demolition subcontractor on a construction, renovation, and demolition project for a hospital in Louisiana. Griffin, in turn, requested bids from Southwinds for the removal of construction and demolition debris from the project site.
Southwinds proposed that it would perform (1) “concrete excavation and haul off” for free; (2) brick haul-off for $40 per truckload; and (3) construction and demolition (“C&D“) haul-off for $12 per cubic yard plus disposal fees. Griffin accepted Southwinds‘s proposal concerning concrete haul-off and brick haul-off, but declined the proposed terms for C&D haul-off.
Griffin and Southwinds entered into a Subcontractor Agreement reflecting their agreement on September 26, 2013. This agreement included a provision requiring arbitration of “a claim” made by either party.
The arbitration provision in paragraph 3 of the Subcontractor Agreement states as follows:
In the event that a claim is not resolved through the negotiations of the parties, claim resolution will be resolved through mediation unless, in the sole discretion of [Griffin], [Griffin] believes mediation would be a useless exercise in which case [Griffin], unilaterally, may escalate the claims process to binding arbitration at any time. If mediation fails, both parties agree that the claim will be resolved pursuant to binding arbitration. Any mediation or arbitration will be conducted under the rules of the American Arbitration Association‘s (“AAA“) Construction Industry Dispute Resolution Procedures (including Mediation and Arbitration Rules) in effect at the time of the execution of this Agreement; provided, however, that where there is a conflict, if any, between those rules and this Agreement, this Agreement governs.
This written agreement included an attached “Exhibit A” that identified the scope of work under the agreement as follows:
Southwinds Express Construction LLC will remove and haul off concrete slabs, foundations and parking at the [hospital] site in Lafayette, Louisiana for No Charge. Southwinds Express Construction LLC will haul brick and concrete generated from the demolition operation for Forty Dollars ($40.00) per load.
Weeks later, Griffin and Southwinds orally agreed that Southwinds would perform C&D haul-off for $9 per cubic yard including disposal fees.1
In the portion of the contract stating that Griffin would pay Southwinds for invoiced amounts within 10 days after Griffin received payment from Lemoine, Southwinds interlineated “except for trucking and dump fees which will be Net 14.” Similarly, Southwinds modified the scope of work exhibit with the interlineation, “Payment terms will be Net 14.” Southwinds executed the modified second agreement. The parties dispute whether
Griffin contends that Southwinds stopped paying landfill disposal fees in November and December 2013, and that the landfill owner consequently barred Southwinds from use of the landfill. Griffin contends that with no landfill available for debris disposal, Southwinds abandoned work on the project and left Griffin with landfill fee arrearages totaling $67,000. Griffin contends that it was required to pay the landfill fees because the landfill operator threatened to place a lien on the project property if the fees were not paid. Griffin also contends that it had to hire third parties to complete the removal of construction and demolition debris.
Griffin filed a demand for arbitration in March 2014. Southwinds objected to the arbitrator‘s jurisdiction, contending that the arbitration provision in the written Subcontractor Agreement did not extend to any claims arising from the subsequent oral agreement to provide C&D haul-off services. The arbitrator overruled Southwinds‘s objection.
A two-day arbitration hearing was held in January 2015. The arbitrator issued an Award of Arbitration on March 12, 2015. In its award, the arbitrator found that the oral agreement was a modification of the Subcontractor Agreement; the oral agreement caused the C&D haul-off to be included within the scope of work of the Subcontractor Agreement; and any claim relating to the C&D haul-off therefore was a claim under the Subcontractor Agreement subject to the Subcontractor Agreement‘s arbitration provision.
Concluding she had jurisdiction to consider this dispute, the arbitrator determined that Southwinds breached its agreement with Griffin. The arbitrator awarded Griffin $42,251.20 in actual damages, $36,851.08 in attorney‘s fees, and $8,800 in arbitration fees and expenses; she also ordered Southwinds to release a lien it had filed against the project.
Griffin sought to have the arbitration award confirmed in district court in April 2015. After briefing and argument from the parties, the trial court signed a final judgment confirming the arbitration award on June 16, 2015. Southwinds appealed.
STANDARD OF REVIEW
We review a trial court‘s decision to confirm or vacate an arbitration award under a de novo standard of review. D.R. Horton-Tex., Ltd. v. Bernhard, 423 S.W.3d 532, 534 (Tex. App.—Houston [14th Dist.] 2014, pet. denied). “Review of an arbitration award is ‘extraordinarily narrow.‘” Amoco D.T. Co. v. Occidental Petroleum Corp., 343 S.W.3d 837, 841 (Tex. App.—Houston [14th Dist.] 2011, pet. denied) (quoting Statewide Remodeling, Inc. v. Williams, 244 S.W.3d 564, 568 (Tex. App.—Dallas 2008, no pet.)). We give an arbitration award great deference and indulge every reasonable presumption in favor of the award and none against it. CVN Grp., Inc. v. Delgado, 95 S.W.3d 234, 238 (Tex. 2002); Amoco D.T. Co., 343 S.W.3d at 841.
