Siluria (Assignment for the Benefit of Creditors), LLC v. Lummus Technology LLC
09-23-00127-CV
Tex. App.Mar 20, 2025Background
- The case involved a dispute over entitlement to a $1.5 million escrowed “holdback contingency” after Lummus Technology LLC purchased assets from Siluria (Assignment for the Benefit of Creditors), LLC.
- The “demonstration unit” at issue was set up at Braskem America, Inc.’s La Porte, Texas, facility; the holdback was to be paid to Siluria if certain contingencies were met under the Escrow Agreement.
- The contingencies were: (1) Lummus securing a lease with Braskem to operate the demonstration unit; or (2) if, by six months after closing, Lummus had not “begun removing” the demonstration unit from Braskem’s facility.
- Lummus did not secure the lease but removed certain assets (computers, tools, parts) from the site before the six-month deadline, and claimed to have “begun removal.”
- Siluria argued that “begin removing” required dismantling the entire large structure at the site, while Lummus argued the phrase included removal of essential operating components.
- A jury found for Lummus; the trial court awarded Lummus the escrow fund and attorney’s fees. Siluria appealed, challenging contract interpretation, evidentiary sufficiency, and the attorney fee award.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Was the contract ambiguous or unambiguous? | Agreement unambiguous; limiting “demonstration unit” to 4-story structure; only full structural removal counts. | Undefined terms get ordinary meaning; “demonstration unit” includes all assets necessary to operate the unit; removing key parts counts as beginning removal. | Agreement unambiguous; undefined terms given ordinary meaning; Lummus’s interpretation controls. |
| Submission of contract interpretation to jury | Legal question for court, jury charge immaterial. | Waived error by not objecting to charge. | Submission was error but harmless since jury found as court should have. |
| Factual sufficiency of evidence | Lummus did not truly begin “removing” demo unit before deadline. | Removal of computers, catalysts, and contacting contractors was beginning removal. | Sufficient evidence supported jury’s finding for Lummus. |
| Attorney’s fees – segregation/availability | Lummus failed to segregate fees; not entitled to fees as LLC for breach of contract. | Claims were intertwined; detailed affidavits submitted; allowed under DJA. | No abuse of discretion; fees were properly awarded and reasonably reduced. |
Key Cases Cited
- State Farm Lloyds v. Page, 315 S.W.3d 525 (Tex. 2010) (ambiguity in contract provisions is a question of law)
- Mosaic Baybrook One, L.P. v. Simien, 674 S.W.3d 234 (Tex. 2023) (plain/ordinary meaning governs undefined contract terms)
- Board of Regents of Tex. Univ. Sys. v. IDEXX Laboratories, Inc., 691 S.W.3d 438 (Tex. 2024) (ambiguity only if multiple reasonable interpretations persist after full examination)
- ConocoPhillips Co. v. Koopmann, 547 S.W.3d 858 (Tex. 2018) (ambiguity requires two reasonable interpretations)
- Barrow-Shaver Res. Co. v. Carrizo Oil & Gas, Inc., 590 S.W.3d 471 (Tex. 2019) (objective intent/contract interpretation principles prevail)
- Tony Gullo Motors I, L.P. v. Chapa, 212 S.W.3d 299 (Tex. 2006) (intertwined claims and attorney’s fee segregation)
