History
  • No items yet
midpage
Sierra Club v. Federal Energy Regulatory Commission
867 F.3d 1357
| D.C. Cir. | 2017
Read the full case

Background

  • FERC approved certificates under NGA §7 for three linked pipelines (Sabal Trail, Hillabee Expansion, Florida Southeast Connection) to deliver ~1.1 billion cubic feet/day to meet Florida utilities’ demand; construction began before rehearing denial.
  • Petitioners: Sierra Club (environmental groups) and Georgia landowners (GBA Associates, Isaacs) challenged FERC’s EIS as inadequate under NEPA and raised rate-setting and procedural claims.
  • FERC prepared a single EIS, held public comment, and adopted mitigation/route adjustments (including compressor relocation) but did not quantify downstream greenhouse-gas (GHG) emissions from burning transported gas.
  • The court considered standing, severability of the unified certificate order, and whether FERC must analyze indirect (downstream) GHG emissions and environmental-justice/cumulative impacts.
  • Holding (majority): remand for a conforming EIS because FERC failed to quantify or adequately explain inability to quantify reasonably foreseeable downstream power-plant GHG emissions; other NEPA, procedural, and rate-setting challenges largely rejected.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether petitioners have standing and whether the Certificate Order is severable Sierra Club and landowners alleged concrete environmental and property injuries tied to Sabal Trail; sought vacatur of whole order Respondents argued limited standing re: specific segments and that portions are severable Court: petitioners have standing; Order not severable because FERC treated project as single integrated proposal — whole order review allowed
Adequacy of environmental-justice and cumulative-impact analysis in EIS Sierra Club: EIS failed to analyze disproportionate impacts and cumulative pollution burden (e.g., Dougherty County) FERC: conducted EJ analysis, compared alternatives, considered relocation and mitigation, projected pollutant levels below standards Held: FERC’s EJ and cumulative-impact discussion met NEPA’s rule-of-reason; no reversal on EJ claims
Whether FERC had to analyze/quantify downstream GHG emissions from power plants burning transported gas Sierra Club: downstream combustion emissions are reasonably foreseeable and legally relevant; EIS should quantify emissions (or explain why not) and assess significance Pipeline developers/FERC: downstream emissions are not legally attributable to FERC (citing Public Citizen/Freeport); uncertain and speculative to quantify Held: Majority — downstream GHG emissions are reasonably foreseeable and FERC had authority to weigh them; EIS must quantify or explain why quantification is infeasible; remand required. (Concurring/dissent would have denied review on this point because Florida siting authority breaks causal chain.)
Validity of FERC’s use of a hypothetical capital structure in initial rate determination Sierra Club: rejecting actual proposed structure and allowing a hypothetical one to justify a high ROE is improper FERC: may use hypothetical capital structure to align risk/reward and protect consumers; similar precedent exists Held: FERC’s use of a hypothetical 50/50 capital structure to justify ROE was not arbitrary or capricious on the arguments presented; rate challenge denied

Key Cases Cited

  • Department of Transportation v. Public Citizen, 541 U.S. 752 (2004) (NEPA causation/proximate-cause principle limiting required analysis where agency cannot prevent downstream effect)
  • Balt. Gas & Elec. Co. v. Nat. Res. Def. Council, 462 U.S. 87 (1983) (NEPA requires agencies to take a "hard look" and disclose environmental effects)
  • Sierra Club v. FERC (Freeport), 827 F.3d 36 (D.C. Cir. 2016) (FERC need not analyze downstream export emissions when DOE had sole licensing authority)
  • EarthReports, Inc. v. FERC, 828 F.3d 949 (D.C. Cir. 2016) (similar to Freeport on FERC’s NEPA obligations regarding LNG exports)
  • WildEarth Guardians v. Jewell, 738 F.3d 298 (D.C. Cir. 2013) (NEPA’s requirements for reasonable forecasting and use of emission estimates as proxies)
  • Nevada v. Dep’t of Energy, 457 F.3d 78 (D.C. Cir. 2006) (NEPA’s rule-of-reason; courts should not "flyspeck" EIS)
  • Del. Riverkeeper Network v. FERC, 753 F.3d 1304 (D.C. Cir. 2014) (scope of NEPA "hard look" and forecasting)
  • Nat’l Consumers Util. Comm’n v. FERC, 42 F.3d 659 (D.C. Cir. 1994) (rate-setting principles; use of capital structure in FERC ratemaking)
  • Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (arbitrary-and-capricious standard for agency decisionmaking)
Read the full case

Case Details

Case Name: Sierra Club v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Aug 22, 2017
Citation: 867 F.3d 1357
Docket Number: 16-1329 Consolidated with 16-1387
Court Abbreviation: D.C. Cir.