ANALYSIS
I. Arbitrability of the C&D Claims
Southwinds contended below that the C&D haul-off claims were not covered by a valid arbitration agreement because they were the subject of the parties’ oral agreement—which, according to Southwinds,
After the arbitrator ruled in Griffin‘s favor on the merits, Griffin filed an action in district court seeking confirmation of the arbitrator‘s award. Southwinds moved to vacate the award, contending the arbitrator exceeded her power by deciding matters outside the scope of her authority—namely, the C&D haul-off claims.
In its final judgment confirming the arbitrator‘s award, the trial court stated:
The Court is persuaded that the agreement between the parties contemplated additional potential work such as the C&D work. Thus, this work arose out of the agreement and, consequently, the arbitration agreement contemplated additional work. Further, the issue of whether there was, in fact, an enforceable oral agreement to do the C&D work was for the arbitrator to decide, not this Court. The Court will note, though, that the agreement between the parties does NOT state that no subsequent oral agreements could be formed; only that no oral representations prior to the written agreement existed or were relied upon.
On appeal, Southwinds contends the trial court erred in determining that C&D haul-off claims fell within the scope of the Subcontractor Agreement‘s arbitration provision. Griffin responds that the Subcontractor Agreement‘s arbitration provision governed at least a portion of the dispute between the parties; the arbitration provision referenced that any arbitration would be conducted pursuant to the American Arbitration Association (“AAA“) rules, which state that determinations of arbitrability shall be made by the arbitrator; and the parties therefore clearly and unmistakably agreed to submit the determination of arbitrability of the C&D haul-off claims to the arbitrator rather than the trial court.
A. Who Determines Arbitrability?
Arbitration is a matter of contract. Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 83, 123 S.Ct. 588, 154 L.Ed.2d 491 (2002).2 The question of arbitrability addresses which claims must be arbitrated. Leshin v. Oliva, No. 04-14-00657-CV, 2015 WL 4554333, at *5 (Tex. App.—San Antonio July 29, 2015, no pet.) (mem. op.); see also Saxa Inc. v. DFD Architecture Inc., 312 S.W.3d 224, 229 (Tex. App.—Dallas 2010, pet. denied) (questions of arbitrability include “whether the parties agreed to arbitrate and whether a claim or dispute is encompassed in the agreement to arbitrate“).
When there is an undisputed arbitration provision in an agreement between the parties, we ordinarily look to the arbitration provision‘s language to determine whether the parties “clearly and unmistakably” intended for the arbitrator to determine arbitrability or instead left that decision to the trial court. See Howsam, 537 U.S. at 83, 123 S.Ct. 588; First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 944, 115 S.Ct. 1920, 131 L.Ed.2d 985 (1995).
Southwinds therefore challenges the existence of an agreement to arbitrate the C&D haul-off claims. As the Supreme Court of Texas has explained:
[W]here the very existence of an agreement is challenged, ordering arbitration could result in an arbitrator deciding that no agreement was ever formed. Such an outcome would be a statement that the arbitrator never had any authority to decide the issue. ... We therefore conclude that where a party attacks the very existence of an agreement, as opposed to its continued validity or enforcement, the courts must first resolve that dispute.
In re Morgan Stanley & Co., 293 S.W.3d 182, 189 (Tex. 2009) (quoting Will-Drill Res., Inc. v. Samson Res. Co., 352 F.3d 211, 219 (5th Cir. 2003)) (emphasis in original).
In Texas La Fiesta Auto Sales, LLC v. Belk, 349 S.W.3d 872 (Tex. App.—Houston [14th Dist.] 2011, no pet.), we considered the situation in which a valid arbitration agreement was acknowledged to exist but was alleged to have merged into a later arbitration agreement with different terms. Id. at 879-80. The appellants contended that, once it was determined a valid arbitration agreement existed, any issue concerning merger should have been decided by the arbitrator. Id. at 880. We concluded that the issue of whether the subsequent contract‘s arbitration provision superseded the initial arbitration agreement was a question for the trial court. Id. Explaining our conclusion, we noted that “it is the trial court‘s duty to determine whether a later agreement between the parties revokes an arbitration clause, because the court must determine the threshold issue of whether a valid arbitration agreement exists.” Id. at 881.
