Schneider Elect. Build. Critical Systems v. Western Surety Co.
0020/15
| Md. Ct. Spec. App. | Nov 30, 2016Background
- Schneider Electric and NCS executed a Master Subcontract Agreement (MSA) with a mandatory arbitration clause for disputes between them; future subcontracts would incorporate the MSA.
- Schneider and NCS entered a subcontract for work at Aberdeen Proving Ground that incorporated the MSA; subcontract required a 100% performance bond from NCS.
- Western Surety issued an AIA A312 performance bond naming Schneider as obligee; the bond incorporated the subcontract (and thus the MSA) by reference and bound NCS and Western “jointly and severally” for performance of the “Construction Contract.”
- NCS stopped work and Schneider terminated the subcontract for cause; Schneider sought arbitration against NCS, later amending to add Western as a co-respondent on the theory the bond incorporated the arbitration clause.
- Western sued in state court to stay arbitration and for declaratory relief; the Harford County circuit court granted partial summary judgment holding Western was not bound to arbitrate under either federal or state law.
- The Court of Special Appeals affirmed: federal/state arbitration statutes do not change that state contract law governs whether a non-signatory surety is bound, and the bond’s language did not evidence intent to bind Western to the MSA arbitration clause.
Issues
| Issue | Plaintiff's Argument (Schneider) | Defendant's Argument (Western) | Held |
|---|---|---|---|
| Whether federal or state law governs whether a non‑signatory can be bound to arbitrate | FAA applies and presumption in favor of arbitration supports binding Western because bond incorporated the subcontract/MSA | State contract law governs formation/enforceability of arbitration agreements; FAA doesn’t displace that | State contract law governs whether a non‑signatory is bound (consistent with Supreme Court precedents) |
| Whether incorporation-by-reference of the subcontract/MSA into the bond binds Western to the MSA arbitration clause | Incorporation by reference of the subcontract (which incorporates the MSA) into the bond makes the arbitration clause applicable to Western | Mere incorporation to define the primary obligation does not alone make the incorporated contract an agreement between different parties | Incorporation by reference alone did not bind Western to arbitrate; no clear intent to make the MSA a contract between Western and Schneider |
| Whether the bond’s “jointly and severally” promise to ensure “performance of the Construction Contract” obligates Western to arbitrate | “Jointly and severally” language obligates Western to the Construction Contract’s terms, including arbitration | “Performance” means completion of work (NCS’s construction obligations); arbitration is an enforcement mechanism, not a performance duty | “Performance” in the bond refers to the contractor’s work; joint-and-several clause did not evidence assent by Western to arbitrate |
| Whether the bond’s forum/limitations clause requires judicial resolution and precludes compelling Western to arbitrate | The arbitration clause governs disputes arising from the Construction Contract and should be enforced against the surety | Bond expressly provides for court actions and statute-of-limitations language; enforcing arbitration would read out that judicial remedy | The bond’s paragraph providing for court proceedings and time limits demonstrates intent to allow judicial suits; compelling arbitration would render those provisions meaningless |
Key Cases Cited
- Perry v. Thomas, 482 U.S. 483 (Supreme Court) (state law governs defenses to arbitration’s enforceability)
- Arthur Andersen LLP v. Carlisle, 556 U.S. 624 (Supreme Court) (whether non‑signatory may be bound is resolved by state contract law principles)
- Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1 (Supreme Court) (principles on abstention and parallel proceedings)
- Scarlett Harbor Associates Ltd. P’ship v. Hartford Accident & Indem. Co. (Scarlett Harbor I), 109 Md. App. 217 (Md. Ct. Spec. App.) (incorporation by reference into a bond does not automatically bind surety to arbitration; contract should be construed to give effect to all provisions)
- Scarlett Harbor Associates Ltd. P’ship v. Hartford Accident & Indem. Co. (Scarlett Harbor II), 346 Md. 122 (Md.) (affirming Scarlett Harbor I)
- AgGrow Oils, LLC v. Nat. Union Fire Ins. Co., 242 F.3d 777 (8th Cir.) (applies state contract principles to decide whether incorporation binds surety to arbitrate)
- Liberty Mut. Ins. Co. v. Mandaree Pub. Sch. Dist. #36, 503 F.3d 709 (8th Cir.) (similar application of state law; incorporation alone did not bind surety to arbitrate)
MOTION TO DISMISS DENIED. JUDGMENT OF THE CIRCUIT COURT FOR HARFORD COUNTY AFFIRMED. CASE REMANDED.
