History
  • No items yet
midpage
Sacramento Municipal Utility District v. United States
130 Fed. Cl. 735
Fed. Cl.
2017
Read the full case

Background

  • SMUD entered a Standard Contract with DOE on June 14, 1983, under the NWPA; DOE was required to begin accepting SMUD’s spent nuclear fuel (SNF) and high-level waste (HLW) by January 31, 1998, but never did.
  • Prior litigation established DOE’s failure to begin acceptance by 1998 constituted a partial breach; multiple runs of litigation produced awards for mitigation costs covering successive time periods (1992–2003; 2004–2009).
  • SMUD filed the present suit (No. 15-577C) seeking mitigation damages for costs incurred from January 1, 2010 through June 30, 2015 attributable to DOE’s continuing partial breach.
  • At trial SMUD sought $29.55 million; the government contested about $7.04 million of that amount, raising issues of causation, allocation between nuclear and non‑nuclear functions, and offsets for insurance refunds.
  • The court compared the actual (breach) world to a hypothetical non‑breach world (but‑for DOE performance) and awarded SMUD $28,867,161 for mitigation costs from 2010–June 30, 2015, after allowing a $682,397 offset for insurance refunds.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Entitlement/jurisdiction and standing SMUD is in privity under the Standard Contract and seeks contract damages for DOE’s ongoing breach Government did not dispute privity or jurisdiction Court has Tucker Act jurisdiction and SMUD has standing
Causation for site/building O&M (T&R and PAP) Costs to maintain/operate T&R and PAP buildings are caused by presence of SNF and would not exist in non‑breach world Buildings also serve non‑nuclear uses; SMUD failed to prove what costs would differ in non‑breach world Court found credible testimony that buildings housed only nuclear staff/security and awarded $3,685,112
Site consolidation, PAP water/septic upgrades, ISFSI generator planning Consolidation and upgrades were done to reduce operating costs tied to onsite nuclear staff; would not have been done if SNF removed These improvements support non‑nuclear infrastructure and SMUD didn’t isolate non‑breach costs Court found consolidation and upgrades attributable to SNF and awarded $698,255
HVAC/carpet for PAP building Replacing failing HVAC and carpeting necessary for occupied nuclear staff and records vault; would not have been done in non‑breach world Improvements benefit non‑nuclear uses; SMUD failed to prove non‑breach baseline Court awarded $481,207 (HVAC + carpet)
ISFSI backup generator and electrical upgrades NRC requires backup power for ISFSI; purchase and installation and related electrical work solely to support SNF storage Some electrical work touches buildings with non‑nuclear functions; SMUD didn’t separate costs against non‑breach world Court accepted that generator/switchgear and relevant electrical upgrades were SNF‑driven and awarded $573,214
IOSB operation/repair and handling‑equipment refurbishment IOSB and contaminated handling equipment must remain onsite while SNF is present; necessary for potential canister retrieval and relicensing SMUD previously removed some wastes and moved equipment later; government argues prior award circumstances differ Court found DOE breach was but‑for cause and mitigation was reasonable; awarded $980,500
ANI insurance brokerage fees and premiums / offsets Brokerage fees to obtain ANI insurance are consequential and recoverable; uncertainty in amount acceptable — imprecision falls on breaching party Broker testimony lacked contemporaneous personal knowledge; government seeks offset for refunds received during claim period Court allowed $86,010 for brokerage fees and applied a $682,397 offset for ANI refunds received 2010–2015

Key Cases Cited

  • Maine Yankee Atomic Power Co. v. United States, 225 F.3d 1336 (Fed. Cir. 2000) (Standard Contract required DOE to begin disposal by Jan. 31, 1998; failure is breach)
  • Indiana Michigan Power Co. v. United States, 422 F.3d 1369 (Fed. Cir. 2005) (successive damages suits structure and limits on future offsets)
  • Yankee Atomic Elec. Co. v. United States, 536 F.3d 1268 (Fed. Cir. 2008) (comparison of breach and non‑breach worlds for causation/damages)
  • Southern Nuclear Operating Co. v. United States, 637 F.3d 1297 (Fed. Cir. 2011) (plaintiff must present hypothetical model of but‑for costs and government may identify avoided costs)
  • Energy Northwest v. United States, 641 F.3d 1300 (Fed. Cir. 2011) (costs incurred in non‑breach world are not recoverable; burden on plaintiff to model non‑breach costs)
  • Bluebonnet Sav. Bank, F.S.B. v. United States, 339 F.3d 1341 (Fed. Cir. 2003) (damages should not put injured party in a better position than full performance; reasonable approximation standard)
  • LaSalle Talman Bank v. United States, 317 F.3d 1363 (Fed. Cir. 2003) (where damages are hard to estimate, burden of imprecision does not fall on the innocent party)
  • Winstar Corp. v. United States, 64 F.3d 1531 (Fed. Cir. 1995) (failure to perform when due is breach)
Read the full case

Case Details

Case Name: Sacramento Municipal Utility District v. United States
Court Name: United States Court of Federal Claims
Date Published: Feb 28, 2017
Citation: 130 Fed. Cl. 735
Docket Number: 15-577C
Court Abbreviation: Fed. Cl.