In Valero Energy Corp. v. Teco Pipeline Co., 2 S.W.3d 576 (Tex. App.—Houston [14th Dist.] 1999, no pet.), we considered a party‘s argument that “its claims are not based on the Operating Agreement, which contains an arbitration clause, but rather, arise out of a separate unwritten partnership agreement, which was created as a result of the sale of the 50% undivided interest in the pipeline.” Id. at 584. The party argued that, because its claims were related to the separate partnership, those claims were not subject to the Operating Agreement‘s arbitration provision. Id. Although we did not make an explicit statement to this effect, our de novo review of the issue indicates that we reviewed an issue decided by the trial court rather than the arbitrator. See id. at 584-86.
These cases inform our analysis here. Similar to the argument advanced in Valero, Southwinds contends the C&D haul-off claims arise from a separate agreement. Consistent with Valero, we conclude that the arbitrability of the C&D haul-off claim is a matter for trial court determination because those claims allegedly stem from a separate agreement. See id. We reach this conclusion because, as we stated in Texas La Fiesta, the trial court must determine the threshold issue of whether a valid arbitration agreement exists under circumstances like those present here. See Texas La Fiesta, 349 S.W.3d at 881; see also In re Bath Junkie Franchise, Inc., 246 S.W.3d 356, 364 (Tex. App.—Beaumont 2008, orig. proceeding)
When, as in this case, the arbitrator determines arbitrability even though it is a question for the trial court, we ordinarily would remand for the trial court to consider the issue. See, e.g., Leshin, 2015 WL 4554333, at *8 (“Whether Leshin was a party to the arbitration agreement under some legal theory is a question of arbitrability, which is for the trial court to determine. Therefore, we reverse the trial court‘s judgment confirming the arbitration award and remand ... for the trial court to consider the arbitrability issue and determine whether there is any legal theory that would allow the trial court to compel Leshin, in his individual capacity, to arbitrate and be bound by any ensuing award.“); Elgohary v. Herrera, 405 S.W.3d 785, 793-94 (Tex. App.—Houston [1st Dist.] 2013, no pet.) (remanding for trial court to consider arbitrability). Because the trial court already has made an independent determination that the claims were arbitrable, we review the trial court‘s determination for error. See, e.g., Roe v. Ladymon, 318 S.W.3d 502, 518 (Tex. App.—Dallas 2010, no pet.) (reviewing trial court‘s independent determination of arbitrability de novo).
B. Were the C&D Claims Arbitrable?
Both the arbitrator and the trial court determined that the C&D haul-off claims were governed by the Subcontractor Agreement‘s arbitration provision. Despite the uniformity of result, our determination that it was the trial court‘s prerogative to resolve the question of arbitrability is important because it determines the applicable standard of review. See id. at 511. As the court succinctly summarized in Ladymon:
The parties to this appeal disagree about a preliminary—but critical—question of law: who has the primary power to decide whether Ladymon is required to arbitrate—the arbitrator or a court? The answer determines the applicable standard of review: if the question is primarily for the arbitrator to decide, courts will review the arbitrator‘s determination of that issue with great deference, but if the question is primarily for the court to decide, courts will review the question independently or de novo.
Id.; see also McReynolds v. Elston, 222 S.W.3d 731, 740 (Tex. App.—Houston [14th Dist.] 2007, no pet.) (“Determining whether a claim falls within the scope of an arbitration agreement involves the trial court‘s legal interpretation of the agreement, and we review such interpretations de novo.“). Accordingly, we review de novo the trial court‘s determination that the Subcontractor Agreement‘s arbitration provision governed the C&D haul-off claims. See, e.g., In re Guggenheim Corp. Funding, LLC, 380 S.W.3d 879, 886 (Tex. App.—Houston [14th Dist.] 2012, orig. proceeding) (“[A] determination of the scope of an unambiguous arbitration clause is a matter of contract interpretation and a question of law for the trial court.“).
Griffin contends that the oral agreement modified the Subcontractor Agreement, leaving intact the Subcontractor Agreement‘s arbitration provision and extending its reach to encompass the C&D haul-off claims.
The trial court stated in its final judgment that “the agreement between the
Claims generally are arbitrable when the facts alleged “touch matters” that are covered by, have a “significant relationship” to, are “inextricably enmeshed” with, or are “factually intertwined” with the contract that contains the arbitration provision. AutoNation USA Corp. v. Leroy, 105 S.W.3d 190, 195 (Tex. App.—Houston [14th Dist.] 2003, no pet.); In re Bath Junkie Franchise, Inc., 246 S.W.3d at 366; see also Branch Law Firm L.L.P. v. Osborn, No. 14-14-00892-CV, — S.W.3d —, —, 2016 WL 444867, at *12 (Tex. App.—Houston [14th Dist.] Feb. 4, 2016, pet. denied) (“Where, as here, the contract includes a broad arbitration clause, we consider whether the facts alleged are sufficiently intertwined with the contract and thus arbitrable.“); Ascendant Anesthesia PLLC v. Abazi, 348 S.W.3d 454, 462 (Tex. App.—Dallas 2011, no pet.) (recognizing that claims may become arbitrable when factually intertwined with arbitrable claims). “To be within the scope of an arbitration provision, the allegations need only be factually intertwined with arbitrable claims or otherwise touch upon the subject matter of the agreement containing the arbitration provision.” In re Prudential Sec. Inc., 159 S.W.3d 279, 283 (Tex. App.—Houston [14th Dist.] 2005, orig. proceeding). We resolve any doubt about the “scope of arbitrable issues” in favor of arbitration. Green Tree Fin. Corp. v. Bazzle, 539 U.S. 444, 452, 123 S.Ct. 2402, 156 L.Ed.2d 414 (2003); Valero, 2 S.W.3d at 590.
Here, we agree with the trial court that the Subcontractor Agreement contemplated additional work. The Subcontractor Agreement stated that Griffin could “at any time require deviation from” the Subcontractor Agreement, including material changes to the scope of work, by providing authorization to Southwinds.3
Additionally, the Subcontractor Agreement‘s broad arbitration provision covered “a claim by [Southwinds] against [Griffin]” and “a claim [filed by Griffin] against [Southwinds].” The parties did not limit the arbitration provision‘s scope to claims arising out of the Subcontractor Agreement or to claims related to the Subcontractor Agreement. The parties placed no limitation on the nature of the claims be-
tween them that fell within the arbitration provision. Because of the broad nature of this arbitration provision, we consider whether the C&D haul-off claims are sufficiently intertwined with the Subcontractor Agreement to be arbitrable. See Branch Law Firm L.L.P., — S.W.3d at —, 2016 WL 444867, at *12. The C&D haul-off claims involved the same construction project and the same essential type of work being performed; they differed only in the type of debris removed. Accordingly, we conclude the C&D haul-off claims had a significant relationship to, and were factually intertwined with, the Subcontractor Agreement.Considering that the contract contemplated additions to the scope of work such as the C&D haul-off, and considering that the asserted claims had a significant relationship with and were factually intertwined with the contractual responsibilities identified in the Subcontractor Agreement, the trial court correctly determined that the C&D haul-off claims were governed by that agreement‘s broad arbitration provision.4 See In re Bath Junkie Franchise, Inc., 246 S.W.3d at 366-67 (noting that, “[w]ithout the parties’ relationship that arose from the Franchise Agreement, Hygiene and Bath Junkie would not have entered into the Termination Agreement,” and concluding that the claims involving the Termination Agreement arose out of and related to the Franchise Agreement and were “within the scope of the claims the parties agreed to submit to arbitration” under the Franchise Agreement); Gerwell v. Moran, 10 S.W.3d 28, 32-33 (Tex. App.—San Antonio 1999, no pet.) (where parties entered into an original agreement and a subsequent agreement, with an arbitration provision contained only in the original agreement, claims based on the subsequent agreement were arbitrable where arbitration provision was broad and subsequent agreement was contemplated by original agreement).
We also note that neither the
The parties here agree that, after they executed the Subcontractor Agreement, they mutually agreed that Southwinds would perform C&D haul-off services for $9 per cubic yard. To that end, Griffin sent Southwinds a new contract. The contract was identical to the original Subcontractor Agreement except that it included one additional sentence in the “Scope of Work” exhibit stating that Southwinds would perform C&D haul-off services at $9 per cubic
Based on this record, these payment terms were not essential to the agreement. See, e.g., Eastman Gas Co. v. Goodrich Petroleum Co., 456 S.W.3d 319, 329 (Tex. App.—Texarkana 2015, pet. denied) (concluding that “the manner of payment and the amount and rate of interest [were] not essential terms” in that instance and the agreement was therefore enforceable). The parties agreed on all material terms and agreed to be bound by the arbitration provision. See Hardin Constr. Grp., Inc. v. Strictly Painting, Inc., 945 S.W.2d 308, 313 (Tex. App.—San Antonio 1997, no writ) (where subcontractor never signed agreement provided by general contractor based on objection to single non-essential term but parties otherwise performed under the terms of the agreement, “the only reasonable conclusion that [the trial court] could have reached was that [the subcontractor] agreed to be bound by all the terms of the subcontract except the [non-essential term],” and that the parties therefore agreed to arbitrate under the arbitration provision in the agreement).
Finally, after having relied on the second written agreement in asserting its counterclaim during the arbitration proceeding, Southwinds cannot argue convincingly that the arbitration provision in that agreement is unenforceable. See In re Citgo Petroleum Corp., 248 S.W.3d at 775 (“Having affirmatively used the “Dispute Resolution Agreement” to support a claim based on the same injury, Rose‘s challenge to the existence of the agreement based solely on the lack of a signature for Pat Tank is not persuasive.“).
The trial court properly determined that the C&D haul-off claims were arbitrable.5
II. Mediation as a Condition Precedent to Arbitration
Southwinds next contends that the trial court erred in determining that mediation was not a condition precedent to arbitration.6
The Subcontractor Agreement provides:
In the event that a claim is not resolved through the negotiations of the parties, claim resolution will be resolved through
Southwinds argues that Griffin‘s “bilateral promise to adhere to a specific [dispute resolution] process is illusory and unenforceable” because Griffin “at its own option or whim ... can stop the dispute resolution process and escalate it” by skipping mediation and going straight to arbitration. According to Southwinds, “[T]he Subcontractor Agreement does not equally bind both parties to the same dispute resolution procedure” because “Griffin‘s promise to adhere to the dispute resolution procedure is totally optional to it, but not Southwinds.” Southwinds asserts as follows: “If enforced as written, [the arbitration provision] deprives Southwinds of a valuable right to resolve disputes through mediation.”
Southwinds contends that, after the Subcontractor Agreement is reformed to remove Griffin‘s supposedly illusory promise, the agreement requires arbitration of claims only if the claims are first mediated unsuccessfully. Because mediation did not occur, Southwinds contends that arbitration was improper due to the failure to satisfy a condition precedent.
A. Who Determines Whether an Arbitration Provision is Illusory?
Before reaching the merits of Southwinds‘s contention, we first must address whether the trial court or the arbitrator decides whether the arbitration provision is illusory and unenforceable. We agree with Southwinds that this determination is the trial court‘s to make, but we rely on a different basis than the one Southwinds urges.
Generally, “[o]nce it is determined that the parties are obligated to submit to arbitration, ‘procedural’ questions which grow out of the dispute and bear on its final disposition should be left to the arbitrator.” Valero, 2 S.W.3d at 583 (quoting John Wiley & Sons, Inc. v. Livingston, 376 U.S. 543, 557, 84 S.Ct. 909, 11 L.Ed.2d 898 (1964)). In Valero, we concluded that the arbitrator decided whether conditions precedent to arbitration were satisfied. Id. at 584.
Southwinds relies on Amir v. International Bank of Commerce, 419 S.W.3d 687 (Tex. App.—Houston [1st Dist.] 2013, no pet.), to argue that this case falls within an exception to the general rule.
Amir acknowledged that, “[t]ypically, questions of whether prerequisites to arbitration have been fulfilled are left to the arbitrators to resolve.” Id. at 692. The court went on to observe as follows:
If, however, there is clearly established proof that a strictly procedural requirement has not been met and that procedural requirement precludes arbitration, a court can deny a motion to compel arbitration on this ground. This is a narrow exception. As an example, a trial court cannot compel arbitration when the provision requires the parties to mediate before arbitration. To do so would frustrate the parties’ original intent clearly expressed in the agreement.
Id. (internal citations omitted); see also In re Igloo Prods. Corp., 238 S.W.3d 574, 579-81 (Tex. App.—Houston [14th Dist.] 2007, orig. proceeding [mand. denied]) (where neither party suggested that arbitration agreement was ambiguous or that condition precedent had been satisfied, issue was really a “‘gateway dispute’ as to whether the arbitration agreement covers a particular kind of controversy” for the trial court to decide).
Amir addresses situations in which “there is clearly established proof that a strictly procedural requirement has not been met and that procedural requirement precludes arbitration“—such as, the court notes, where the parties’ agreement clearly requires the parties to mediate before arbitration. See Amir, 419 S.W.3d at 692. In re Igloo involved an arbitration provision restricted to “disputes that cannot first be resolved through [Igloo‘s] internal dispute resolution procedures or mediation.” See In re Igloo, 238 S.W.3d at 581. It was undisputed that no mediation had occurred. See id.
This case, in contrast, involves an arbitration provision that expressly allows Griffin unilaterally to “escalate the claims process to binding arbitration at any time.” Thus, this case does not fall within the “narrow exception” under which the agreement unambiguously requires mediation as a condition precedent to arbitration. See id.; cf. In re Pisces Foods, L.L.C., 228 S.W.3d 349, 351, 353 (Tex. App.—Austin 2007, orig. proceeding) (employment agreement requiring both employee and employer to follow multi-step dispute resolution program—including mediation—before arbitrating raised “no question of fact with respect to the mediation prerequisite,” and “expressly require[d] mediation as a precondition for requesting arbitration“).
Southwinds is correct that the determination here was for the trial court to make, but not for the reason it advances. Southwinds contends that we must (1) determine that Griffin‘s option to avoid mediation makes the arbitration provision illusory; and then (2) read the option out of the agreement. After removing the option, Southwinds argues that mediation is a condition precedent to arbitration. Because Griffin indisputably did not mediate before arbitrating, Southwinds contends that this case falls within the “narrow exception” described above so the trial court can decide a strictly procedural requirement was not met.
Southwinds flips the order in which we must proceed. Contrary to Southwinds‘s assertion, the threshold question is not whether a condition precedent was satisfied. Instead, the threshold question is whether an arbitration provision allowing one contracting party to skip mediation before arbitrating is illusory and unenforceable. A decision on the arbitration provision‘s enforceability comes before a decision on whether the arbitration provision imposes a condition precedent.
When Southwinds asserts that Griffin‘s option to skip mediation makes the arbitration provision illusory, Southwinds attacks the arbitration provision itself as being unenforceable as drafted. This unenforceability challenge was the trial court‘s to decide. See In re Labatt Food Serv., L.P., 279 S.W.3d 640, 643 (Tex. 2009, orig. proceeding) (whether there is
B. Did Griffin‘s Option Not to Mediate Before Arbitrating Make the Arbitration Provision Illusory and Unenforceable?
In reaching its conclusion that mediation was not a condition precedent to arbitration, the trial court necessarily concluded that Griffin‘s unilateral option to bypass mediation before arbitrating did not make the arbitration provision illusory and unenforceable. We agree.
“An arbitration clause is not illusory unless one party can avoid its promise to arbitrate by amending the provision or terminating it altogether.” In re 24R, Inc., 324 S.W.3d 564, 567 (Tex. 2010, orig. proceeding). The mere fact that an arbitration provision is one-sided does not make it illusory. Royston, Rayzor, Vickery, & Williams, LLP v. Lopez, 467 S.W.3d 494, 505 (Tex. 2015); NACE Int‘l v. Johnson, No. 01-15-00529-CV, 2016 WL 4486158, at *3 (Tex. App.—Houston [1st Dist.] Aug. 25, 2016, no pet.) (mem. op. on reh‘g).
The arbitration agreement in NACE provided that disputes would be resolved through arbitration but allowed NACE the unilateral right to pursue litigation if it was unsatisfied by the arbitration result. NACE Int‘l, 2016 WL 4486158, at *1. The other party maintained that the arbitration agreement was illusory “because NACE effectively never agreed to submit itself to binding arbitration when it reserved the right to pursue litigation if a ‘satisfactory settlement’ is not reached by the arbitration process.” Id. at *3. The court concluded that, “[b]ecause both NACE and Appellees must first arbitrate all claims and neither can avoid that promise by amending or terminating the arbitration clause, the arbitration agreement is not illusory.” Id. at *4.
The arbitration provision in this case provided that the parties would mediate all disputes unless Griffin in its sole discretion believed that mediation would be useless, in which case Griffin could escalate directly to arbitration. The agreement did not allow Griffin to avoid arbitration; nor did it allow Griffin to litigate an unsatisfactory arbitration result. We conclude that Griffin‘s ability to unilaterally bypass mediation in favor of arbitration did not render the arbitration provision illusory. See id. at *4; Cleveland Constr., Inc. v. Levco Constr., Inc., 359 S.W.3d 843, 853-54 (Tex. App.—Houston [1st Dist.] 2012, pet. dism‘d) (party‘s promise to arbitrate claims “at [its] option” did not make arbitration provision illusory); see also In re Palm Harbor Homes, Inc., 195 S.W.3d 672, 678 (Tex. 2006) (orig. proceeding) (rejecting argument that arbitration agreement was substantively unconscionable because it bound homebuyers to arbitrate with the manufacturer but did not bind the manufacturer to arbitrate with homebuyers).
Having concluded that the arbitration provision was not illusory, we further agree with the trial court‘s conclusion that, under the plain language of the parties’ agreement allowing Griffin the option to bypass mediation, mediation was not a condition precedent to arbitration for Griffin. Cf. In re Pisces Foods, 228 S.W.3d at 351
III. Manifest Disregard and Gross Mistake
In its final issue, Southwinds argues that the arbitration award should be vacated because it is tainted by manifest disregard of the law and gross mistake in applying the law. Southwinds contends that the arbitrator manifestly disregarded the law and made a gross mistake of law in deciding matters that were not covered by a valid arbitration agreement.
Under the
Likewise, neither gross mistake nor manifest disregard of the law is a basis for vacating an arbitration award under the
Accordingly, regardless of whether the
Additionally, because we have concluded above that a valid and enforceable arbitration agreement covered all claims, including the C&D haul-off claims, Southwinds‘s argument that there was no valid arbitration agreement cannot form the basis for any manifest disregard of the law or gross mistake in applying the law on the part of the arbitrator.7
CONCLUSION
Having concluded that a valid and enforceable arbitration agreement existed covering all claims between the parties and that Southwinds failed to demonstrate any meritorious grounds for vacatur of the arbitrator‘s award, we conclude that the trial court properly confirmed the award. We affirm the trial court‘s judgment.
(Frost, C.J., concurring).
Kem Thompson Frost, Chief Justice, concurring
In this case, in which no party moved to compel or stay arbitration, the trial court confirmed an arbitration award under the
Grounds for vacatur not listed in Texas Civil Practice and Remedies Code section 171.088 fail.
The trial court confirmed an arbitration award as to the C&D haul-off claims asserted by appellee/applicant D.H. Griffin of Texas, Inc. against appellant/respondent Southwinds Express Construction, LLC. (hereinafter the “Claims“). D.H. Griffin asked the trial court to confirm the arbitration award under
- there was no agreement to arbitrate, the issue was not adversely determined in any proceeding to compel arbitration, and Southwinds objected at the arbitration that there was no agreement to arbitrate;
- the arbitrator exceeded her power by deciding the Claims because the parties had not agreed to arbitrate them;
- the award is tainted by manifest disregard of law and gross mistake in applying the law; and
- by failing to mediate the Claims, D.H. Griffin failed to fulfill a condition precedent to any obligation of Southwinds to arbitrate the Claims, thus precluding confirmation of the arbitration award.
Significantly, no party sought to compel or stay arbitration of the Claims. If the trial court had compelled arbitration or denied a stay of arbitration, this court could review either of these rulings on appeal, and would not be limited to the
because no party asked to compel or stay arbitration, the only grounds upon which Southwinds could obtain vacatur of the arbitration award are those listed in
Southwinds sought vacatur on the grounds that the award is tainted by manifest disregard of law and gross mistake in applying the law. Southwinds also sought vacatur on the ground that by failing to mediate the claims D.H. Griffin failed to fulfill a condition precedent to any obligation of Southwinds to arbitrate the Claims. Because none of these grounds is listed in
The trial court did not err in determining that the Claims fall within the scope of the parties’ arbitration agreement.
In paragraph 3 of the Subcontractor Agreement of September 26, 2013 (the “Agreement“), D.H. Griffin and Southwinds agree as follows:
In the event that a claim is not resolved through the negotiations of the parties, claim resolution will be resolved through mediation unless, in the sole discretion of [D.H. Griffin], [D.H. Griffin] believes mediation would be a useless exercise in which case [D.H. Griffin], unilaterally, may escalate the claims process to binding arbitration at any time. If mediation fails, both parties agree that the claim will be resolved pursuant to binding arbitration. Any mediation or arbitration will be conducted under the rules of the American Arbitration Association‘s (“AAA“) Construction Industry Dispute Resolution Procedures (including Mediation and Arbitration Rules) in effect at the time of the execution of this Agreement; provided, however, that where there is a conflict, if any, between those rules and this Agreement, this Agreement governs.
On appeal, Southwinds asserts that the trial court erred in confirming the award and denying Southwinds’ motion to vacate based on the argument that there was no agreement to arbitrate because the Claims do not fall within the scope of this arbitration agreement. As the party seeking to vacate the arbitration award, Southwinds had the burden of presenting a record establishing that (1) there was no agreement to arbitrate because the Claims were outside the scope of the arbitration agreement; (2) this issue was not adversely determined in a motion to compel or stay arbitration; and (3) Southwinds did not participate in the arbitration without raising this objection.6 The record reflects that there was no motion to compel or stay arbitration, and that in its arbitration-pro-
To the extent the appellant argues that there was no arbitration agreement based on a failure to meditate, the appellant did not prove that it raised this objection in the arbitration.
On appeal, Southwinds also appears to assert that the trial court erred in confirming the award and denying vacatur based on an argument that there was no agreement to arbitrate because the parties have not mediated the Claims and claims that have not been mediated do not fall within the Arbitration Clause. As the party seeking to vacate the arbitration award, Southwinds was obliged to present a record establishing that (1) there was no agreement to arbitrate because the parties have not mediated the Claims and claims that have not been mediated do not fall within the Arbitration Clause; (2) this issue was not adversely determined in a motion to compel or stay arbitration; and (3) Southwinds did not participate in the arbitration without raising this objection.8 Southwinds submitted its answer in the arbitration proceeding, but nothing in that answer raises this objection. Our record does not contain evidence showing that Southwinds voiced this complaint in the arbitration proceeding. Because Southwinds failed to prove in the trial court that it raised this objection in the arbitration proceeding, the trial court did not err in denying Southwinds‘s motion to vacate to the extent Southwinds asserted this ground of vacatur.9
To the extent the appellant argues that the arbitrator exceeded her power because the Claims are outside the scope of the Arbitration Clause, the trial court did not err in rejecting this argument.
It may be presumed for the sake of argument, that an arbitrator exceeds her powers within the meaning of
not been mediated do not fall within the Arbitration Agreement, Southwinds failed to prove that it raised this objection in the arbitration, as required by statute, and the trial court did not err in denying Southwinds‘s motion to vacate to the extent Southwinds asserted this ground of vacatur.13
This court need not address whether it is for the courts or the arbitrator to decide issues as to Southwinds‘s arguments that mediation is a condition precedent to arbitration.
On appeal, Southwinds asserts generally that, under the Agreement, mediation is a condition precedent to arbitration. Southwinds also argues that the clause in the Agreement granting D.H. Griffin, but not Southwinds, a unilateral opt-out of the Agreement‘s requirement of mediation before arbitration would render the mediation requirement illusory and must be stricken from the Agreement.14 Southwinds argues that, with the clause stricken, the parties agreed to arbitrate only the claims that were not successfully mediated. And, Southwinds asserts, because the parties have not mediated the Claims, there is no agreement to arbitrate the Claims. Under the analysis stated above, this court may affirm the trial court‘s judgment without addressing the merits of these arguments and without addressing whether it is for the arbitrator or the courts to decide
Even if this court needed to address whether it is for the courts or the arbitrator to decide the condition-precedent issues, the better course would be to address these issues based on section 171.088 rather than cases in which the court reviews a motion to compel or stay arbitration.
If this court had to address this question, a sounder option would be to rely upon
Instead of resolving these issues under the
In addition, a review of the majority‘s cited cases reveals considerable conflict and uncertainty among courts as to the analysis of purported conditions precedent to arbitration. In many of these cases the courts do not discuss the specific language of the agreement regarding the alleged condition precedent.19 And, many of the courts fail to specify whether courts should analyze cases in which the parties unambiguously agree to arbitrate only claims unresolved by a pre-arbitration dispute-resolution procedure differently that they analyze cases in which there is an unequivocal agreement to arbitrate and then a separate, general statement that the parties will seek to resolve a dispute by such a procedure before arbitration.20 Some cases indicate that, at the motion-to-compel-or-stay-arbitration stage, courts never determine whether an alleged condition precedent, such as meditation, has been satisfied and that the arbitrators determine all such issues.21 Some cases indicate that, at the
Notes
More than a half-century ago, in John Wiley & Sons, the Supreme Court of the United States held that it was for the arbitrator to decide whether the parties completed the grievance procedure required before arbitration, concluding that, though the grievance procedure was a procedural matter, this issue grew out of the parties’ dispute and bore on its final disposition.23 The high court then made a statement not necessary to its holding as to when this type of issue might be determined by the court.24 Nearly four decades later, in Howsam, the Supreme Court articulated a legal standard for determining which issues should be decided by the
court and which issues should be decided by the arbitrators, based on a determination as to whether the issue was one of substantive arbitrability or procedural arbitrability.25 The Howsam court cited John Wiley & Sons for its holding but did not cite the John Wiley & Sons dictum. That dictum is inconsistent with the legal standard articulated in Howsam.26 Likewise, neither the BG Group case from the United States Supreme Court nor the Supreme Court of Texas cases following Howsam and BG Group mention the John Wiley & Sons dictum.27 Nonetheless, some courts of appeals have concluded that the John Wiley & Sons dictum creates a narrow exception to a general rule that the arbitrators decided procedural matters, such as the requirement of other dispute-resolution matters.28 Though the majority concludes otherwise, this court in Igloo did not follow
In addition, in In re U.S. Home Corp., the Supreme Court of Texas determined that it could decide whether mediation was a condition precedent to arbitration that had not been satisfied such that the parties had no duty to arbitrate, without relying on any alleged exception under John Wiley & Sons, thus raising an issue as to the viability of this court‘s analysis in cases such as Valero and Omoruyi, in which this court either indicates that the arbitrators always should determine this issue or almost always should determine this issue subject to a narrow exception based on the John Wiley & Sons dictum.31
Today, the majority wades into these troubled waters. The better course would be to decide the appeal under the vacatur analysis expounded above, without relying upon cases in which the court reviews a motion to compel or stay arbitration.
Conclusion
For the reasons stated above, I respectfully concur in the court‘s judgment but I respectfully decline to join the majority‘s opinion.
WILLIAM J. BOYCE
JUSTICE
